RE: SDP2008 -00003 Crown BMW Retail Parts & Service Building- Preliminary
Tax Map 78, Parcels 15B & 15131
Dear Mr. Garcia
The Albemarle County Planning Commission, at its meeting on, July 29, 2008 approved the modification
of Section 4.2.3.2 to allow disturbance of critical slopes by a vote of 6:0.
The Department of Community Development hereby grants administrative approval to the above
referenced site plan.
The approval of the preliminary site plan is valid for (1) one year in accordance with Section 32.4.3.1 of
Chapter 18 of the Albemarle County Code. Therefore, the preliminary approval shall expire on August
12, 2009. If the preliminary site plan approval expires, a new application must be filed and processed.
Please address all of the requirements and conditions listed below and submit eight (8) tentative plan
copies to the Department of Community Development. This letter must be submitted with the tentative
plans, as a checklist, to document that you have addressed all requirements or conditions, or the tentative
plan will be denied.
Erosion and Sediment Control, BMP Stormwater Management, and road plans with the associated
applications and fees must also be submitted with the eight (8) tentative Plans.
Once the tentative plan is submitted and reviewed you will receive comments from all
departments /divisions /agencies that have made comment on the tentative plan. Any further
responses must be made directly to each department/division /agency that has further comment.
After all aforementioned departments/divisions/agencies have granted a tentative approval, you
must verify with the Planner that you may submit the final mylars (2 sets), two paper copies, the
final site plan application, and final site plan fee to the Department of Community Development.
Signing of the plans will occur within one week once it is determined that the final site plan mylars
reflect all tentative approvals.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section 32.6), in
addition to the following conditions.
The Department of Community Development shall not accept submittal of the final site plan for signature
until tentative approvals for the following conditions have been obtained:
1. The Final Site Plan shall meet the requirements of Chapter 18, Section 32.6 of the
Albemarle County Code
Current Development Planner approval to include:
a. Landscape plan
b. Lighting plan
C. All necessary easements for access.
d. Plat combining Tax Map 78, Parcels 15B and 15B1
3. Current Development Engineer approval to include:
a. Provision of minimum 100 feet of sight distance for all travelways.
b. All necessary easements for construction and maintenance of walls, slopes and
drainage improvements.
114. Albemarle County Building Official approval.
5. Albemarle County Service Authority Approval to include:
a. Water and Sewer plans.
b. Agreements for activity within existing or proposed utility easments and on
Service Authority property.
6. Fire and Rescue Division approval to include:
a. Adequacy of fire flow.
b. Location of Fire Hydrants.
7. Architectural Review Board approval.
8. Virginia Department of Transportation approval of entrances.
If you should have any questions or comments regarding the above noted action, please do not hesitate to
contact me at (434) 296 -5832.
Sincerely,
William D. Fritz, AICP
Chief of Current Development
Zoning and Current Development Division
Cc. Mike Craddock
3633 -C West Wendover Ave
Greensboro Nc 27407
Astar Asb Va2 Llc C/O Eproperty Tax / Dept 114
P O Box 4900
Scottsdale Az 85261
File: SDP -08 -3