HomeMy WebLinkAboutSDP200800155 Approval - County 2008-08-04f
R( l'At
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
August 4, 2008
Julia Skare
Draper Aden Associates
700 Harris Street, Suite E
Charlottesville, VA 22903
via email: jskare @daa.com
RE: SDP2008 -78 Restoration of Montalto - Preliminary
Dear Ms. Skare:
The Department of Community Development hereby grants administrative approval to the above
referenced site plan.
The approval of the preliminary site plan is valid for (1) one year in accordance with Section 32.4.3.1 of
Chapter 18 of the Albemarle County Code. Therefore, the preliminary approval shall expire on August 4,
2009. If the preliminary site plan approval expires, a new application must be filed and processed.
Please address all of the requirements and conditions listed below and submit eight (8) tentative plan
copies to the Department of Community Development. This letter must be submitted with the tentative
plans, as a checklist, to document that you have addressed all requirements or conditions, or the tentative
plan will be denied.
Erosion and Sediment Control, BMP Stormwater Management, and road plans with the associated
applications and fees must also be submitted with the eight (8) tentative Plans.
Once the tentative plan is submitted and reviewed you will receive comments from all
departments /divisions/agencies that have made comment on the tentative plan. Any further
responses must be made directly to each department/division/agency that has further comment.
After all aforementioned departments /divisions/agencies have granted a tentative approval, you
must verify with the Planner that you may submit the final mylars (2 sets), two paper copies, the
final site plan application, and final site plan fee to the Department of Community Development.
Signing of the plans will occur within one week once it is determined that the final site plan mylars
reflect all tentative approvals.
The final site plan will be subject to all final site plan requirements (Zoning Ordinance Section 32.6), in
addition to the following conditions.
The Department of Community Development shall not accept submittal of the final site plan for signature
until tentative approvals for the following conditions have been obtained:
Zoning & Current Development approval to include:
U application items as specified in Section 18 -32.6
Eneineering annroval to include:
L7 All applicable items as specified in the Design Standards Manual, Section 902 B.
Please see attached memo from Phil Custer for final site plan information.
Please contact Phil Custer at 296 -5832 if you have questions or require additional information.
Fire & Rescue approval to include:
Verify adequate fire flow is available
Please contact James Barber at 296 -5833 if you have questions or require additional information. C ( /
Building Inspection Division approval to include:
ERearrange the barrier -free parking spaces in the Court Yard of the Main House so that
one of them is van - accessible (min. 8' wide parking space, with min. 8' wide adjacent
access aisle)
Please contact Jay Schlothauer at 296 -5836 if you have questions or require additional information.
Sincerely, 4 j
Summer Frederick Otc 1 l
Zoning & Current Development d
cf 9
2