HomeMy WebLinkAboutSUB201200057 Bond Reduction 2016-05-05 (2)COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
5 May 2016
Alan Taylor
alan@riverbenddev.com
Re: Bond reduction request for Foothill Crossing Phase H
Thank you for the documentation regarding completion of Foothill Crossing Phase H. This bond is
currently $1,143,010.00. The Bond can now be reduced to $228,602.00 (the minimum 20% of original
bond amount). The total bond can be released upon receipt of evidence of road acceptance into the
VDOT system and an accepted sign maintenance agreement.
Please contact me if you have questions.
Sincerely,
Matt Wentland, PE
Civil Engineer H
Copy: Ana Kilmer, Leslie Tate, File
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
5 May 2016
Alan Taylor
alan@riverbenddev.com
Re: Bond reduction request for Foothill Crossing Phase III
Thank you for the documentation regarding completion of Foothill Crossing Phase III. This bond is
currently $379,250.00. The Bond can now be reduced to $75,850.00 (the minimum 20% of original
bond amount). The total bond can be released upon receipt of evidence of road acceptance into the
VDOT system, the completion of the intersection at Phase IV, and an accepted sign maintenance
agreement.
Please contact me if you have questions.
Sincerely,
Matt Wentland, PE
Civil Engineer II
Copy: Ana Kilmer, Leslie Tate, File