SUB201400197
SubApplication Type:
Hyland Ridge, Phase 2 & 4 - Road Plans
New Public Use Road Plan
Date Completed:03/17/2015
Reviewer:Shelly Plaster VDOT
Review Status:Approved
Reviews Comments:
Division:
Date Completed:04/22/2015
Reviewer:Max Greene Engineering
Review Status:No Objection
Reviews Comments:Road Bond estimate for Phase 4 was removed from bond per developers request. Phase 4 road
bond will not be posted at this time. New bond request form will be required for Phase 4 road bond
and plat approval.
Division:
Date Completed:12/12/2014
Reviewer:Max Greene Engineering
Review Status:See Recommendations
Reviews Comments:Please adequately address the VDOT comments/requirements. No additional comments or
conditions at this time. VDOT approval is required prior to bonding of road.
County Engineer has required a mitigation plan approval prior to final road plan approval.
Division:
Date Completed:12/12/2014
Reviewer:Shelly Plaster VDOT
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:12/09/2014
Reviewer:Max Greene Engineering
Review Status:See Recommendations
Reviews Comments:12/9/14 road plan has not been reviewed at this time. Bond request form will be placed on hold until
road plan approval.
Division:
Date Completed:03/24/2015
Reviewer:Max Greene Engineering
Review Status:Administrative Approval
Reviews Comments:
Division:
Date Completed:07/27/2015
Reviewer:Max Greene Engineering
Review Status:No Objection
Reviews Comments:
Division:
Page: 1 of 1 County of Albemarle Printed On: May 09, 2016