HomeMy WebLinkAboutWPO201500033 Review Comments 2015-10-09Short Review Comments Report for:
WPO201500033
SubApplication Type:
Hillbrook - VSMP
Stormwater Management/BMP Plan
Erosion and Sediment Control Plan
Stream Buffer Mitigation Plan
Date Completed:06/26/2015
Reviewer:Justin Deel Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:08/20/2015
Reviewer:Justin Deel Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:09/23/2015
Reviewer:Justin Deel Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:10/09/2015
Reviewer:Justin Deel Engineering
Review Status:Approved
Reviews Comments:
Division:
Date Completed:10/15/2015
Reviewer:Justin Deel Engineering
Review Status:See Recommendations
Reviews Comments:SWM and ESC bond estimates sent to Ana Kilmer, 10/15/2015.
Division:
Date Completed:12/07/2015
Reviewer:Ana Kilmer CommDev-Central Ops
Review Status:Approved
Reviews Comments:11/17/2015 swa submitted - waiting for bonds to route agreement for approval
12/2/2015 - swa approved by cao
12/4/2015 - swa signed by CE
12/7/2015 - swa agreement recorded at clerks office, deed book 4702, page 492
Division:
Page: 1 of 1 County of Albemarle Printed On: June 21, 2016
)
COMMONWEALTH of VIRGINIA
DEPARTMENT OF ENVIRONMENTAL QUALITY
Street address: 629 East Main Street,Richmond,Virginia 23219
Molly Joseph Ward Mailing address:P.O.Box 1105,Richmond,Virginia 23218 David K.Paylor
Secretary of Natural Resources www.deq.virginia.gov Director
(804)698-4000
1-800-592-5482
December 15, 2015
Hilltop Partners LLC
PO Box 645
Charlottesville, VA 22902
jess@reddirtdev.com
RE: Coverage under the VPDES Construction General Permit(VAR10)
General Permit No. VAR10H633
Hillbrook
Residential
Albemarle
Dear Permittee:
DEQ has reviewed your Registration Statement received on May 29, 2015 and determined that the proposed
land-disturbing activity is covered under the General VPDES Permit for Discharges of Stormwater from
Construction Activities (VAR10). The effective date of your coverage under this general permit is July 1, 2014 or
the date of this letter,whichever is later.
A copy of the general permit can be obtained from DEQ's webpage at the following location:
http://www.deq.virginia.gov/Portals/O/DEQ/Water/Publications/CGP2014.pdf.
The general permit contains the applicable Stormwater Pollution Prevention Plan (SWPPP) requirements and
other conditions of coverage. Please print the general permit and read it carefully as you will be responsible for
compliance with all permit conditions.
DEQ staff has determined that the proposed land-disturbing activity will discharge to a surface water identified
as impaired or for which a TMDL wasteload allocation has been established and approved prior to the term of the
general permit for (i) sediment or a sediment-related parameter or (ii) nutrients. Therefore, the following general
permit(Part 1.6.4)and SWPPP requirements (Part II.A.5) must be implemented for the land-disturbing activity:
• Permanent or temporary soil stabilization shall be applied to denuded areas within seven (7) days after
final grade is reached on any portion of the site;
• Nutrients (e.g., fertilizers) shall be applied in accordance with manufacturer's recommendations or an
approved nutrient management plan and shall not be applied during rainfall events;
• Inspections shall be conducted at a frequency of (i) at least once every four (4) business days or (ii) at
least once every(5) business days and no later than 48 hours following a measurable storm event. In the
event that a measurable storm event occurs when there are more than 48 hours between business days,
the inspection shall be conducted on the next business day; and
• Representative inspections used by utility line installation, pipeline construction, or other similar linear
construction activities shall inspect all outfalls.
The general permit will expire on June 30, 2019. The conditions of the general permit require that you submit
a new registration statement at least 90 days prior to that date if you wish to continue coverage under the general
Nose
permit, unless permission for a later date has been granted by the Board. Permission cannot be granted to
submit the registration statement after the expiration date of the general permit.
If you have any questions about this permit, please contact the DEQ Office of Stormwater Management at
ConstructionGP(a,deq.virginia.gov.
Sincerely,
91.04:61/1,e.4.74
Frederick K. Cunningham, Director
Office of Water Permits
2
Justin Deel
From: Lauren Gilroy<lauren@shimp-engineering.com>
Sent: Wednesday, October 07, 2015 1:52 PM
To: Justin Deel; Justin Shimp, P.E.
Subject: RE: Hillbrook VSMP
Attachments: 61-126-SP C4 (100715).pdf
Hi Justin,
Here is the utility plan sheet showing the new SWM lot. Please take a look and let us know if you think it will be ok.
Best,
Lauren
From:Justin Deel [mailto:jdeel@albemarle.org]
Sent:Tuesday, October 06, 2015 5:16 PM
To:Justin Shimp, P.E.<justin@shimp-engineering.com>; Lauren Gilroy<lauren@shimp-engineering.com>
Subject: Hillbrook VSMP
Justin,
In reviewing the final plat I have realized an oversight on my part with the VSMP review/approval.We cannot approve
stormwater facilities on home lots. Please call me tomorrow to discuss how we can resolve the fact that the detention
system is on lot 1. Glenn has informed me that we cannot bond this plan as it stands.
Justin Deel, EIT
Civil Engineer II
Department of Community Development
County of Albemarle, Virginia
434.296.5832 ext. 3565
1