Loading...
HomeMy WebLinkAboutWPO201600025 Approval - County 2016-06-24COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit plan review Project title: Mass Grading of General Industrial Office Project file number: WP0201600025 Plan preparer: Meridian Planning Group [tmiller@meridianwbe.com] Owner or rep.: DCF LLC [email] Plan received date: 4 April 2016 (Rev. 1) 7 June 2016 Date of comments: 26 April 2016 (Rev. 1) 24 June 2916 Reviewers: Max Greene County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is Approved. The rationale is given in the comments below. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. 1. The registration Statement and item #9 Certification will need to be signed prior to final VSMP approval. The documents can be left at the front counter for the owner to sign upon request. Certification will be signed prior to beginning the pre -construction meeting. If the responsible person is not willing to sign the certificate then the meeting will be adjourned until a responsible party is willing to sign the certification. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. Item appears to be adequately addressed at this time. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is approved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17-403. 1. Could not verify "A" hydrological soils in the area of this property. Please clarify the name and location of type "A" soils on the plan. This item was addressed via conversation with consultant. This SWM plan is for mass grading only. All existing hard scape is proposed to be removed with this plan. A new VSMP plan will be required prior to final site plan approval. Engineering Review Comments Page 2 of 3 D. Erosion and Sediment Control Plan (ESOP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is approved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Tree clearing is shown on the demolition plan without sediment control basin in place. The trees may be timbered without removing the tree stumps as in a true silviculture activity. However, the sediment control structures will need to be in place prior to tree stump removal and/or clearing the site for grading. Please show the sediment basin on the demolition plan with a note that the sediment basin will be constructed and approved prior to any additional land disturbance. No E&SC measures have been shown for tree removal/demolition plan. Therefore, no land disturbance will occur with the silviculture operation to remove the timber. E&SC measures will be properly installed and approved by the County VSMP Inspector prior to any land disturbance. Should the silviculture operation create any land disturbance then the project will be delayed while the E&SC measures are installed for approval. 2. Soil hydrologic designation does not appear to have an "A" type soil in the vicinity of this project. Please clarify locations of type "A" soils on this project. Item addressed. 3. A turbidity curtain may be required to protect the existing pond if sediment should be noticed due to site development. Item to be field determined by County VSMP Inspector. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process; After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. After bonding and agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Engineering Review Comments Page 3 of 3 Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; hiq2://www.albemarle.org/deptforyns.asl2?department--cdengno File: CDDE2_vsmp_Approval_Mass Grading of General Industrial Office _wpo201600025.doc