HomeMy WebLinkAboutWPO201600048 Approval - County 2016-07-26COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Project title:
Project file number:
Plan preparer:
Owner or rep.:
Plan received date:
Date of comments:
Reviewers:
VSMP Permit plan review
North Pointe Sanitary Sewer Extension
WP0201600048
Townes Site Engineering
Great Eastern Management
22 June 2016
26 July 2016
Max Greene
[bmitchell@cctownes. com]
[david@southern-classic.com]
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMPNESCP permit by issuing a project approval or denial. This project is
Approved. The rationale is given in the comments below. The VSMP application content
requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. This plan will be added to the on-site SWPPP. The existing DEQ Permit #VAR10C806 does not
appear to require modification at this time.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
The PPP portion of the SWPPP should have been addressed in the original document, but will be
updated with this plan..
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is approved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. This is a linear project and will be re -vegetated upon completion.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
This plan is a replacement for the expired WP0201200068 plan and is generally the same plan for the
erosion and sediment control of the project. Please see the "Process" for the next step in bonding this
proj ect.
Engineering Review Comments
Page 2 of 2
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled
with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a
joint VSMP and grading permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
hM2://www.albemarle.or�z/deptfonns.ap?department--cdena3Wo
File: CDDE1_vsrap_Approval_North Pointe Sanitary Sewer Extension_wpo201600048.doc