HomeMy WebLinkAboutSUB201400067 Approval - County 2016-08-02John Anderson
From: John Anderson
Sent: Tuesday, August 02, 2016 8:39 AM
To: 'Scott Collins'; 'Adam Long'
Cc: Frank Pohl; Max Greene; Matthew Wentland
Subject: SUB201400067 -Westlake Hills Phase II, III, & IV ROAD Plans -Approved
Attachments: VDOT-SUB-2014-00067 Westlake Hills phase II III IV Road Plans 2-11-15.pdf; RE:
Westlake Hills Subdivision Water and Sewer Bond; wpo201400031-west1ake hills-
memo-071814-Revl-revfinal.pdf
Scott,
Please accept this ROAD Plan Approval. All aspects of ROAD Plan review are complete, all elements of ROAD Plan
approved. CV is tortuous where this project is concerned.
This was my first review on joining Engineering, 7 -Apr, 2016. We received this plan 16 -Apr 2014. This may partially
explain erratic review performance. At any rate:
County View
Planning, 5/30/14 (Ellie Ray):
"—A condition of approval of the critical slope waiver granted during the preliminary plat process was an overlot grading
plan to the satisfaction of Engineering; has this condition been satisfied?
Some minor conflicts between street trees and utility laterals exist in a few places; these conflicts can be resolved in the
field."
ACSA, Approved by 13 -Apr, 2016
Collins may have more explicit ACSA Approval Date. CV [dialog box] comment:
"Placeholder Dates
ref. email, J. Lynn/ACSA to A. Kilmer (4/13/2016 8:49 AM); UTILITY bond estimate, phase 2 and 3 =$400,000.
ref. email, J. Lynn/ACSA to A. Kilmer (5/3/2016 1:23 PM); UTILITY bond estimate, phase 2 only =$245,000.
Assume ROAD /Utility plan approved by ACSA.
janderson2 8/2/2016 7:49 AM" —see Also, Attached
ACF&R, 9/26/14
"Based on plat dated 8/26/14
No comments or objections"
VDOT. 2/11/15. Attached
Comments adequately addressed.
Engineering, 10/13/14 —Also, Attached
"Defer to VDOT"
Additional ROAD Plan e -Approval to follow. Approval date is 2 -Aug 2016.
CV reflects ROAD Plan approval (or will, within minutes —need this email's time).
Engineering staff will be aware. Note: new teL #, below —please feel free to call.
-best,
John E. Anderson, PE
Senior Project Manager
Facilities & Environmental Services
Project Management Division
County of Albemarle
401 McIntire Road
Charlottesville, Virginia 22902-4596
(434) 872-4501 office; ext 4 or 9-3069
(434) 906-1506 mobile
(434) 972-4091 fax
Janderson2&albemarle. org