HomeMy WebLinkAboutWPO201500078 Review Comments WPO VSMP 2016-09-01Phone (434) 296-5832 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 VSMP Permit plan review Project: North Pointe Middle Entrance & Rt. 29 Improvements Plan preparer: Brian Mitchell, P.E., Mona Gabriel, P.E. Townes Site Engineering -9850 Lori Road, Suite 201 Chesterfield, VA 23832 [Mitchell@cctownes.com ] Owner or rep.: CWH Properties Limited Partnership, P.O. Box 5526 Charlottesville, VA 22905 Plan received date: 25 Sep 2015 (Rev. 1) 28 Dec 2015 (Rev. 2) 3 Aug 2016 Date of comments: 17 Nov 2015 (Also: 11/13/2015 10:28 AM email) (Rev. 1) 5 Jan 2016 (Rev. 2) 1 Sept 2016 Reviewer: John Anderson (Rev. 2) Matt Wentland Fax (434) 972-4126 Engineering has completed review of Application WP0201500078. County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is approved. The rationale is given in the comments below. The VSMP application content requirements can be found in County Code section 17-401. V S M P P l a n s (WP0201500078) A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. SWPPP — SWPPP —Revise SWPPP for Middle Entrance / Rt. 29 Improvements (discussed 11 -Nov). (Rev. 1) Partially addressed. Thank you for .PDFs sent 4 Jan. As follow-up: Please show grading for trap or basin measures required to contain wash waters, vehicle wash waters, concrete wash out, and any on-site fuel storage. Ref. Sec. 6.C. Table/Sources of Pollutants, 6.G.a./d. —Pollution Prevention Awareness. DEQ during periodic site inspections instructs on importance of an Exhibit showing these features. Please revise Exhibit to show: dumpster, portable sanitary (porta-john), fuel storage, if any. Areas with potential to contaminate runoff should drain to containment/trap. For example, silt fence downstream of porta-john. Concrete wash-out, dumpster draining to trapping device (lined, in case of concrete wash-out). On-site fuel storage: berm with 10ml liner sized to hold fuel volume + 2 yr. storm event. .PDF examples available. Exhibit is not intended as a detailed design but to show containment and locations which contractor is free to change. Exhibit is a construction aid and resource protection/inspection management tool. Sec. 6.E. —Provide Names of persons responsible for pollution prevention practices (Sec. 8 qualified personnel, for example). Sec. 6.F. —Recommend list state/local incident reporting telephone numbers: Engineering Review Comments Page 2 of 4 Emergency Contacts. Normal Working Hours DEQ Valley Regional Office 540-574-7800 Nights, Holidays & Weekends VA Dept. of Emergency Management 804-674-2400 24 Hour Reporting Service Local Contacts Albemarle County/Community Development (Normal Business) 434-296-5832 Local Fire Department 911 Local Police Department 911 Sec. 6.G. —Pollution Prevention Awareness. Items a - g outline procedures and prohibit discharge/spills without reference to frequency of training, or employee orientation to procedures/prohibitions. Provide brief detail that explains training frequency and PPP awareness training and orientation for personnel. Sec. 6.G.b. (Minor edit): "proper disposal in a manner to contact with stormwater" should read: "proper disposal in a manner to prevent contact with stormwater." Appendix C. —Appears unnecessary (No contents) Registration Statement —Please revise to list 20.37 Ac. Estimated Area to be disturbed. With subsequent sections of development (Sec. 1, for example), revise estimated Area to be disturbed to show cumulative area to be disturbed. There are fee implications when Area exceeds 50 Ac., or 100 Ac. Fees increase at these levels. (Rev.2) Addressed B. VSMP: SWPPP: Stormwater Management Plan (WP0201500078) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is approved. The stormwater management plan content requirements can be found in County Code section 17-403. 1. ARB Entrance Corridor requirements vs. SWM BMP design. [see C-lA, IL Entrance Corridor, 2.2] (Rev. 1) Addressed —Applicant response: "Ms. Falkenstein [Alb. Co.] believes that the ARB review for SWM 2 is not required until it is time to review one of the commercial buildings that will be installed upstream of SWM/BMP 2." 2. C -1A, IV, 4.3, E&S Control (b)/Post-construction SWM: Demonstrate design meets proffer condition: 80% annual average sediment removal rate as published by the Center for Watershed Protection in Article 64 of The Practice of Watershed Protection (2000 edition). (Rev. 1) Addressed. Applicant response: "A study has been prepared by Williamsburg Environmental Group, Inc, in April 2006 to evaluate the pre and post construction sediment rates for the North Pointe Development. The study shows that the development of the North Pointe Development including the associated SWM's could result in an estimated reduction in sediment delivered to the Rivanna from 794 tons/year to 146 tons/year (81.6% reduction). A copy of the Sediment Loading Estimates report dated April 2006 is provided in the letter of transmittal for your records." 3. Title p. Note —Remove Part II C technical criteria Note. This Title sheet statement requires clarification provided in 12 -Nov County email. (Rev. 1) Partially addressed. As minor follow-up: C-1 reference to email should read Albemarle County Community Development rather than Economic Development. (Rev. 2) Addressed 4. Title sheet —Revise 2.66 Project Area Acreage. (Rev. 1) Addressed. 5. Transfer ROAD PLAN Sheet 6 to VSMP. Also, please ensure 6" DIA Vert. Orifice Elev. =433.50', consistent with routings (discussed 11 -Nov). (Rev. 1) Addressed. 6. Show steep slopes on sheets C-3, C -3A, C -3B, C-4, C -4A, C-413 —welcome .PDF preview (discussed 1I - Nov). (Rev. 1) Addressed. 7. C -7A —11.17 Ac. CBPA image extends across Flat Branch, and up opposite bank, beyond E&S sheet LOD. Area picks up road inlets that will be treated by retention basin, but part of the shape of this 11.17 Ac. area, I do not understand, and hope to discuss later today. (Rev. 1) Addressed. 8. C-2 —Label Airport Acres Road. (Rev. 1) Addressed. Engineering Review Comments Page 3 of 4 9. Please provide Map of stream/wetland impacts covered by VWP Individual Permit Number 14-0364, issued 3 -Apr 2015. `Permitted impacts' referenced in Construction Narrative / Existing Site Conditions Note -C- 3B. (Rev. 1) Addressed. New 10. C-8, SWM/BMP Cross-section: L, 30" DIA barrel =47.69'. Routing L=82.3'. Revise for consistency; revise routings if necessary. (Rev. 2) Addressed 11. C-8, SWM/BMP Cross-section: Label slope, %, SWM 2, 30" DIA outfall pipe. (Rev. 2) Addressed 12. C-8, SWM/BMP Cross-section: Consider buoyancy. Provide concrete riser base, provide base dimensions. (Rev. 2) Addressed 13. C-8, SWM/BMP Cross-section: Revise profile to show Emergency Spillway Elev. 436.50 higher than primary spillway/riser rim Elev. 436.00. (Rev. 2) Addressed 14. C -8A: Str. 14 L =135.25' but L =137.57' in Drainage Structure Summary Table. Revise for consistency. (Rev. 2) Addressed 15. Note: With subsequent WPO submissions, Section 1, for example, use NOAA Atlas 14 point precipitation frequency estimates for Charlottesville, VA, 24 -hr event: 2 -yr =3.68"; 10 -yr =5.57". Link: http://hdsc.nws.noaa.,,gov/hdsc/pfds/pfds_m4p_cont.html?bkmrk=va (Rev. 2) Addressed C. VSMP: SWPPP: Erosion Control Plan (WPO201500078) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is approved. The erosion control plan content requirements can be found in County Code section 17-402. 1. Profiles/to scale -ST, SB (discussed 11 -Nov). (Rev. 1) Partially addressed. As follow-up: Compare C-5 silt trap 1, 2 (table) bottom/floor Elev. torp ofiles. Revise profiles/tables. Also: ST2 profile appears to indicate excavation > 4' Max. Revise such that (wet Vol. ) excavation <4'. [Note: silt trap #2: 1.0 x wet volume rqd. =1,899 cf, or < 2,148 cf wet Vol. Actual -1.25 multiplier conservative approach acknowledged] (Rev. 2) Addressed 2. Label LOD; plan view: sheets C -3A, C -3B, C-4, C -4A, C -4B + LOD Table for these sheets, to total 16.1 Ac. (Table required to facilitate tracking of LOD, relative to VAR10C806; MAP INDEX, LOD to increase). (Rev. 1) Partially addressed. As follow-up: On each sheet (listed above) that shows graphic LOD, please define acreage of area of disturbance ( =16.1 Ac). (Rev. 2) Addressed 3. C-2B/C-3 -Heavy demolition hatching obscures some labels (discussed 11 -Nov). (Rev. 1) Addressed. 4. C-3 -Southern Entrance Phase 1 Construction Entrance Notes: 3. Revise to read Airport Acres Road; 5. Recommend road stationing for 54" RCP and 15" CMP. (Rev. 1) Addressed. As follow-up: Revise Note 5. to reference road station 11+50 rather than station 12+50. (Rev. 2) Addressed 5. [11/13/2015 11:08 AM] #51 -Please label ST, SB floor dimensions (L x W), discussed 11 -Nov. (Rev. 1) Addressed. New 6. As discussed 4 Jan, slopes steeper than 3:1 must be permanently stabilized with landscaping vegetation hardier than grass (does not require mowing). Provide notes, labels, and detail to identify species and locations requiring vegetation hardier than grass, C -4B, C-8. Also, email: 1/4/2016 4:32 PM) (Rev. 2) Addressed 7. Add CIP to Legend, C-1 (Rev. 2) Addressed D. VSMP: Mitigation Plan The mitigation plan requirements can be found in County Code section 17-406 Stream buffer mitigation: Show stream buffer impacts/2:1 Mitigation required per Ch. 17, Article VI. [C- SA, IV, Stormwater Management & Stream Bed Conservation, 4.4] -briefly discussed, 11 -Nov. (Rev. 1) Addressed. Applicant response: "A stream buffer plan sheet has been added to the plan set which shows the County defined stream buffer in relation to the overall North Pointe Property. The majority of the property for the Engineering Review Comments Page 4 of 4 North Pointe development is wooded and therefore the mitigation is naturally met since there will be no place to plant new vegetation at the required 2:1 mitigation rate. Please see Stream Buffer Mitigation plan sheet C-9." Engineering plan review staff are available 2-4 PM on Thursdays if a meeting to discuss this review would be helpful. I am also available at 434.296-5832 —x3458 should you have any questions. Process: After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. This project holds a valid CGP/VPDES Permit: VAR10C806. After bonding and agreements are complete, the County can hold a pre -construction conference. Applicants will need to request a pre -construction conference by completing a form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; hLtp://www.albemarle.oriz/deptforms.asp?department=cden,izmTo Thank you -434.296-5832 —x3458 File: WP0201500078 North Pointe Rt29-ME VSMP 090116rev2 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit plan review Project: North Pointe Middle Entrance & Rt. 29 Improvements Plan preparer: Brian Mitchell, P.E., Mona Gabriel, P.E. Townes Site Engineering -9850 Lori Road, Suite 201 Chesterfield, VA 23832 [bmitchellkcctownes.com ] Owner or rep.: CWH Properties Limited Partnership, P.O. Box 5526 Charlottesville, VA 22905 Plan received date: 25 Sep 2015 (Rev. 1) 28 Dec 2015 Date of comments: 17 Nov 2015 (Also: 11/13/2015 10:28 AM email) (Rev. 1) 5 Jan 2016 Reviewer: John Anderson Engineering has completed review of Application WP0201500078 V S M P P l a n s (WP0201500078) A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. SWPPP — SWPPP —Revise SWPPP for Middle Entrance / Rt. 29 Improvements (discussed 11 -Nov). (Rev. 1) Partially addressed. Thank you for .PDFs sent 4 Jan. As follow-up: Please show grading for trap or basin measures required to contain wash waters, vehicle wash waters, concrete wash out, and any on-site fuel storage. Ref. Sec. 6.C. Table/Sources of Pollutants, 6.G.a./d. —Pollution Prevention Awareness. DEQ during periodic site inspections instructs on importance of an Exhibit showing these features. Please revise Exhibit to show: dumpster, portable sanitary (porta john), fuel storage, if any. Areas with potential to contaminate runoff should drain to containment/trap. For example, silt fence downstream of porta john. Concrete wash-out, dumpster draining to trapping device (lined, in case of concrete wash-out). On-site fuel storage: berm with 10ml liner sized to hold fuel volume + 2 yr. storm event. .PDF examples available. Exhibit is not intended as a detailed design but to show containment and locations which contractor is free to change. Exhibit is a construction aid and resource protection/inspection management tool. Sec. 6.E. —Provide Names of persons responsible for pollution prevention practices (Sec. 8 qualified personnel, for example). Sec. 6.F. —Recommend list state/local incident reporting telephone numbers: Emergency Contacts: Normal Working Hours DEQ Valley Regional Office 540-574-7800 Engineering Review Comments Page 2 of 4 Nights, Holidays & Weekends VA Dept. of Emergency Management 804-674-2400 24 Hour Reporting Service Local Contacts Albemarle County/Community Development (Normal Business) 434-296-5832 Local Fire Department 911 Local Police Department 911 Sec. 6.G. —Pollution Prevention Awareness. Items a - g outline procedures and prohibit discharge/spills without reference to frequency of training, or employee orientation to procedures/prohibitions. Provide brief detail that explains training frequency and PPP awareness training and orientation for personnel. Sec. 6.G.b. (Minor edit): "proper disposal in a manner to contact with stormwater" should read: "proper disposal in a manner to prevent contact with stormwater." Appendix C. —Appears unnecessary (No contents) Registration Statement —Please revise to list 20.37 Ac. Estimated Area to be disturbed. With subsequent sections of development (Sec. 1, for example), revise estimated Area to be disturbed to show cumulative area to be disturbed. There are fee implications when Area exceeds 50 Ac., or 100 Ac. Fees increase at these levels. B. VSMP: SWPPP: Stormwater Management Plan (WPO201500078) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved for reasons provided in comments below. The stormwater management plan content requirements can be found in County Code section 17-403. 1. ARB Entrance Corridor requirements vs. SWM BMP design. [see C-lA, II. Entrance Corridor, 2.2] (Rev. 1) Addressed —Applicant response: "Ms. Falkenstein [Alb. Co.] believes that the ARB review for SWM 2 is not required until it is time to review one of the commercial buildings that will be installed upstream of SWM/BMP 2." 2. C-lA, IV, 4.3, E&S Control (b)/Post-construction SWM: Demonstrate design meets proffer condition: 80% annual average sediment removal rate as published by the Center for Watershed Protection in Article 64 of The Practice of Watershed Protection (2000 edition). (Rev. 1) Addressed. Applicant response: "A study has been prepared by Williamsburg Environmental Group, Inc, in April 2006 to evaluate the pre and post construction sediment rates for the North Pointe Development. The study shows that the development of the North Pointe Development including the associated SWM's could result in an estimated reduction in sediment delivered to the Rivanna from 794 tons/year to 146 tons/year (81.6% reduction). A copy of the Sediment Loading Estimates report dated April 2006 is provided in the letter of transmittal for your records." 3. Title p. Note —Remove Part 11 C technical criteria Note. This Title sheet statement requires clarification provided in 12 -Nov County email. (Rev. 1) Partially addressed. As minor follow-up: C-1 reference to email should read Albemarle County Community Development rather than Economic Development. 4. Title sheet —Revise 2.66 Project Area Acreage. (Rev. 1) Addressed. 5. Transfer ROAD PLAN Sheet 6 to VSMP. Also, please ensure 6" DIA Vert. Orifice Elev. =433.50', consistent with routings (discussed 11 -Nov). (Rev. 1) Addressed. 6. Show steep slopes on sheets C-3, C -3A, C-313, C-4, C -4A, C-413 —welcome .PDF preview (discussed 1I - Nov). (Rev. 1) Addressed. 7. C -7A —11.17 Ac. CBPA image extends across Flat Branch, and up opposite bank, beyond E&S sheet LOD. Area picks up road inlets that will be treated by retention basin, but part of the shape of this 11.17 Ac. area, I do not understand, and hope to discuss later today. (Rev. 1) Addressed. 8. C-2 —Label Airport Acres Road. (Rev. 1) Addressed. 9. Please provide Map of stream/wetland impacts covered by VWP Individual Permit Number 14-0364, issued 3 -Apr 2015. `Permitted impacts' referenced in Construction Narrative / Existing Site Conditions Note —C - 3B. (Rev. 1) Addressed. Engineering Review Comments Page 3 of 4 New 10. C-8, SWM/BMP Cross-section: L, 30" DIA barrel =47.69'. Routing L=82.3'. Revise for consistency; revise routings if necessary. 11. C-8, SWM/BMP Cross-section: Label slope, %, SWM 2, 30" DIA outfall pipe. 12. C-8, SWM/BMP Cross-section: Consider buoyancy. Provide concrete riser base, provide base dimensions. 13. C-8, SWM/BMP Cross-section: Revise profile to show Emergency Spillway Elev. 436.50 higher than primary spillway/riser rim Elev. 436.00. 14. C -8A: Str. 14 L =135.25' but L =137.57' in Drainage Structure Summary Table. Revise for consistency. 15. Note: With subsequent WPO submissions, Section 1, for example, use NOAA Atlas 14 point precipitation frequency estimates for Charlottesville, VA, 24 -hr event: 2 -yr =3.68"; 10 -yr =5.57". Link: http://hdsc.nws.noaa.gov/hdsc/pfds/pfds map cont.html?bkmrk=va C. VSMP: SWPPP: Erosion Control Plan (WPO201500078) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESOP. This plan is disapproved for reasons provided in comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Profiles/to scale -ST, SB (discussed 11 -Nov). (Rev. 1) Partially addressed. As follow-up: Compare C-5 silt trap 1, 2 (table) bottom/floor Elev. torp ofiles. Revise profiles/tables. Also: ST2 profile appears to indicate excavation > 4' Max. Revise such that (wet Vol. ) excavation <4'. [Note: silt trap #2: 1.0 X wet volume rqd. =1,899 cf, or < 2,148 cf wet Vol. Actual -1.25 multiplier conservative approach acknowledged] 2. Label LOD; plan view: sheets C -3A, C -3B, C-4, C -4A, C-413 + LOD Table for these sheets, to total 16.1 Ac. (Table required to facilitate tracking of LOD, relative to VAR10C806; MAP INDEX, LOD to increase). (Rev. 1) Partially addressed. As follow-up: On each sheet (listed above) that shows graphic LOD, please define acreage of area of disturbance ( =16.1 Ac). 3. C-2B/C-3 -Heavy demolition hatching obscures some labels (discussed 11 -Nov). (Rev. 1) Addressed. 4. C-3 -Southern Entrance Phase 1 Construction Entrance Notes: 3. Revise to read Airport Acres Road; 5. Recommend road stationing for 54" RCP and 15" CMP. (Rev. 1) Addressed. As follow-up: Revise Note 5. to reference road station 11+50 rather than station 12+50. 5. [11/13/2015 11:08 AM] #51 -Please label ST, SB floor dimensions (L X W), discussed 11 -Nov. (Rev. 1) Addressed. New 6. As discussed 4 Jan, slopes steeper than 3:1 must be permanently stabilized with landscaping vegetation hardier than grass (does not require mowing). Provide notes, labels, and detail to identify species and locations requiring vegetation hardier than grass, C-413, C-8. (Also, email: 1/4/2016 4:32 PM) 7. Add CIP to Legend, C-1 D. VSMP: Mitigation Plan The mitigation plan requirements can be found in County Code section 17-406 1. Stream buffer mitigation: Show stream buffer impacts/2:1 Mitigation required per Ch. 17, Article VI. [C - 1A, IV, Stormwater Management & Stream Bed Conservation, 4.4] -briefly discussed, 11 -Nov. (Rev. 1) Addressed. Applicant response: "A stream buffer plan sheet has been added to the plan set which shows the County defined stream buffer in relation to the overall North Pointe Property. The majority of the property for the North Pointe development is wooded and therefore the mitigation is naturally met since there will be no place to plant new vegetation at the required 2:1 mitigation rate. Please see Stream Buffer Mitigation plan sheet C-9." Engineering plan review staff are available 2-4 PM on Thursdays if a meeting to discuss this review would be helpful. I am also available at 434.296-5832 -x3069 should you have any questions. Engineering Review Comments Page 4 of 4 Process: After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. This project holds a valid CGPNPDES Permit: VAR10C806. After bonding and agreements are complete, the County can hold a pre -construction conference. Applicants will need to request a pre -construction conference by completing a form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; htt2://www.albemarle.org/deptforms.asp?departinent=cdengmTo Thank you -434.296-5832 —x3069 Pile: W110201500078 North I'ointc R129 -ME VSMP 010516rcv 1 • k#00 COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville,Virginia 22902-4596 Phone(4341296-5832 Fax(434)972-4126 VSMP Permit Plan Review Project: North Pointe Middle Entrance&Rt.29 Improvements—Amendment 1 Plan preparer: Brian Mitchell,P.E.,Jessica Seese,P.E. Townes Site Engineering-9850 Lori Road,Suite 201 Chesterfield,VA 23832 [bmitchell(acctownes.com Owner or rep.: CWH Properties Limited Partnership,P.O.Box 5526 Charlottesville,VA 22905 Plan received date: 5 July 2018 Date of comments: 17 July 2018 Reviewer: Matt Wentland County Code section 17-410 and Virginia Code§62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below.The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain(1)a PPP,(2)an ESCP,(3)a SWMP,and(4)any TMDL measures necessary. 1. The approved SWPPP will need to be updated with these plans. The revised ESC plans have been included in Section 4 of the updated SWPPP included with this submittal. B.Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. The approved PPP will need to be updated with these plans. The revised PPP has been included in Section 6 of the updated SWPPP included with this submittal. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved,and the reasons are provided in the comments below.The stormwater management plan content requirements can be found in County Code section 17-403. 1. Please add the plant schedule to the buffer/swm/bmp landscape plans.(ARB comment) The plant schedule has been added to the landscape details sheet C-10B(as well as the road plan sheet C- 13A). D. Erosion and Sediment Control Plan (ESCP) Virginia Code§62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved,and the reasons are provided in the comments below.The erosion control plan content requirements can be found in County Code section 17-402. 1. Include a note on the plans that the haul road will be restored to the pre-development conditions, including removing the stone and eliminating any channelization caused by the grading of the road. A note as such has been added to the Phase II ESC plan on sheet C-4. Engineering Review Comments Page 2 of 2 2. Include a reference to VESCH 3.24 for the stream crossing. A reference to VESCH 3.24(typical label)has been added to sheets C-3/C-4 next to the stream crossing and the temporary culvert crossing detail has been added to the bottom left of sheet C-3. 3. A new/additional bond will be required for the additional disturbance. Note—this will be addressed following plan approval/re-approval. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re-submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays,should you require a meeting to discuss this review. Process; After approval,plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms,which will need to be completed by the owner and submitted along with cash,certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. After bonding and agreements are complete,county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time,the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing,this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application,they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued,via the coverage letter,the County can hold a pre-construction conference. Applicants will need to complete the request for a pre-construction conference form,and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber,and the fee remaining to be paid. This will be checked by county staff,and upon approval,a pre-construction conference will be scheduled with the County inspector. At the pre-construction conference,should everything proceed satisfactorily,a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; http://www.albemarle.org/deptforms.asp?department=cdengwpo COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit Plan Review Project: North Pointe Middle Entrance & Rt. 29 Improvements — Amendment 1 Plan preparer: Brian Mitchell, P.E., Jessica Seese, P.E. Townes Site Engineering -9850 Lori Road, Suite 201 Chesterfield, VA 23832 [bmitchell@cctownes.com ] Owner or rep.: CWH Properties Limited Partnership, P.O. Box 5526 Charlottesville, VA 22905 Plan received date: 5 July 2018 Date of comments: 17 July 2018 Reviewer: Matt Wentland County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESOP, (3) a SWMP, and (4) any TMDL measures necessary. 1. The approved SWPPP will need to be updated with these plans. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. The approved PPP will need to be updated with these plans. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17-403. 1. Please add the plant schedule to the buffer/swm/bmp landscape plans. (ARB comment) D. Erosion and Sediment Control Plan (ESOP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. Include a note on the plans that the haul road will be restored to the pre -development conditions, including removing the stone and eliminating any channelization caused by the grading of the road. Engineering Review Comments Page 2 of 2 2. Include a reference to VESCH 3.24 for the stream crossing. 3. A new/additional bond will be required for the additional disturbance. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process; After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. After bonding and agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; ht!p://www.albemarle.or�z/deptforms.asp?department=cden,izwpo File: WP0201500078 North Pointe Middle Entrance Amendment 1 07-17-18.doc VSMP 1. ARB Entrance Corridor requirements vs. SWM BMP design. [see C -IA, II. Entrance Corridor, 2.2] 2. C -IA, IV, 4.3, E&S Control (b)/Post-construction SWM: Demonstrate design meets proffer condition: 80% annual average sediment removal rate as published by the Center for Watershed Protection in Article 64 of The Practice of Watershed Protection (2000 edition). 3. SWPPP —Revise SWPPP for Middle Entrance / Rt. 29 Improvements (discussed 11 -Nov). 4. Profiles/to scale —ST, SB (discussed 11 -Nov). 5. Title p. Note —Remove Part II C technical criteria Note. This Title sheet statement requires clarification provided in 12 -Nov County email. 6. Title sheet —Revise 2.66 Project Area Acreage 7. Stream buffer mitigation: Show stream buffer impacts/2:1 Mitigation required per Ch. 17, Article VI. [C- IA, IV, Stormwater Management & Stream Bed Conservation, 4.4] —briefly discussed, 11 -Nov. 8. Label LOD; plan view: sheets C -3A, C-313, C-4, C -4A, C-413 + LOD Table for these sheets, to total 16.1 Ac. (Table required to facilitate tracking of LOD, relative to VAR10C806; MAP INDEX, LOD to increase) 9. Transfer ROAD PLAN Sheet 6 to VSMP. Also, please ensure 6" DIA Vert. Orifice Elev. =433.50', consistent with routings (discussed 11 -Nov). 10. Show steep slopes on sheets C-3, C -3A, C-313, C-4, C -4A, C-413 —welcome .PDF preview (discussed 1I - Nov). 11. C -7A —11.17 Ac. CBPA image extends across Flat Branch, and up opposite bank, beyond E&S sheet LOD. Area picks up road inlets that will be treated by retention basin, but part of the shape of this 11.17 Ac. area, I do not understand, and hope to discuss later today. 12. C-2 —Label Airport Acres Road 13. C-2B/C-3 —Heavy demolition hatching obscures some labels (discussed 11 -Nov). 14. C-3 —Southern Entrance Phase 1 Construction Entrance Notes: 3. Revise to read Airport Acres Road; 5. Recommend road stationing for 54" RCP and 15" CMP. 15. Please provide Map of stream/wetland impacts covered by VWP Individual Permit Number 14-0364, issued 3 -Apr 2015. `Permitted impacts' referenced in Construction Narrative / Existing Site Conditions Note —C-313. The Review for the following application has been completed: Application Number= WP0201500078 Reviewer = John Anderson Review Status = Requested Changes Completed Date = 11/17/2015 Thanks for your patience. CV comments: "Two(2) 13-Nov plan review emails,one with Attachment listing 15 preview comments,the other listing 6 items within text of email,were topic of discussion, 17-Nov,9AM: J. Anderson,Mona Gabriel,Townes Site Engineering. Applicant response will include preview comments. Plan revisions will respond to comments not directly dispensed with during conversation on 17-Nov. Please see responses below. County is grateful for Ms. Gabriel's willingness to discuss preview comments;this may save time/resources." Thank you for taking the time to discuss the comments over the phone with me. Also, Although it may take a day or two for print copy plan revision re-submittal to reach Engineering,once submitted,I intend to comment within 10 business days,or within 2 weeks. I regret delay commenting on •this plan submittal. Thank you! Thanks,again. 434.296-5832—x3069 VSMP 1. ARB Entrance Corridor requirements vs.SWM BMP design. [see C-lA,II.Entrance Corridor,2.2] Thank you for pointing that out. We are checking with the planner,Rachel Falkenstein on the timing and process for the ARB review. Ms. Falkenstein believes that the ARB review for SWM 2 is not required until it is time to review one of the commercial building that will be installed upstream of SWM/BMP 2. Ms. Falkenstein is checking with the zoning team to decide when the ARB review for SWM 2 will be required and will let us know. 2. C-lA,IV,4.3,E&S Control(b)/Post-construction SWM:Demonstrate design meets proffer condition:80% annual average sediment removal rate as published by the Center for Watershed Protection in Article 64 of The Practice of Watershed Protection(2000 edition). A study has been prepared by Williamsburg Environmental Group, Inc in April 2006 to evaluate the pre and post construction sediment rates for the North Pointe Development. The study shows that the development of the North Pointe Development including the associated SWM's could result in an estimated reduction in sediment delivered to the Rivana from 794 tons/year to 146 tons/year(81.6% reduction).A copy of the Sediment Loading Estimates report dated April 2006 is provided in the letter of transmittal for your records. 11110VPPP—Revise SWPPP for Middle Entrance/Rt.29 Improvements(discussed 11-Nov). A SWPPP that is specific to the Middle Entrance project is provided in the submittal packet for your review as requested If the SWPPP is not included please let me know and I will email you a pdf copy for your review 41110Profilesho scale-ST,SB(discussed 11-Nov). ��. Profiles for the two sediment traps and the sediment basin have been provided as requested y'sPlease see sheet C-S for the sediment trap profiles and sheet C-8A for the sediment basin yprofiles. opiorttle p.Noteemove Part II C technical criteria Note. This Title sheet statement requires clarification provided in 12Nov County email. Email dated November 12th is referenced as discussed on the phone. Please see sheet C-1. 6. Title sheet-Revise 2.66 Project Area Acreage Project area acreage has been revised as requested. Please see sheet C-1. 7. Stream buffer mitigation: Show stream buffer impacts/2:1 Mitigation required per Ch. 17,Article VI. [C- 1A,IV,Stormwater Management&Stream Bed Conservation,4.4]-briefly discussed, 11-Nov. A stream buffer plan sheet has been added to the plan set which shows the County defined stream buffer in relation to the overall North Pointe Property. The majority of the property for the North Pointe Development is wooded and therefore the mitigation is naturally met since there will no place to plant new vegetation at the required 2:1 mitigation rate. Please see Stream er Mitigation plan sheet C-9 abel LOD;plan view:sheets C-3A,C-3B,C-4,C-4A,C-4B+LOD Table for these sheets,to total 16.1 Ac.(Table required to facilitate tracking of LOD,relative to VAR10C806;MAP INDEX,LOD to increase) The limits of disturbance have been labeled as requested 9. Transfer ROAD PLAN Sheet 6 to VSMP. Also,please ensure 6"DIA Vert.Orifice Elev.=433.50', consistent with routings(discussed 11-Nov). The pond grading sheet has been added to the WPO plan set as requested. Please see sheet C-8 10. Show steep slopes on sheets C-3,C-3A,C-3B,C-4,C-4A,C-4B-welcome.PDF preview(discussed 11- Nov). Steep slope hatch has been added on sheets C-3 thru C-4B as requested. 11. C-7A-11.17 Ac.CBPA image extends across Flat Branch,and up opposite bank,beyond E&S sheet LOD. Area picks up road inlets that will be treated by retention basin,but part of the shape of this 11.17 Ac.area, I do not understand,and hope to discuss later today. As discussed on the phone, the limits of the project area on the east.follows along the centerline of the field located Flat Branch. 12. C-2-Label Airport Acres Road A label has been added for Airport Acres Road on all the applicable Plan sheets as requested. 13. C-2B/C-3-Heavy demolition hatching obscures some labels(discussed 11-Nov). The demolition plan sheets have been revised to lighten the demolition hatching for clarity. Please ee revised sheets C-2 thru C-2B. C-3-Southern Entrance Phase 1 Construction Entrance Notes:3.Revise to read Airport Acres Road;5. Recommend road stationing for 54"RCP and 15"CMP. Notes have been revised as requested IIIIMase provide Map of stream/wetland impacts covered by VWP Individual Permit Number 14-0364, issued 3-Apr 2015. `Permitted impacts'referenced in Construction Narrative/Existing Site Conditions Note-C-3B. The wetland impacts map is provided as requested. If map is not included in the submittal packet please contact me and I will email you a copy in pdf format. Mona, Also,as follow-up to 5-Dec 2014 plan review comments- #49-Townes response-could we discuss? As we discussed over the phone, the contours shown in the vicinity of sediment Trap I represent the existing condition of this trap. Size has been verified and is adequate to handle the drainage area draining to it #50-Recommend Note re. Inspection frequency,VAR10 Part I, B.4 d.(1)-every 4 da\, d The applicable SWPPP inspection requirements specified in Part II F 2 shall be amended as follows. (1) Inspections shall be conducted at a frequency of(i)at least once every four business days or (ii)at least once every five business days and no later than 48 hours following a measurable storm event In the event that a measurable storm event occurs when there are more than 48 hours between business days, the inspection shall be conducted on the next business day and The inspection frequency has been added to the SWPPP. #51 -Please label ST, SB floor dimensions(L x W),discussed 11-Nov Floor dimensions have been added as requested. Please see sheet C-3A. #52-Please show TS/PS,MU, DC(shown w/Legend,but not plan views) The aforementioned measures have been added where applicable on the Erosion and Sediment Control Plan sheets. Please see revised EC sheets. Jed: Sheet C-3B,please provide a Proposed SB contours have added as reques e #64/65-Delete reference to basins 2&2A. Please reference basin to be built:Pond IP in routings.-see Also, 12-Nov county email The name of the Pond has been changed to "2"in the Routing, and the Pond reference has been change to match Pond name for consistency.