HomeMy WebLinkAboutSUB201100109 Review Comments Road Plan and Comps. 2011-09-14 Philip Custer
From: Glenn Brooks
Sent: Wednesday, October 12, 2011 1:27 PM
To: Glenn Brooks; Mark Graham; Bill Fritz; Philip Custer
Cc: Claudette Grant
Subject: RE: Stonefield Boulevard Road Plan VDOT Review
As a matter of fact, we could take this one step further; strike out the stop signs and waterline with a red marker, and
approve the plan as marked. These are not necessary for the road plan anyway.
From: Glenn Brooks
Sent: Wednesday, October 12, 2011 1:22 PM
To: Mark Graham; Bill Fritz; Philip Custer
Cc: Claudette Grant
Subject: RE: Stonefield Boulevard Road Plan VDOT Review
A public road plan has been submitted. I don't read an approval for a public road plan.To me this says VDOT is offering
"guidance in the review" of a private road.
We could only approve a private road after the proffer is changed accordingly. For a public road plan approval, it
appears the same plan revisions are requested; move the waterline,and remove the four stop signs on the main route.
(Four way stops can be requested with warrant analysis when traffic can be measured.)
My recommendation to the board will be to move the waterline, and remove the four stop signs. Simple.
From: Mark Graham
Sent: Wednesday, October 12, 2011 10:39 AM
To: Bill Fritz; Glenn Brooks; Philip Custer
Subject: FW: Stonefield Boulevard Road Plan VDOT Review
Phil,
I assume we should treat this as the road plan approval by VDOT.
From: DeNunzio, Joel D., P.E.Lmailto:Joel.DeNunzioCa�VDOT.virginia.gov]
Sent: Wednesday, October 12, 2011 10:33 AM
To: Mark Graham
Cc: Sprinkel, D. Brent P.E.; Barron, L. Marshall
Subject: Stonefield Boulevard Road Plan VDOT Review
Stonefield Boulevard Road Plan VDOT Review
Mr. Graham,
In accordance with the Virginia Administrative Code 24 VAC30-92-20, Secondary Street Acceptance
Requirements, VDOT has reviewed the subject plan at the request of Albemarle County for streets that are
proposed for maintenance by an entity other than VDOT.
In this review we have found that the streets meet the minimum requirements set forth by the VDOT Road
Design Manual and the VDOT Road and Bridge Specifications with the exception of the proposed four way
1
stop at the intersection of Stonefif 3oulevard and Main Street and the in, 'lotion of the waterline within
the proposed public road pavement. Four way stop type of traffic control rt./tires a warrant analysis as
described in the Manual of Uniform Traffic Control which should be submitted and approved prior to its
installation. The installation of utilities within the proposed public road right of way should be located outside
of the pavement and within the outer 3 to 5 feet of the right of way.
This review does not represent VDOT's commitment to accept the proposed street into the State Secondary
System of Highways as stated in 24 VAC30-92-20 section A but is provided to assist Albemarle County with
general guidance in the review process.
Please let me know if you have any questions.
Thanks,
Joel
Joel DeNunzio, P.E.
VDOT Culpeper
Land Development
434-589-5871
ioel.denunzio@vdot.virginia.gov
2
NNW' "NOV
Philip Custer
From: Philip Custer
Sent: Friday, September 23, 2011 5:21 PM
To: 'Herbert F. White Ill, P.E.'; 'Rob Umberger'; 'Tom Gallagher'
Cc: Gerald Gatobu; Bill Fritz; Mark Graham; Glenn Brooks
Subject: Engineering review of Stonefield Blvd. and Regal Cinema
Attachments: E2_ecp swm fsp_PBC_sdp-2011-00047 The Shops at Stonefield-Regal Cinema.doc; E2_ecp
swm rp_PBC_wpo-2011-00036 Stonefield Blvd. Road Plan.doc
Good evening,
Attached are the engineering comment letters from the review of the applications for the Stonefield Blvd. Plan (WPO-
2011-00036 and SUB-2011-00109), received 15 September 2011, and the Regal Cinema Site Plan (SDP-2011-00047 and
WPO-2011-00055), received 31 August 2011. Both plans are close to receiving technical approval and require a few
modifications. These technical issues can be addressed by W&W sending me pdfs of these changes on Monday. These
changes include:
Stonefield Blvd.
-removal of stop signs and stop bars and intersections 3 and 6.
-addition of hatching and a note regarding the intersection with 2nd st.
Regal Cinema
-extension of the curb along west main street
-providing a new branch to the temporary pipe system west of Stonefield Blvd.to accept water from the construction of
the parking lot that bypasses the inlets on grade (see comment B3 for more details)
-increasing the size of the new temporary pipe system to 30" (see comment B3)
Please email the pdfs of all of the changes at one time (if not in one email) so they can be reviewed at one time. Once I
have signed off on all changes, I will provide ESC and SWM bond estimates for both plans and let you know how many
copies of each plan I will need for the WPO and road inspection files(Gerald is coordinating the site plan file).
There is one administrative issue left in the comment letter regarding the construction of the sanitary sewer line on the
Northrup Grumman property. Generally, we require the easement plats to be recorded before final site plans are
signed. I don't have my arms around this issue completely, but in talking with some people here,the final site plan could
be signed if ACSA guarantees the easement since they have the power of condemnation. The county should have
clarification on this early next week.
Please let me know if you have any questions. I will be in the office tomorrow and can respond to any immediate
questions that you have then.
Thanks,
Phil
(434) 296-5832 x3072
ALg�,��
�'IRGINZ�
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902 -4596
Phone (434) 296 -5832 Fax (434) 972 -4126
Project: Stonefield Blvd. Road, ESC, and SWM Plans; WPO- 2011 -00036 & SUB - 2011 -00109
Plan preparer: Mr. Herb White, PE; W & W Associates
Owner or rep.: Albemarle Place EAAP LLC
Date received: (Rev. 1) 15 September 2011
16 June 2011 (Traffic Study Received 1 June 2011)
Date of Comment: (Rev. 1) 23 September 2011
3 August 2011
Engineer: Phil Custer
The Road, ESC, and SWM plans for Stonefield Blvd. (WPO- 2011 -00036 and SUB - 2011 - 00109) received
on 15 September 2011, have been reviewed. The plans can be approved after the following comments
have been addressed:
A. Traffic Study Review (SUB- 2011 - 00109)
1. Please elaborate on the figures (peak hour and ADT) used for the multiplex theater. The county
only possesses the 7th edition and an ADT per seat is not available in that edition. The only per
day traffic figure for the theater is based off of screens, which yields 4095 trips for this project.
The applicant's estimate of 1310 seems low. Also, for a PM peak hour, a theater usually generates
more entering traffic.
(Rev. 1) After conversations with VDOT, this comment has been withdrawn.
2. The report assumes 15% of total residential trips will be pedestrian only which seems to be overly
optimistic for this project. Please provide the source for this assumption.
(Rev. 1) Comment has been addressed.
3. While I understand the reasoning for the commercial - commercial reduction, I don't think it is a
sound. Please provide a source for the use of this reduction technique. It seems to me it would be
more reasonable to use an average of the three commercial ADT estimates (21850 for Phase 1I and
24631 for Phase III).
(Rev. 1) Comment has been withdrawn.
4. The passby capture is not justified for this type of analysis. The pass -by capture should only be
used for traffic impact analyses which this report is not, despite its title; this report looks at new
internal intersections constructed with this development, not the development's impacts on
Hydraulic and Route 29. This analysis was performed with the rezoning application and no
additional analysis of this kind is needed.
(Rev. 1) Comment has been withdrawn.
5. Please provide a graphic such similar to those in Appendix A that distributes the Phase III ADT
(vehicles, not percentages) throughout the road grid.
(Rev. 1) Comment has been addressed.
6. Table D2 shows that Southbound Stonefield Blvd. shows that 100% of the traffic wishes to go
straight through the intersection. I don't think this is realistic. If it is correct, a left turn lane is not
needed. I also think that more traffic will wish to turn left from Eastbound D3 drive than —16 %.
(Rev. 1) Comment has been addressed.
7. Given the layout of the development, I do not suspect that Inglewood Drive between I" and 3rd
Streets will be carrying any significant amount of through traffic. The —1500 vehicles a day
through this street should not preclude use of angled parking along this street. Per the variation
letter issued by the Director of Planning, angled parking may be used but the details will be subject
to the review of the planner and engineer assigned to the project. The dimensions of the angled
parking should be drawn to the standards of the Zoning Ordinance (18 -4.12) and the County
Design Manual. County staff may also require the entrances to parking areas off this road to be
consolidated to simplify the sight lines for vehicles backing out of spaces.
8. County engineering does not support the use of four way stops at Sta. 15 +11 and Sta. 17 +11.
(Rev. 1) Please remove the stop signs and stop bars for the north and south movements on
Stonefield Blvd. through the intersections with Main Street and the parking lot south of the
Sperry Marine Entrance. These stop conditions are not warranted at this time.
9. Since approximately 2/3 of all Northbound Stonefield Blvd. vehicles will be making a right turn at
3`d St., engineering review feels it is reasonable to maintain a 2nd Northbound lane from the
entrance to Sperry Marine to 3`d St. Since the fourway stop at Stonefield Blvd. and 3`d St. will
meter the traffic flow through southbound Stonefield Blvd. the second southbound lane may be
eliminated per the variation approved by the Director of Planning.
(Rev. 1) Since the road terminates at this intersection and no development of Blocks F and G
are proposed at this time or in the immediate future, the design of this intersection does not
need to be settled now. However, on all sheets showing the northern terminus of Stonefield
Blvd., please hatch an area and ROW large enough for a 200ft right turn lane and add a note
stating: "The design of the intersection of Stonefield Blvd. (District Ave.) and Second Street has
yet to be approved and a future right hand turn lane will likely be needed. This intersection will
be reviewed when the construction documents for Block F, Block G, or, possibly, the permanent
extension of Stonefield Blvd. (District Ave.) to Route 29 is submitted."
B. Road Plan Review (SUB- 2011 - 00109)
1. 1llG wuuny LnwgCS oz.-)u 1ur the review of all public road plans. Please provide a check for $250
to the county for this review of the plan with a completed SUB Application with the appropriate
Road Plan Review box checked.
(Rev. 1) Comment has been addressed. The SUB application for this road plan is SUB -2011-
00109.
2. Please make the necessary adjustments to the plans to address comments A8 and A9.
(Rev. 1) Please refer to these comments above.
3. On southbound Stonefield Blvd., the wide median does not appear necessary. More stacking area
could be provided if the 2nd left turn lane was extended to the intersection with Main Street.
(Rev. 1) No modifications were required.
4. I don't believe structure 38.1 has been approved on any county plan. The approved SWM plan
has no structure from 38 to 39. Please update this set accordingly.
(Rev. 1) The applicant has stated this has been modified on an amendment that was approved
by other county staff.
5. For storm drain and road profiles, please also show the existing grade line of the site before the
mass grading plan was enacted.
(Rev. 1) County Engineering has provided relief on this requirement to allow a cut fill exhibit
to address this comment.
C. Erosion and Sediment Control Plan Review (WPO- 2011 - 00036)
1. Because of strict requirements of Water Protection Ordinance Section 17- 207.B.2, erosion and
sediment control plans for projects of such a large size must be designed to be closed out as soon
as possible. For this reason, subsequent plans cannot assume that the sediment basins constructed
with the mass grading application will remain online. Therefore, each ESC plan must be a
standalone application.
This road plan assumes that the mass grading plan has been completed and is stabilized, but still
relies on the sediment basin for ultimate sediment treatment. This ESC plan must be a standalone
plan.
(Rev.]) The current plan is acceptable. However, the plan is not a standalone plan, but relies
on a sediment basin and temporary pipe system that was approved and constructed under
WPO- 2009 - 00074, Albemarle Place Mass Grading. Without this plan, the plan currently under
review (WPO- 2011 - 00036) would not meet state standards. The nine month disturbance limit
for this mass grading plan will be reached on 112612011. Before that date, an extension must
be approved by the Board of Supervisors since the reason for the extension is a construction
sequencing decision made by the applicant, and not something out of the applicant's control
such as poor weather. To receive this extension, the applicant must provide a request for
extension by 1112312011 to the clerk of the Board of Supervisors. If the Board of Supervisors
does not allow a portion of the mass grading plan that is relied upon by a subsequent plan to
remain active, that plan approval would be invalidated and a stop work order for all related
construction will be issued until an amendment is approved that meets state regulations without
the basin.
2. Sediment -laden water must not enter the stormsewer system and detention facilities. Inlet
protection is more often than not an inadequate measure because the inlets are constructed well
after initial land disturbance. Even after installation, storm inlets are often bypassed because their
rim elevation is higher than the subbase and gravel around them until the final stage of
construction. Much of the runoff with this project will be directed out of the north end of the road.
The remainder will escape out the graded entrances unless diversions and ROW diversions are
utilized. A sediment trap or basin at the north end of the road and perhaps one or two on the east
side of the road south of the Sperry site appears to be necessary.
(Rev. 1) Sediment -laden water will be allowed to travel through temporary pipe systems that are
filled in after stabilization has occurred. The county will consider these systems as temporary
slope drains since they are not permanent and carry sediment -laden water to settling facilities.
Please see the previous comment.
3. Please provide clearer language on the plan that the mass grading plan is to be completed prior to
the start of this application. It is important to the implementation of this plan that the area to the
west is stabilized.
(Rev. 1) Please refer to comments Cl and C2.
4. For simplification of the design of the ESC plan, I recommend that the ESC plan for the cinema,
parking lot for the cinema, and Stonefield Blvd. are combined into one plan, assuming all projects
can be completed in 9 months.
(Rev. 1) This comment was only a recommendation.
5. Please detail how the Sperry traffic is to be dealt with during construction. How will Sta. 19 +00 to
Sta. 20 +50 of Stonefield Blvd. be constructed?
(Rev. 1) Comment has been addressed. I have some concerns about the practicality of the
solution of having flaggers on site but will not impose any restrictions because the general
public is not affected.
6. Please show the grading for the cleanwater diversion west of the road. Please remove the inlet
protection for this inlet (it should be cleanwater and therefore not need protection) and make sure
there is an adequate sump for the discharge to this facility. A ROW diversion should also be
constructed across this entrance to keep runoff from the construction area from going into this drop
inlet.
(Rev. 1) Comment has been addressed.
7. Because this plan will be implemented after stabilization of the mass grading plan, please confirm
there will be no construction traffic wanting to access the north end of the site.
(Rev. 1) Please refer to comments Cl and C2.
8. Please remove all references to the biofilter from the ESC plan sheet.
(Rev. 1) Comment has been addressed.
9. Please provide a completed Bond Estimate Request Form to the county engineer to receive an ESC
bond.
(Rev. 1) A completed Bond Estimate Request Form has been received and estimates will be
provided shortly.
D. Stormwater Management Plan Review (WPO- 2011 - 00036)
1. Every parcel that requires a stormwater management facility must sign a Stormwater Management
Facility Maintenance Agreement with the County. Please complete this form and submit it to Ana
Kilmer with a $17 recordation fee after reading the instructions online. Another agreement may be
required for the master stormwater management plan approved under WPO- 2010 - 00023.
(Rev. 1) Ana Kilmer has determined that the previously recorded Stormwater Facility
Maintenance Agreement for the project covers all new facilities.
2. Biofilters must have 2.5' of state approved mix. Please increase the media depth by 6 inches. The
county allows a minimum of lft of stone below the media mix.
(Rev. 1) Comment has been addressed.
3. The 5% impervious area sizing methodology for biofilters assumes that lft of ponding is provided.
The 6" provided in this plan is not adequate. The goal with a biofilter treating to a 65% removal
rate is to treat the volume of water of 1" of rain falling on the impervious area. In this case, the
target volume is about 2850cf but a volume of 1110cf is provided. The simplest solution would be
to raise the rim of the DI -7 another 0.5ft.
(Rev. 1) Comment has been addressed.
4. Please provide outlet protection at the outlet of the storm drain system in the forebay.
(Rev. 1) Comment has been addressed.
5. Please provide a completed Bond Estimate Request Form to the county engineer to receive a SWM
bond.
(Rev. 1) A completed Bond Estimate Request Form has been received and estimates will be
provided shortly.
`+err+' „.....„
WA
ENGINEERS
SURVEYORS
PLANNERS
ASSOCIATES
September 14,2011
Mr. Philip Custer, P.E.
Civil Engineer I
Albemarle County
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
Re: Stonefield Boulevard Road Plan WPO 2011-00036
WWA Project No. 208026.02
Dear Mr. Custer:
This letter is to document and respond to your review comments dated August 3, 2011.
Our responses are as follows:
A. Traffic Study Review
These issues have been deferred to VDOT per previous meetings.
B. Road Plan Review
1. Comment: The county charges$250 for the review of all public road plans. Please
provide a check for$250 to the county for this review of the plan with a completed
SUB Application with the appropriate Road Plan Review box checked.
Response: A completed SUB Application and $250 review fee has been provided
with this submittal as requested.
2. Comment: Please make the necessary adjustments to the plans to address
comments A8 and A9.
Response: These issues have been deferred to VDOT per previous meetings.
3. Comment: On southbound Stonefield Blvd., the wide median does not appear
necessary. More stacking area could be provided if the 2'`d left turn lane was
extended to the intersection with Main Street.
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
..................................................................................................................................................
Lynchburg•Charlottesville
Response: The necessary stacking has been provided in accordance with the traffic
study. No modifications have been made to the median with this revision.
4. Comment: I don't believe structure 38.1 has been approved on any county plan.
The approved SWM plan has no structure from 38 to 39. Please update this set
accordingly.
Response: The stormwater management plans have been revised and will be
submitted under separate cover.
5. Comment: For storm drain and road profiles,please also show the existing grade
line of the site before the mass grading plan was enacted.
Response: A cut/fill exhibit has been provided for reference with this submittal.
C. Erosion and Sediment Control Plan Review (WPO-2011-00036)
1. Comment: Because of strict requirements of Water Protection Ordinance Section
17-207.B.2, erosion and sediment control plans for projects of such a large size
must be designed to be closed out as soon as possible. For this reason, subsequent
plans cannot assume that the sediment basins constructed with the mass grading
application will remain online. Therefore, each ESC plan must be a standalone
application.
This road plan assumes that the mass grading plan has been completed and is
stabilized, but still relies on the sediment basin for ultimate sediment treatment. This
ESC plan must be a standalone plan.
Response: All final site plans for blocks"A"—"Dl", have been submitted. The
road plans and site plans are to be built concurrently and coordinated during
construction. These plans have been revised to show the temporary south diversion
pipe the Albemarle Place Erosion and Sediment Control Plan, WPO-2009-00074 to
transport silt laden water to the south sediment basin. A temporary sediment trap
has been added below the intersection of Stonefield Boulevard and Second Street to
capture runoff from the areas that do not get picked up in the temporary diversion
pipe to the south sediment basin.
2. Comment: Sediment-laden water must not enter the stormsewer system and
detention facilities. Inlet protection is more often than not an inadequate measure
because the inlets are constructed well after initial land disturbance. Even after
installation, storm inlets are often bypassed because their rim elevation is higher
than the subbase and gravel around them until the final stage of construction.
Much of the runoff with this project will be directed out of the north end of the road.
The remainder will escape out the graded entrances unless diversions and ROW
diversions are utilized. A sediment trap or basin at the north end of the road and
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
..................................................................................................................................................
Lynchburg•Charlottesville
Page 2 of 5
perhaps one or two on the east side of the road south of the Sperry site appears to
be necessary.
Response: These plans have been revised to show the temporary south diversion
pipe the Albemarle Place Erosion and Sediment Control Plan, WPO-2009-00074 to
transport silt laden water to the south sediment basin. A temporary sediment trap
has been added below the intersection of Stonefield Boulevard and Second Street to
capture runoff from the areas that do not get picked up in the temporary diversion
pipe to the south sediment basin.
3. Comment: Please provide clearer language on the plan that the mass grading plan
is to be completed prior to the start of this application. It is important to the
implementation of this plan that the area to the west is stabilized.
Response: The road plans and site plans are to be built concurrently and will be
coordinated during construction.
4. Comment: For simplification of the design of the ESC plan, I recommend that the
ESC plan for the cinema,parking lot for the cinema, and Stonefield Blvd. are
combined into one plan, assuming all projects can be completed in 9 months.
Response: The road plans and site plans are to be built concurrently and will be
coordinated during construction.
5. Comment: Please detail how the Sperry traffic is to be dealt with during
construction. How will Sta. 19+00 to Sta. 20+50 of Stonefield Blvd. be
constructed?
Response: Notes have been added to the plans stating that the Contractor shall
proved flaggers at this intersection to direct traffic. Please refer to Dwg. C-12 for
details.
6. Comment: Please show the grading for the cleanwater diversion west of the road.
Please remove the inlet protection for this inlet (it should be cleanwater and
therefore not need protection) and make sure there is an adequate sump for the
discharge to this facility. A ROW diversion should also be constructed across this
entrance to keep runoff from the construction area from going into this drop inlet.
Response: As requested grading has been added for the cleanwater diversion west
of the road, the inlet protection has been removed, and ROW diversions have been
added. Please refer to Dwg. C-12 for details.
7. Comment: Because this plan will be implemented after stabilization of the mass
grading plan,please confirm there will be no construction traffic wanting to access
the north end of the site.
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
Lynchburg•Charlottesville
Page 3 of 5
Response: The road plans and site plans are to be built concurrently and will be
coordinated during construction.
8. Comment: Please remove all references to the biofilter from the ESC plan sheet.
Response: The label has been removed from the biofilter as requested. Please refer
to Dwg. C-12 for details.
9. Comment: Please provide a completed Bond Estimate Request Form to the county
engineer to receive an ESC bond.
Response: Noted.
D. Stormwater Management Plan Review (WPO-2011-00036)
1. Comment: Every parcel that requires a stormwater management facility must sign
a Stormwater Management Facility Maintenance Agreement with the County.
Please complete this form and submit it to Ana Kilmer with a$17 recordation fee
after reading the instructions online. Another agreement may be required for the
master stormwater management plan approved under WPO-2010-00023.
Response: Noted.
2. Comment: Biofilters must have 2.5'of state approved mix. Please increase the
media depth by 6 inches. The county allows a minimum of lft of stone below the
media mix.
Response: The media depth for the biofilter has been increased to 2.5'. Please refer
to Dwg. C-22 for details.
3. Comment: The 5% impervious area sizing methodology for biofilters assumes that
1 ft of ponding is provided. The 6"provided in this plan is not adequate. The goal
with a biofilter treating to a 65%removal rate is to treat the volume of water of 1"
of rain falling on the impervious area. In this case, the target volume is about
2850cf but a volume of 1110cf is provided. The simplest solution would be to raise
the rim of the DI-7 another 0.5ft.
Response: The biofilter has been revised to provide a ponding depth of 1'. Please
refer to Dwg. C-22 for details.
4. Comment: Please provide outlet protection at the outlet of the storm drain system
in the forebay.
Response: Outlet protection has been provided at the outfall of the storm sewer in
the forebay of the biofilter. Please refer to Dwg. C-12 for details.
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
.................................................................................................................................................
Lynchburg•Charlottesville
Page 4 of 5
5. Comment: Please provide a completed Bond Estimate Request Form to the county
engineer to receive a SWM bond.
Response: Noted.
I trust that the above responses and plan changes properly address the outstanding issues.
If you have any questions,please contact me.
Sincerely,
WW Associates, Inc.
111.
��...
Herbert F. White III, P.E.
President
cc: Thomas R. Gallagher, Edens and Avant
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
..................................................................................................................................................
Lynchburg•Charlottesville
Page 5 of 5
Philip Custer
From: Philip Custer
Sent: Friday, September 02, 2011 10:44 AM
To: 'Tom Gallagher'; 'Herbert F. White Ill, P.E.'
Cc: Glenn Brooks; Gerald Gatobu; Bill Fritz
Subject: FW: Stonefield Blvd Road Plans
I was out yesterday,so I wasn't able to forward Joel's comments then.
From: DeNunzio, Joel D., P.E. jmailto:Joel.DeNunzio@VDOT.virainia.govl
Sent: Wednesday, August 31, 2011 4:16 PM
To: Philip Custer
Subject: Stonefield Blvd Road Plans
Stonefield Blvd Road Plans
Phil,
I have reviewed the subject road plan and have the following comments:
1. The road classification is an urban collector with a 25 mph speed. Note 4 on the cover sheet along with
labels on the plan and profile sheets and the typical section sheets refers to an urban local. All geometric and
spacing standards must be within the GS-7 standard.
2. Note#1 for General Construction Notes for Streets should refer to the VDOT 2007 Road and Bridge
Specifications and the VDOT 2008 Road and Bridge Standards.
3. Note#9 on sheet C-5 should require any springs to be capped with a standard spring box, SB-1, SB-1 PC.
4. Note#22 on sheet C-5 should refer to streets needing to met the minimum service requirements in
accordance with the VDOT SSAR's.
5. A list of mandatory VDOT inspections should be in the VDOT notes section. These mandatory inspections
will also be listed with the final approval of the plans and the issuance of any permits. These need to include:
a. Installation of any enclosed drainage system before it is covered
b. Installation of any enclosed utility placements within the right-of-way before being covered
c. Construction of the cuts and fills, including field density tests, before placement of roadbed base
materials
d. A final pavement design, based on actual soil characteristics and certified tests, shall be completed and
approved before the pavement structure is placed
1
e. Placement of base materials'6tricluding stone depths, consistent with` ie approved pavement design,
prior to placement of the paving course or courses, followed by field density and moisture tests and the
placement of a paving course as soon as possible
f. Construction of pavement, including depth and density, upon completion as part of the final inspection
6. The overall plan on sheet C-7 and all other applicable sheets need to remove stop bars from all
intersections on approaches that do not have stop control.
7. Sheet C-8 needs to show intersection sight distances on intersections at station 17+00 along with sight
easement lines. The intersection at station 20+00 needs to label the sight easement lines.
8. The grading within the clear zone right of station 20+50 to station 22+00 needs to meet the clear zone
requirements for recoverable area.
9. North bound lanes from Hydraulic to Sperry entrance should be marked for 2 through lanes.
10. Show stopping sight distances on the vertical curves.
11. A vertical curve needs to be added at station 15+10.
12. All pavement markings for edge lines need to be 4". The legend calls for 6" for the yellow lines.
13. Locations of the street trees at intersections needs to be setback as shown in the VDOT Road Design
Manual Appendix B(1)-44.
14. Show the sight lines across the biofilter landscape plan. It appears there will be sight line obstructions
for the proposed vegetation.
15. At this time there is not enough information to determine the adequacy of the t-type intersection at
Stonefield Blvd and proposed Second Street. This intersection will need to be analyzed with phase 2 and
possibly modified to include a right turn lane or a roundabout.
16. A warrants analysis will need to be submitted to VDOT and approved by VDOT for the 4-way stop
condition at the intersection of Stonefield Blvd and Main Street prior to acceptance of the road into the state
maintenance system.
Please let me know if you have any questions.
Thanks
Joel
Joel DeNunzio, P.E.
VDOT Culpeper
Land Development
2
434-589-5871 ""
joel.denunzioPvdot.virginia.gov
3
WENGINEERS
SURVEYORS
PLANNERS
ASSOCIATES
September 14,2011
Mr. Joel D. DeNunzio, P.E.
VDOT Charlottesville Residency
701 VDOT Way
Charlottesville, Virginia 22911
Re: Stonefield Boulevard Road Plan WPO 2011-00036
WWA Project No. 208026.02
Dear Mr. DeNunzio:
This letter is to document and respond to your review comments dated August 31, 2011.
Our responses are as follows:
1. Comment: The road classification is an urban collector with a 25 mph speed. Note
4 on the cover sheet along with labels on the plan and profile sheets and the typical
section sheets refers to an urban local. All geometric and spacing standards must
be within the GS-7 standard.
Response: Note 4 on the cover sheet, the labels on the plan and profile sheets, and
the labels on the typical sections have been revised to state that the road
classification for Stonefield Boulevard is urban collector. The centerline of the
roadway has been revised to be in compliance with the GS-7 standard.
2. Comment: Note #1 for General Construction Notes for Streets should refer to the
VDOT 2007 Road and Bridge Specifications and the VDOT 2008 Road and Bridge
Standards.
Response: Note#1 of the General Construction Notes for Streets located on Dwg.
C-3 has been revised as requested.
3. Comment: Note #9 on sheet C-S should require any springs to be capped with a
standard spring box, SB-1, SB-1 PC.
Response: Note #9 in the VDOT Notes located on Dwg. C-5 has been revised to
include the requested information.
4. Comment: Note #22 on sheet C-S should refer to streets needing to meet the
minimum service requirements in accordance with the VDOT SSAR's.
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
..................................................................................................................................................
Lynchburg•Charlottesville
Response: Note#22 in the VDOT Notes located on Dwg. C-5 has been revised to
include the requested information.
5. Comment: A list of mandatory VDOT inspections should be in the VDOT notes
section. These mandatory inspections will also be listed with the final approval of
the plans and the issuance of any permits. These need to include:
a. Installation of any enclosed drainage system before it is covered.
b. Installation of any enclosed utility placements within the right-of-way before
being covered.
c. Construction of the cuts and fills, including field density tests, before placement
of roadbed base materials.
d. A final pavement design, based on actual soil characteristics and certified tests,
shall be completed and approved before the pavement structure is placed.
e. Placement of base materials, including stone depths, consistent with the
approved pavement design,prior to placement of the paving course or courses,
followed by field density and moisture tests and the placement of a paving
course as soon as possible.
f Construction of pavement, including depth and density, upon completion as
part of the final inspection.
Response: Note #24 has been added to the VDOT Notes located on Dwg. C-5 to
include the requested information.
6. Comment: The overall plan on sheet C-7 and all other applicable sheets need to
remove stop bars from all intersection on approaches that do not have stop control.
Response: No stop bars have been removed with this submission.
7. Comment: Sheet C-8 needs to show intersection sight distances on intersections at
station 17+00 along with sight easement lines. The intersection at station 20+00
needs to label the sight easement lines.
Response: As requested the intersection site distances have been added to Dwg. C-8
of the plans for the intersection at Sta. 17+00 and the site easement lines have been
labeled for the intersection at Sta. 20+00.
8. Comment: The grading within the clear zone right of station 20+50 to station
22+00 needs to meet the clear zone requirements for recoverable area.
Response: The grading adjacent to the biofilter from Sta. 20+50 to Sta. 22+00 has
been adjusted so it meets the clear zone requirements for Stonefield Boulevard.
Please refer to Dwg. C-22 for details.
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
Lynchburg•Charlottesville
Page 2 of 4
9. Comment: North bound lanes from Hydraulic to Sperry entrance should be marked
for 2 through lanes.
Response: The pavement markings have been revised to show two through north
bound lanes from Hydraulic to the Sperry entrance. Please refer to Dwg. C-14 for
details.
10. Comment: Show stopping sight distances on the vertical curves
Response: Stopping site distances have been added to the crest vertical curves.
Please refer to Dwg. C-9 and Dwg. C-10.
11. Comment: A vertical curve needs to be added at station 15+10.
Response: A vertical curve has been added to the profile at Sta. 15+10 for
Stonefield Boulevard. Please refer to Dwg. C-9 for details.
12. Comment: All pavement markings for edge lines need to be 4". The legend calls
for 6"for the yellow lines.
Response: The width of the edge lines has been revised in the legend to show a 4"
width as requested. Please refer to Dwg. C-14 for details.
13. Comment: Locations of the street trees at intersections needs to be setback as
shown in the VDOT Road Design Manual Appendix B(1)44.
Response: The street tree locations have been revised per the requirements set forth
in the VDOT Road Design Manual Appendix B(1)44. Please refer to Dwg. C-24 for
details.
14. Comment: Show the sight lines across the biofilter landscape plan. It appears
there will be sight line obstructions for the proposed vegetation.
Response: Sight distance lines have been added for the intersection at the Sperry
entrance and the landscaping in the biofilter has been adjusted accordingly. Please
refer to Dwg. C-26 for details.
15. Comment: At this time there is not enough information to determine the adequacy
of the t-type intersection at Stonefield Blvd and proposed Second Street. This
intersection will need to be analyzed with phase 2 and possibly modified to include
a right turn lane or a roundabout.
Response: Noted.
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
Lynchburg•Charlottesville
Page 3 of 4
16. Comment: A warrants analysis will need to be submitted to VDOT and approved
by VDOT for the 4-way stop condition at the intersection of Stonefield Blvd and
Main Street prior to acceptance of the road into the state maintenance system.
Response: This note has been added to the plans. Please refer to the VDOT notes
on Dwg. C-5 for details.
I trust that the above responses and plan changes properly address the outstanding issues.
If you have any questions,please contact me.
Sincerely,
WW Associates, Inc.
��•�
Herbert F. White III, P.E.
President
cc: Thomas R. Gallagher, Edens and Avant
3040 Avemore Square Place•Charlottesville,Virginia 22911
Telephone(434)984-2700•Fax(434)978-1444
..................................................................................................................................................
Lynchburg•Charlottesville
Page 4 of 4
Niormo- *vole
Philip Custer
From: Philip Custer
Sent: Wednesday, August 03, 2011 6:58 PM
To: 'Herbert F. White Ill, P.E.'; 'Tom Gallagher'
Cc: Glenn Brooks; Gerald Gatobu; Mark Graham
Subject: Engineering review of Stonefield Blvd. and Regal Cinema
Attachments: E1_ecp swm rp_PBC_wpo-2011-00036 Stonefield Blvd. Road Plan.doc; E1_ecp swm
fsp_PBC_sdp-2011-00047 The Shops at Stonefield-Regal Cinema.doc
Good evening,
Attached are the comment letters from engineering's review of the Stonefield Blvd. (WPO-2011-00036) and Cinema
(SDP-2011-00047) plans. I apologize for the delay in getting comments to you. My workload is steadily dwindling, so
any future reviews will be much swifter. We will also do our best to help meet any deadline you may have.
Feel free to contact me if you have any questions. We can also discuss any of these comments in the meeting Gerald
has scheduled on Monday. Or, if a more immediate meeting is needed, please let me know and I can try to schedule
another time.
Thanks,
Phil
296-5832 x3072
1
Cf A
vlRclr��'
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
Project: Stonefield Blvd. Road,ESC,and SWM Plans; WPO-2011-00036
Plan preparer: Mr. Herb White,PE; W&W Associates
Owner or rep.: Albemarle Place EAAP LLC
Date received: 16 June 2011 (Traffic Study Received 1 June 2011)
Date of Comment: 3 August 2011
Engineer: Phil Custer
The Road,ESC, and SWM plans for Stonefield Blvd. (WPO-2011-00036)received on 16 June 2011,have
been reviewed. The traffic study requested during the review of preliminary site plan,but was received on
1 June 2011,has also been reviewed. The plans can be approved after the following comments have been
addressed:
A. Traffic Study Review(Unnamed SUB application)
1. Please elaborate on the figures(peak hour and ADT)used for the multiplex theater. The county
only possesses the 7th edition and an ADT per seat is not available in that edition. The only per
day traffic figure for the theater is based off of screens,which yields 4095 trips for this project.
The applicant's estimate of 1310 seems low. Also, for a PM peak hour, a theater usually generates
more entering traffic.
2. The report assumes 15%of total residential trips will be pedestrian only which seems to be overly
optimistic for this project. Please provide the source for this assumption.
3. While I understand the reasoning for the commercial-commercial reduction, I don't think it is a
sound. Please provide a source for the use of this reduction technique. It seems to me it would be
more reasonable to use an average of the three commercial ADT estimates(21850 for Phase II and
24631 for Phase III).
4. The passby capture is not justified for this type of analysis. The pass-by capture should only be
used for traffic impact analyses which this report is not, despite its title;this report looks at new
internal intersections constructed with this development,not the development's impacts on
Hydraulic and Route 29. This analysis was performed with the rezoning application and no
additional analysis of this kind is needed.
5. Please provide a graphic such similar to those in Appendix A that distributes the Phase III ADT
(vehicles,not percentages)throughout the road grid.
6. Table D2 shows that Southbound Stonefield Blvd. shows that 100% of the traffic wishes to go
straight through the intersection. I don't think this is realistic. If it is correct, a left turn lane is not
needed. I also think that more traffic will wish to turn left from Eastbound D3 drive than---16%.
7. Given the layout of the development,I do not suspect that Inglewood Drive between 1st and 3`d
Streets will be carrying any significant amount of through traffic. The—1500 vehicles a day
through this street should not preclude use of angled parking along this street. Per the variation
letter issued by the Director of Planning, angled parking may be used but the details will be subject
to the review of the planner and engineer assigned to the project. The dimensions of the angled
parking should be drawn to the standards of the Zoning Ordinance(18-4.12)and the County
Design Manual. County staff may also require the entrances to parking areas off this road to be
consolidated to simpthe sight lines for vehicles backing out ofaces.
8. County engineering does not support the use of four way stops at Sta. 15+11 and Sta. 17+11.
9. Since approximately 2/3 of all Northbound Stonefield Blvd. vehicles will be making a right turn at
3rd St., engineering review feels it is reasonable to maintain a 2nd Northbound lane from the
entrance to Sperry Marine to 3rd St. Since the fourway stop at Stonefield Blvd. and 3rd St. will
meter the traffic flow through southbound Stonefield Blvd. the second southbound lane may be
eliminated per the variation approved by the Director of Planning.
B. Road Plan Review(Unnamed SUB application)
1. The county charges $250 for the review of all public road plans. Please provide a check for$250
to the county for this review of the plan with a completed SUB Application with the appropriate
Road Plan Review box checked.
2. Please make the necessary adjustments to the plans to address comments A8 and A9.
3. On southbound Stonefield Blvd.,the wide median does not appear necessary. More stacking area
could be provided if the 2nd left turn lane was extended to the intersection with Main Street.
4. I don't believe structure 38.1 has been approved on any county plan. The approved SWM plan
has no structure from 38 to 39. Please update this set accordingly.
5. For storm drain and road profiles,please also show the existing grade line of the site before the
mass grading plan was enacted..
C.Erosion and Sediment Control Plan Review(WPO-2011-00036)
1. Because of strict requirements of Water Protection Ordinance Section 17-207.B.2, erosion and
sediment control plans for projects of such a large size must be designed to be closed out as soon
as possible. For this reason, subsequent plans cannot assume that the sediment basins constructed
with the mass grading application will remain online. Therefore, each ESC plan must be a
standalone application.
This road plan assumes that the mass grading plan has been completed and is stabilized,but still
relies on the sediment basin for ultimate sediment treatment. This ESC plan must be a standalone
plan.
2. Sediment-laden water must not enter the stormsewer system and detention facilities. Inlet
protection is more often than not an inadequate measure because the inlets are constructed well
after initial land disturbance. Even after installation, storm inlets are often bypassed because their
rim elevation is higher than the subbase and gravel around them until the final stage of
construction. Much of the runoff with this project will be directed out of the north end of the road.
The remainder will escape out the graded entrances unless diversions and ROW diversions are
utilized. A sediment trap or basin at the north end of the road and perhaps one or two on the east
side of the road south of the Sperry site appears to be necessary.
3. Please provide clearer language on the plan that the mass grading plan is to be completed prior to
the start of this application. It is important to the implementation of this plan that the area to the
west is stabilized.
4. For simplification of the design of the ESC plan, I recommend that the ESC plan for the cinema,
parking lot for the cinema, and Stonefield Blvd. are combined into one plan, assuming all projects
can be completed in 9 months.
5. Please detail how the Sperry traffic is to be dealt with during construction. How will Sta. 19+00 to
Sta. 20+50 of Stonefield Blvd. be constructed?
6. Please show the grading for the cleanwater diversion west of the road. Please remove the inlet
protection for this inlet(it should be cleanwater and therefore not need protection)and make sure
there is an adequate sump for the discharge to this facility. A ROW diversion should also be
constructed across this entrance to keep runoff from the construction area from going into this drop
inlet.
7. Because this plan will be implemented after stabilization of the mass grading plan,please confirm
there will be no construction traffic wanting to access the north end of the site.
8. Please remove all refences to the biofilter from the ESC plan sheer`
9. Please provide a completed Bond Estimate Request Form to the county engineer to receive an ESC
bond.
D. Stormwater Management Plan Review(WPO-2011-00036)
1. Every parcel that requires a stormwater management facility must sign a Stormwater Management
Facility Maintenance Agreement with the County. Please complete this form and submit it to Ana
Kilmer with a$17 recordation fee after reading the instructions online. Another agreement may be
required for the master stormwater management plan approved under WPO-2010-00023.
2. Biofilters must have 2.5' of state approved mix. Please increase the media depth by 6 inches. The
county allows a minimum of 1 ft of stone below the media mix.
3. The 5% impervious area sizing methodology for biofilters assumes that 1 ft of ponding is provided.
The 6"provided in this plan is not adequate. The goal with a biofilter treating to a 65%removal
rate is to treat the volume of water of 1"of rain falling on the impervious area. In this case,the
target volume is about 2850cf but a volume of 1110cf is provided. The simplest solution would be
to raise the rim of the DI-7 another 0.5ft.
4. Please provide outlet protection at the outlet of the storm drain system in the forebay.
5. Please provide a completed Bond Estimate Request Form to the county engineer to receive a SWM
bond.