i RE: SP201600010 Cornerstone Community Church Addition
Dear Mr.Kotarski,
On October 12, 2016,the Board of Supervisors took action on your Special Use Permit request to allow
an expansion of existing church from 180 to 250 seats under Section 10.2.2.35 of the Zoning Ordinance
on TMPs 045000000031D0 in the Rio District. The Special Use Permit was approved by the Board's
1 adoption of the attached resolution and conditions.
Please be advised that although the Albemarle County Board of Supervisors took action on the
project noted above, no uses on the property as approved above may lawfully begin until all
1 applicable approvals have been received and conditions have been met. This includes:
• compliance with conditions of the SPECIAL USE PERMIT;'
• approval of and compliance with a SITE PLAN or a SITE PLAN AMENDMENT; and
1 • approval of a ZONING COMPLIANCE CLEARANCE.
Before beginning uses as allowed by this special use permit or if you have questions regarding the above-
noted action,please contact Rebecca Ragsdale at(434)296-5832 ext. 3226.
Sincerely,
of
e > .
David Benish
(Acting)Chief of Planning
*Attachment*
RESOLUTION TO APPROVE
j SP 2016-00010 CORNERSTONE COMMUNITY CHURCH
WHEREAS,the Monticello Wesleyan Church,which is now operating nder the name of the
g
Cornerstone Community Church(the"Owner"),is the owner of Tax Map and Parcel Number 04500-00-00-
031D0(the"Property"); and
5 WHEREAS,the Owner filed an application for a special use permit to expand the existing church
building by adding 8,800 square feet of internal space, increasing the external footprint by 4,250 square feet,
and by expanding the associated parking on the Property,and the application is identified as Special Use
Permit 2016-00010 Cornerstone Community Church ("SP 2016-10"); and
1 WHEREAS,the proposed use is allowed on the Property by special use permit under Albemarle
County Code §§ 18-10.2.2.35 and 18-4.2.6(a);and
WHEREAS,on August 23,2016,after a duly noticed public hearing,the Albemarle County
Planning Commission recommended approval of SP 2016-10 with modified conditions; and
WHEREAS,on October 12,2016,the Albemarle County Board of Supervisors held a duly noticed
public hearing on SP 2016-10.
INOW,'1111EREFORE,BE IT RESOLVED that,upon consideration of the foregoing,the
Transmittal Report prepared for SP 2016-10 and all of its attachments,the information presented at the
public hearing,and the factors relevant to a special use permit in Albemarle County Code §§ 18-10.2.2.35,
18-4.2.6(a), and 18-33.8,the Albemarle County Board of Supervisors hereby approves SP 2016-10,subject
to the conditions attached hereto.
* * *
I, Claudette K.Borgersen,do hereby certify that the foregoing writing is a true,correct copy of a
Resolution duly adopted by the Board of Supervisors of Albemarle County,Virginia,by a vote of five to one,
as recorded below, at a regular meeting held on October 12,2016.
// .,— , /
j Clerk,Board of County A isors
plif
Aye Nay
Mr.Dill Y
Ms.Mallek _ N
Ms.McKeel Y
Ms.Palmer Y
1 Mr.Randolph Y
1 Mr. Sheffield Y
SP-2016-00010 Cornerstone Community Church Conditions
1. Development and use shall be in general accord with the conceptual plan titled"Cornerstone
Community Church Addition—Application Plan"prepared by Timmons Group and dated
9/16/2016(hereafter"Conceptual Plan"),as determined by the Director of Planning and the
Zoning Administrator. To be in accord with the Conceptual Plan,development and use shall
I reflect the following major elements within the development essential to the design of the
development,as shown on the Conceptual Plan:
• building orientation
• building size
Minor modifications to the plan which do not conflict with the elements above may be made
to ensure compliance with the Zoning Ordinance.
2. The site plan for this expansion shall include trees to be planted in each biofilter or similar
stormwater management facility. The tree species for these plantings shall be native species,
shall be taken from the"Large Deciduous Trees"section of the County's "Plant Canopy
Calculations"document, and shall comply with the minimum caliper size or height listed in
that document at time of planting. The trees in each biofilter pr similar stormwater
management facility shall have a total mature canopy area,as calculated by the number of
trees multiplied by the"Area of Canopy"value for each species in the"Plant Canopy
Calculations"document, of at least 50 percent of the floor area of the biofilter.
3. The area of assembly shall be limited to a maximum 250-seat sanctuary.
4. There shall be no day care center or private school on site without approval of a separate
special use permit.
5. The applicant shall obtain Virginia Department of Health approval of well and/or onsite
sewage system prior to approval of the fmal site plan.
6. All outdoor lighting shall be only full cut off fixtures and shielded to reflect light away from
all abutting properties. A lighting plan limiting light levels at all property lines to no greater
than 0.3 foot candles shall be approved by the Zoning Administrator or his/her designee
prior to approval of the fmal site plan.
7. If the use, structure,
or activity for which this special use permit is issued is not commenced
by October 12,2019,the permit shall be deemed abandoned and the authority granted
thereunder shall thereupon terminate. -