HomeMy WebLinkAboutSUB201300091 Bond Estimates 2016-12-20Cascadia - Blocks 4-7, Phase 3 Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Plan At SUB201300091 Item No. Unit Unit Cost Cost installed % compete cost remaining Delphi Lane Begin station 32+40.00 End station 35+65.Q,W road length 325.0 ft aggregate base 8. in d 325.0 ft L 31.0 ft W 470.2 ton $35.00 $16,455.83 0% $16,455.83 blotted or prime&double seal 325.0 ft L 0.0 ft W 0.0 sy $10.00 $0.00 0% $0.00 asphalt base 2. in d 325.0 ft L 26.0 ft W 103.5 tons $100.00 $10,351.25 0% $10,351.25 asphalt surface 1. in d 325.0 ft L M26.0 ft W 77.6 tons $120.00 $9,316.13 0% $9,316.13 curb CG-2 0. ft $13.00 $0.00 0% $0.00 curb CG-6 630.0 ft $15.00 $9,450.00 0% $9,450.00 sidewalk, concrete (6) 610.0 ft $17.00 $10,370.00 0% $10,370.00 ramp CG-12 2 ft $350.00 $700.00 0% $700.00 street name sign 0 each $200.00 $0.00 0% $0.00 traffic control sign 2 each $200.00 $400.00 0% $400.00 Street Landscape Each 16 each $275.00 $4,400.00 0% $4,400.00 guardrail ES @ 3000 0.0 ft $17.00 $0.00 0% $0.00 drop inlet or grate 6each $3,500.00 $21,000.00 0% $21,000.00 standard manhole frame top (not inlet) 0 each $500.00 $0.00 0% $0.00 manhole structure (per ft. rise) 26 ft $450.00 $11,700.00 0% $11,700.00 pipe, rcp, cmp (15 to 48") 15. in d 0 ES-1,2 0 EC-1 297.0 ft $35.00 $10,395.00 0% $10,395.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 193.0 ft $40.00 $7,720.00 0% $7,720.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 0.0 ft $40.00 $0.00 0% $0.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 0.0 ft $40.00 $0.00 0% $0.00 pipe, rcp, cmp (60 to 108") 96. in d 0 ES- 1,2 EC-1 ft $320.00 $0.00 0% $0.00 rip -rap, placed 2. ft d .0 it L ft W 0.0 ton $60.00 $0.00 0% $0.00 matting, EC-2 or 3 0.0 it L ft W 0.0 sy $2.00 $0.00 0% $0.00 clear and grub (for wooded sites) 0.0 ft L ft W 0.0 acre $24,000.00 $0.00 0% $0.00 cut grading 200.0 cy $4.00 $28,800.00 0% $28,800.00 fill grading 0.0 cy $9.00 $0.00 0% $0.00 as -built drawings (1 k+ price per 0.1 mi.) 325.0 ft L 0.06155 mi. 1 Isum $2,000.00 $3,000.00 0% $3,000.00 survey and layout (price per 0.1 mi.) 325.0 ft L 0.06155 mi. 1 Isum $2,000.00 $3,000.00 0% $3,000.00 mobilization r 1 Isum $5,000.00 $5,000.00 0% $5,000.00 materials testing 325.0 ft L 0.65 inc of 500' 2 each $200.00 $340.00 0% $340.00 compaction testing 325.0 ft L 0.65 inc of 500' 2 each $200.00 $340.00 0% $340.00 CBR tests (1 every 0.1 mi. per road) 325.0 ft L 0.65 inc of 500' 2 each $200.00 $340.00 0% $340.00 stone depth inspections 325.0 ft L 0.65 inc of 500' 2 each $200.00 $340.00 0% $340.00 pavement inspections 325.0 ft L 0.65 inc of 500' 2 each $200.00 $340.00 0% $340.00 pipe and drainage video inspections 490 ft $1.00 $490.00 0% $490.00 VDOT surety (1 lane) 325.0 ft L 0.06155 mi. 2 Lanes $2,000.00 $2,462.12 0% $2,462.12 VDOT maintenance fee (1 In rd, 1 yr) 325.0 ft L 0.06155 mi. 2 Lanes $150.00 $184.66 0% $184.66 VDOT admin. Cost recovery fee(1 lane) 325.0 ft L 0.06155 mi. 2 Lanes $100.00 $373.11 0% $373.11 cost sum $157,268.09 $157,268.09 contingency $15,726.81 $15,726.81 Total $173,000 $173,000 0:\Users\mwentland\Documents\SUB201300091 Cascadia 4-7 Ph3 RP bond est 12-20-16.xls 12/20/2016 Cascadia - Blocks 4-7, Phase 3 Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Plan # SUB201300091 Item No. Unit Unit Cost Cost installed % compete cost remaining Glissade Lane Begin station 10+50.00 End station 14+25.OW road length 375.0 tt aggregate base 8. in d tt W 375.0 ft LjftW 525.0 ton $35.00 $18,375.00 0% $18,375.00 blotted or prime&double seal 375.0 ft Ltt W 0.0 sy $10.00 $0.00 0% $0.00 asphalt base 2. in d 375.0 ft Ltt W 143.6 tons $100.00 $14,355.47 0% $14,355.47 asphalt surface 1. in d 375.0 ft L 86.1 tons $120.00 $10,335.94 0% $10,335.94 curb CG-2 0.0 ft $13.00 $0.00 0% $0.00 curb CG-6 730.0 ft $15.00 $10,950.00 0% $10,950.00 sidewalk, concrete (6) 720.0 ft $17.00 $12,240.00 0% $12,240.00 ramp CG-12 3 ft $350.00 $1,050.00 0% $1,050.00 street name sign 0 each $200.00 $0.00 0% $0.00 traffic control sign 5each $200.00 $1,000.00 0% $1,000.00 Street Landscape Each 16 each $275.00 $4,400.00 0% $4,400.00 guardrail ES @ 3000 0.0 ft $17.00 $0.00 0% $0.00 drop inlet or grate 8 each $3,500.00 $28,000.00 0% $28,000.00 standard manhole frame top (not inlet) 0 each $500.00 $0.00 0% $0.00 manhole structure (per ft. rise) 50 ft $450.00 $22,500.00 0% $22,500.00 pipe, rcp, cmp (15 to 48") 15A in d r 0 ES-1,2 0 EC-1 274.0 it $35.00 $9,590.00 0% $9,590.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 216.0 it $40.00 $8,640.00 0% $8,640.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 0.0 ft $40.00 $0.00 0% $0.00 pipe, rcp, cmp (15 to 48") 18. in d 1 ES-1,2 0 EC-1 0.0 ft $40.00 $0.00 0% $0.00 pipe, rcp, cmp (60 to 108") 96. in d 0 ES-1,2 0 EC-1 hL O.Ojtt $320.00 $0.00 0% $0.00 rip -rap, placed 2. ft d P0.0 ft L 0.0 ft W 0.0 ton $60.00 $0.00 0% $0.00 matting, EC-2 or 3 0.0 ft L tt W 0.0 sy $2.00 $0.00 0% $0.00 clear and grub (for wooded sites) L 0.0 ft L tt W 0.0 acre $24,000.00 $0.00 0% $0.00 cut grading cy $4.00 $12,000.00 0% $12,000.00 fill grading cy $9.00 $10,350.00 0% $10,350.00 as -built drawings (1k+ price per 0.1 mi.) 375.0 ftL 0.07102 mi. 11sum $2,000.00 $3,000.00 0% $3,000.00 survey and layout (price per 0.1 mi.) 375.0 ft L 0.07102 mi. 1 Isum $2,000.00 $3,000.00 0% $3,000.00 mobilization -Isum $5,000.00 $5,000.00 0% $5,000.00 materials testing 375.0 ft L 0.75 inc of 500' 2 each $200.00 $360.00 0% $360.00 compaction testing 375.0 ft L 0.75 inc of 500' 2 each $200.00 $360.00 0% $360.00 CBR tests (1 every 0.1 mi. per road) 375.0 ft L 0.75 inc of 500' 2 each $200.00 $360.00 0% $360.00 stone depth inspections 375.0 ft L 0.75 inc of 500' 2 each $200.00 $360.00 01/6 $360.00 pavement inspections 375.0 ft L 0.75 inc of 500' 2 each $200.00 $360.00 0 % $360.00 pipe and drainage video inspections 490 ft $1.00 $490.00 0 % $490.00 MOT surety (1 lane) 375.0 ft L 0.07102 mi. Lanes $2,000.00 $2,940.91 01/6 $2,840.91 MOT maintenance fee (1 In rd, 1 yr) 375.0 ft L 0.07102 mi. jk�2 Lanes $150.00 $213.07 01/6 $213.07 MOT admin. Cost recovery fee(1 lane) 375.0 ft L 0.07102 mi. Lanes $100.00 $392.05 0 % $392.05 $180,522.43 $180,522.43 cost sum contingency $18,052.24 $18,052.24 Total $198,580 $198,580 :rs\mwentland\Documents\SUB201300091 Cascadia 4-7 Ph3 RP bond est 12-20-16.xls 12/20/2016 Cascadia - Blocks 4-7, Phase 3 Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer) Plan # SUB201300091 Item No. Unit Unit Cost Cost installed % compete cost remaining Flat Waters Lane Begin station 10+15.00 End station 13+10._U road length 295.0 tt aggregate base 8. in d tt W 295.0 ft LjftW 413.0 ton $35.00 $14,455.00 0% $14,455.00 blotted or prime&double seal 295.0 ft Ltt W 0.0 sy $10.00 $0.00 0% $0.00 asphalt base 2. in d 295.0 ft Ltt W 90.3 tons $100.00 $9,034.38 0% $9,034.38 asphalt surface 1. in d 295.0 ft L 67.8 tons $120.00 $8,130.94 0% $8,130.94 curb CG-2 0.0 ft $13.00 $0.00 0% $0.00 curb CG-6 570.0 ft $15.00 $8,550.00 0% $8,550.00 sidewalk, concrete (6) 230.0 ft $17.00 $3,910.00 0% $3,910.00 ramp CG-12 2 ft $350.00 $700.00 0% $700.00 street name sign 2 each $200.00 $400.00 0% $400.00 traffic control sign 4 each $200.00 $800.00 0% $800.00 Street Landscape Each 0 each $275.00 $0.00 0% $0.00 guardrail ES @ 3000 0.0 ft $17.00 $0.00 0% $0.00 drop inlet or grate 0 each $3,500.00 $0.00 0% $0.00 standard manhole frame top (not inlet) 0 each $500.00 $0.00 0% $0.00 manhole structure (per ft. rise) 0 ft $450.00 $0.00 0% $0.00 pipe, rcp, cmp (15 to 48") 15A in d r 0 ES-1,2 0 EC-1 0.0 it $35.00 $0.00 0% $0.00 pipe, rcp, cmp (15 to 48") 24. in d 0 ES-1,2 0 EC-1 0.0 it $50.00 $0.00 0% $0.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 0.0 ft $40.00 $0.00 0% $0.00 pipe, rcp, cmp (15 to 48") 18. in d 0 ES-1,2 0 EC-1 0.0 ft $40.00 $0.00 0% $0.00 pipe, rcp, cmp (60 to 108") 96. in d 0 ES-1,2 0 EC-1 hL O.Ojtt $320.00 $0.00 0% $0.00 rip -rap, placed 2. ft of ft L 0.0 ft W 0.0 ton $60.00 $0.00 0% $0.00 matting, EC-2 or 3 0.0 ft L tt W 0.0 sy $2.00 $0.00 0% $0.00 clear and grub (for wooded sites) ` 0.0 ft L tt W 0.0 acre $24,000.00 $0.00 0% $0.00 cut grading cy $4.00 $13,200.00 0% $13,200.00 fill grading cy $9.00 $0.00 0% $0.00 as -built drawings (1k+ price per 0.1 mi.) 295.0 ftL 0.05587 mi. 11sum $2,000.00 $3,000.00 0% $3,000.00 survey and layout (price per 0.1 mi.) 295.0 ft L 0.05587 mi. 1 Isum $2,000.00 $3,000.00 0% $3,000.00 mobilization -Isum $5,000.00 $5,000.00 0% $5,000.00 materials testing 295.0 ft L 0.59 inc of 500' 2 each $200.00 $320.00 0% $320.00 compaction testing 295.0 ft L 0.59 inc of 500' 2 each $200.00 $320.00 0% $320.00 CBR tests (1 every 0.1 mi. per road) 295.0 ft L 0.59 inc of 500' 2 each $200.00 $320.00 0% $320.00 stone depth inspections 295.0 ft L 0.59 inc of 500' 2 each $200.00 $320.00 01/6 $320.00 pavement inspections 295.0 ft L 0.59 inc of 500' 2 each $200.00 $320.00 0 % $320.00 pipe and drainage video inspections 0 ft $1.00 $0.00 0 % $0.00 VDOT surety (1 lane) 295.0 ft L 0.05587 mi. 2 Lanes $2,000.00 $2,234.85 0% $2,234.85 VDOT maintenance fee (1 In rd, 1 yr) 295.0 ft L 0.05587 mi. Lanes $150.00 $167.61 01/6 $167.61 VDOT admin. Cost recovery fee(1 lane) 295.0 ft L 0.05587 mi. Lanes $100.00 $361.74 0 % $361.74 $74,544.52 $74,544.52 cost sum contingency $7,454.45 $7,454.45 Total $82,000 $82,000 :rs\mwentland\Documents\SUB201300091 Cascadia 4-7 Ph3 RP bond est 12-20-16.xls 12/20/2016