Road and Drainage plan review
Project title: Belvedere Phase IV A - Road Plans
Project file number: SUB201600212
Plan preparer: Collins Engineering [scott@collins-engineering.com]
Owner or rep.: Belvedere Station Land Trust
Date Received: 7 November 2016
Date of comments: 20 December 2016
Engineering has reviewed your plans and has the following comments:
1. The professional seals need to be signed and dated (Ref. 18-32.6.1).
2. Existing easements (access, drainage, sight, sanitary, etc.) with deed book, locations and
dimensions to be shown.
3. Show all steep slopes (some are not shown), and the correct type (hatching).
4. There are steep slopes in the disturbed area (lots 239 & 240) that are to be preserved (Ref. 18-
30.7.4).
5. Plans indicate "...steep slopes shall be field verified." Verification must be provided prior to road
plan approval and shall be field verified and certified by a licensed land surveyor. Aerial survey as
a measure of improved topographic accuracy is not deemed acceptable.
6. The side notes state that there is no retaining wall, but a proposed wall (along back lots) is
shown in the plans.
7. The height of the retaining wall exceeds 6' in the steep slope area, and must be staggered (Ref.
18-30.7.5).
8. Provide wall details and design certified by professional engineer.
9. 15" stormwater pipe is shown going under, or though wall; Show details at penetration, and
include in wall design.
10. Provide safety railing on back lots for walls greater than 4 feet (requirement).
11. Refer to the following design detail/calc to make sure the required widths are met (Design
Manual, section 6) for storm line STR 6 to STR 1 (end wall):
Engineering Review Comments
Page 2 of 3
E k5E11E%T KroTH . DIANaTER � 1, + l q u-{' 1 = 10' 1 till .l
12. Streets signs needed for traffic control (shown and labeled): speed limit on all streets, stop signs
at all intersections. Street sign needed, typ. placed opposite stop sign.
13. Street sign needed indicating "no parking" along turnaround, and sign indicating street is not a
though street (Sect. 18-32.7.2).
Comments are pending from the Albemarle County Service Authority, and VDOT, and will be forwarded
along as they are received.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
Engineering Review Comments
Page 3 of 3
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
hlt2://www.albemarle.org/deptforms.asp?department=cdengao
If you have any questions or concerns, please contact me either by email (diameskalbemarle.org) or by
phone at 434-296-5832.
Sincerely,
David James
Civil Engineer I
File: SUB201600212 Belvedere Phase IVA - Road Plans comments 12-20.doc