HomeMy WebLinkAboutSDP201600020 Calculations 2016-05-31 telgiarc May 31,2016 RE: Texas Roadhouse Water Supply Test and Site Flow Analysis Charlottesville,VA The requested water supply test and site flow analysis for the subject project is detailed in the attached report. Flow Test Results: Date/Time Performed:August 11th 2015 Fire Hydrant Flow Test Effective Point:At the base of the pressure hydrant (Hydrant#10546) Static=68 psi; Residual=62 psi @ 1744 gpm Available Flow @ 20 psi (Node 5)=4880 gpm Static Pressure @ BOR:57 psi Available Pressure @ 295 gpm at the BOR = 57 psi Available Pressure @ 730 gpm at the BOR = 54 psi 10%Safety Factor=-7 psi Test Elevation relative to BOR: Even with proposed planned finished floor elevation (488 Ft.AMSL) A fire pump WILL NOT be required. Backflow Prevention Requirements: Double Check Detector Assembly(DCDA) Device assumed for deduct in calculations: A 6-inch, Ames 3000SS, double check detector assembly backflow preventer. This needs to be approved by the Civil Engineer.This is for recommendation only and NOT to be used for construction or exact main locations. Should you have any questions regarding this matter,do not hesitate to contact me. Sincerely, Eliseo Gutierrez Fire Protection Consultant ATTACHMENTS: Attachment#1—Location Sketch Attachment#2—Area Water Map/AHJ Flow Test Results Attachment#3—Water Supply Graph—Fire Sprinkler Calculations Attachment#4—Water Supply Graph—Fire Flow Calculations Teigian Corporation 10230 South 50th P1.;Tempe;AZ•Tel:480-753-5444 •Fax.480,753-5450 Teirgiar inc1€udes the entities of Telgian Corporation, TVA l=ire A Life Safety, Inc.and Fire Materials Group,t,LC I 0 I a) v 0 00 1 C 1 '+r ) XI W 1 1 1 _c --- N. 1 U 4--, 1 N 1 Cn O I J 0 J 1 N crS [ H a U Z v o I ? Lo Jcc 0 co 1 J m =` 0 1 0 oC oI _z T— al 4t -06 II as co OI (� a) co c cc i• r— ccs a I cn E • w - 1 cLSU I Q 1 I 8 1 a) I N zr)E cz 2 � � Q" o -0 I a) Q �.( .co_ C V rn fk a) a) we umH C I OWO a) c_n as 0 PI �,'t � 0N' .0 am CO 0 L7 -o -0 Q4,N I— O a) A N 4- C `- 'V) N ++ E U = O �_ a +r fC C ` o II o ~ 0 0 co Z O c U O O C O ( %s) . R Attachment #2 - Area Water Map / AHJ Finw Test Results Albemarle County •i Hydrant Flow Date of Report Service Autr 8/11/2015 5°4"in9eCtAneMng Test Report ma Six/Snap 1404dC.hallolleavOle.VA 27911113419//4.11 Location Rio Rd and 29 Date and Time of Test 8/11/2015 1:00:00 PM Minutes of Flow 2 Pipe Size(Inches) 8 Pressure Hydrant 10546 Static Pressure(psi) 68 Residual Pressure(psi) 62 Flow Hydrant#1 12667 Pltot Pressure#1(psi) 42 Test Flow 1 906 Flow Hydrant#2 12673 Pltot Pressure#2(psi) 36 Test Flow 2 838 Flow Hydrant#3 Pitot Pressure#3(psi) Test Flow 3 0 Total Estimated Flow(gpm) 1744 Estimated Consumption(gal) 3488 ........... AWWA Q20 Calculation(gpm) 0 (Value of zero indicates insufficient pressure drop for calculation) Comments Both hydrants were fully open For method of calculating pitot flow with a diffuser:see eq.13,Waiski and Lutes article 1990 Journal Management and Operations AWWA (All tests conducted using 2.5 discharge outlet unless otherwise specified) Signature of Tester: isic, 2 Ns) I\ ...... 7 ..--,,...... , •,,_ g . ; Zft r OM= %fro .r. it ci 4ii N 0 ' . 0 4 4410 ( ,r1 -.6 (2, .E c a . .E - • - 0 :i. 2 ..) V i .13 c`4 .' ''' 1, t C ' °•• .! f a) • .0 2 2 = = ., 1- k g ; t (.-() a , 1111/4. J . 3 . TOC141 /6 = ° qIN ' D / 4. ,... _... 8 3 41) . , 14/- ,..-, ----- so ‘; / ...44: 4.— ..F7 a > ,! .,_ IQ a) 42/ W 0 - Ls 4/ / itsj u5o. ; •••I , . 7 VII:71 / C•1 V = 0 • 4-, . tit .1 . • . .) c--- / / co 4 i / i 0 41, Ott --- r / C.I -i.11 qt . ig, CC ...D1., , / 0 ' ..^... / (1) . ,- ,-,444*, CZ V! X Mr- 1,,;„10. i -..orir a) / at a ,_. /I II m ou_ 411111' ----'---- / S _lk g 54 ' 110 - 1101 11111 -11 V V4 '..1 /630V I-EG> Sh".---) %-, 2 . 0?1 0 -.. o co 1 7 LI •litlik ,. . /------ „ c.... --i •. NI a) 0 , no. . .,. , f• ,,,.. ,.. .. . .4., ...t..7.N. ...4. , . -:' , - ;17-1:,,,,,,,, .- • • , - / f --.4' ' LPP'-''Ca f `•%%, , , • . i • ,if i / .• ,-, 4( "// 15 :4 64 '- ' . 4 0 ,.. -.•., • •,- •,,,i „-- (..) .44 . ...- ma) VEl'Eri4 b-gg; PE . .. rggzPtb 7", 144t pr, ,:.‘..,)\•:‘..,.,‘,...,r:1,2\i. , ,,) „\,,, LI:;f.-r P fi .-E,EI,028 '' '' ni,„`\'•11...- -.01/44" .il4. .ErKit „. . nmcc.gwoEr bg-5k2ggVm • Fal.,2;apo . . , —.•D=(-,.0 , ,ou0EF • V i N! / Is! V>iinl' ! . . \ - I YERtiV /111#14 / .,. • -._ co . _ = 2 t‘ . . , DMo ' '.,'' al- \ \ / 2 \\ ATTACH!' -`'T#3 PAGE 1 OF 5 WATER SUPPLY SITE SURVEY stove PROJECT:Texas Roadhouse „„, ioi FIRE SPRINKLER DEMAND LOCATION:455 Albermale Square Albermale County CITY/STATE:Charlottesville.VA Gauge Static(psi) Residual(psi) Flow(gpm) Hydrant Building FFE(ft) Elevation(ft) 68 62 1744 488 488 Outlet Outlet Outlet Outlet Hydrant Hydrant Hydrant - Hydrant Pitot#3 Pitot#4 Diameter#1 pilot#1(psi) Diameter Pitot#2(psi) Diameter#3 Diameter Coefficient Coefficient#1 Coefficient#2 Coefficient#3 (psi) (psi) (in) #2(in) (in) #4(in) #4 2.5 -- 42 2.5 -- 36 Gauge Hydrant Location: Hydrant#10546 Flow Hydrant Location: Hydrant#12667 and Hydrant#12673 Test By: Albermale County Service Authority Date: 8/11/2015 Time: 1:00 P.M. Backflow Prevention: Size: 6-inch Type: Double Check Detector Mfg: Ames Model: 3000SS Water Meter: Size: None Mfg: Model: 70 ------------------------- ♦ Observed Flow Test Point 60 --- ------`—+:9 — - ®--..1.............._ -s s--- ==''.�� • ...... .Raw Water Flow Test — • • #4 Below Q • 295gpm @ 32 psi '._ — —#7 Below N 730gpm @ 22psi #9 Below • Target Demand ■ Target Demand 0 0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 Flow(gpm) Flow Rate(gpm) 0 295 ( 730 I Calculated Demands Static(psi) Residual(psi) gpm psi 1. Pressure available at test 68 68.0 67.0 295 32 2. Elevation Adjustment 0 Included in Included in Calcs 730 22 Calcs 3. Pressure loss due to friction 0 Included in Included in Calcs Calcs Pressure at base of riser 4. upstream of BFP&meter 68 67 63.5 5. BFP loss/preload -4 -3 -2.5 Additional Demands 6. Water meter loss 0 0 0 Pressure at base of riser gpm psi 7. downstream of BFP&meter 64 61 8. Safety factor -7 -7 -7 9. Total base of riser pressure 57 57 54 Telgian Corporation SPRINKLER SYSTEM HYDRAULIC ANALYSIS Page 2 ' DATE: 5/27/2016 \HASS\TEXAS ROAD HOUSE_CHAR TESVILLE, VA. SDF Now,JOB TITLE : Attachment #3 WATER SUPPLY DATA SOURCE STATIC RESID . FLOW AVAIL. TOTAL REQ' D NODE PRESS . PRESS . @ PRESS . @ DEMAND PRESS . TAG (PSI) (PSI) (GPM) (PSI) (GPM) (PSI) SRC 68 . 0 62 . 0 1744 . 0 67 . 8 295 . 0 AGGREGATE FLOW ANALYSIS : TOTAL FLOW AT SOURCE 295 . 0 GPM TOTAL HOSE STREAM ALLOWANCE AT SOURCE 0 . 0 GPM OTHER HOSE STREAM ALLOWANCES 295 . 0 GPM TOTAL DISCHARGE FROM ACTIVE SPRINKLERS 0 . 0 GPM NODE ANALYSIS DATA NODE TAG ELEVATION NODE TYPE PRESSURE DISCHARGE (FT) (PSI) (GPM) BOR 488 . 0 HOSE STREAM 67 . 1 195 . 0 1 488 . 0 - - - - 67 . 3 - - - 2 488 . 0 - - - - 67 . 5 - - - 3 488 . 0 - - - - 67 . 5 - - - 4 488 . 0 - - - - 67 . 5 - - - 5 488 . 0 - - - - 67 . 8 - - - 6 488 . 0 - - - - 67 . 8 - - - 7 488 . 0 - - - - 67 . 5 - - - 8 488 . 0 - - - - 67 . 5 - - - H1 488 . 0 HOSE STREAM 67 . 4 100 . 0 H2 488 . 0 - - - - 67 . 8 - - - SRC 488 . 0 SOURCE 67 . 8 295 . 0 SPRINKLER SYSTEM HYDRAULIC ANALYSIS Page 3 DATE': 5/27/2016 \HASS\TEXAS ROAD HOUSE_CHAR 'TESVILLE, VA. SDF JOB TITLE : Attachment #3 PIPE DATA PIPE TAG Q (GPM) DIA (IN) LENGTH PRESS . END ELEV. NOZ . PT DISC . VEL (FPS) HW (C) (FT) SUM. NODES (FT) (K) (PSI) (GPM) FL/FT (PSI) Pipe : 1 -195 . 0 6 . 280 PL 41 . 00 PF 0 . 2 BOR 488 . 0 H. S . 67 . 1 195 . 0 2 . 0 140 FTG 2E2TG PE 0 . 0 1 488 . 0 0 . 0 67 . 3 0 . 0 0 . 001 TL 184 . 00 PV Pipe : 2 -195 . 0 8 . 390 PL 452 . 00 PF 0 . 1 1 488 . 0 0 . 0 67 . 3 0 . 0 1 . 1 140 FTG ET PE 0 . 0 2 488 . 0 0 . 0 67 . 5 0 . 0 0 . 000 TL 542 . 00 PV Pipe : 3 -195 . 0 24 . 980 PL 438 . 00 PF 0 . 0 2 488 . 0 0 . 0 67 . 5 0 . 0 0 . 1 140 FTG T PE 0 . 0 3 488 . 0 0 . 0 67 . 5 0 . 0 0 . 000 TL 679 . 00 PV Pipe : 4 -195 . 0 8 . 390 PL 95 . 00 PF 0 . 0 3 488 . 0 0 . 0 67 . 5 0 . 0 1 . 1 140 FTG T PE 0 . 0 4 488 . 0 0 . 0 67 . 5 0 . 0 0 . 000 TL 154 . 00 PV Pipe : 5 -295 . 0 8 . 390 PL 470 . 00 PF 0 . 3 4 488 . 0 0 . 0 67 . 5 0 . 0 1 . 7 140 FTG ---- PE 0 . 0 5 488 . 0 0 . 0 67 . 8 0 . 0 0 . 001 TL 470 . 00 PV Pipe : 6 -295 . 0 8 . 390 PL 1 . 00 PF 0 . 0 5 488 . 0 0 . 0 67 . 8 0 . 0 1 . 7 140 FTG ---- PE 0 . 0 SRC 488 . 0 SRCE 67 . 8 (N/A) 0 . 001 TL 1 . 00 PV Pipe : 7 0 . 0 8 . 390 PL 482 . 00 PF 0 . 0 5 488 . 0 0 . 0 67 . 8 0 . 0 0 . 0 140 FTG 3ET PE 0 . 0 6 488 . 0 0 . 0 67 . 8 0 . 0 0 . 000 TL 634 . 00 PV Pipe : 8 0 . 0 8 . 390 PL 103 . 00 PF 0 . 0 6 488 . 0 0 . 0 67 . 8 0 . 0 0 . 0 140 FTG E PE 0 . 0 H2 488 . 0 0 . 0 67 . 8 0 . 0 0 . 000 TL 134 . 00 PV Pipe : 9 100 . 0 8 . 390 PL 78 . 00 PF 0 . 0 4 488 . 0 0 . 0 67 . 5 0 . 0 0 . 6 140 FTG T PE 0 . 0 7 488 . 0 0 . 0 67 . 5 0 . 0 0 . 000 TL 137 . 00 PV Pipe : 10 100 . 0 8 . 390 PL 229 . 00 PF 0 . 0 7 488 . 0 0 . 0 67 . 5 0 . 0 0 . 6 140 FTG T PE 0 . 0 8 488 . 0 0 . 0 67 . 5 0 . 0 0 . 000 TL 288 . 00 PV Pipe : 11 100 . 0 6 . 280 PL 158 . 00 PF 0 . 1 8 488 . 0 0 . 0 67 . 5 0 . 0 1 . 0 140 FTG 2E PE 0 . 0 H1 488 . 0 H. S . 67 . 4 100 . 0 0 . 000 TL 202 . 00 PV SPRINKLER SYSTEM HYDRAULIC ANALYSIS Page 2 . DATE: 5/27/2016 \HASS\TEXAS ROAD HOUSE CHAR YTESVILLE, VA. SDF JOB TITLE : Attachment #3 WATER SUPPLY DATA SOURCE STATIC RESID . FLOW AVAIL . TOTAL REQ'D NODE PRESS . PRESS . @ PRESS . @ DEMAND PRESS . TAG (PSI) (PSI) (GPM) (PSI) (GPM) (PSI) SRC 68 . 0 62 . 0 1744 . 0 66 . 8 730 . 0 AGGREGATE FLOW ANALYSIS : TOTAL FLOW AT SOURCE 730 . 0 GPM TOTAL HOSE STREAM ALLOWANCE AT SOURCE 0 . 0 GPM OTHER HOSE STREAM ALLOWANCES 730 . 0 GPM TOTAL DISCHARGE FROM ACTIVE SPRINKLERS 0 . 0 GPM NODE ANALYSIS DATA NODE TAG ELEVATION NODE TYPE PRESSURE DISCHARGE (FT) (PSI) (GPM) BOR 488 . 0 HOSE STREAM 63 . 3 480 . 0 1 488 . 0 - - - - 64 . 4 - - - 2 488 . 0 - - - - 65 . 1 - - - 3 488 . 0 - - - - 65 . 2 - - - 4 488 . 0 - - - - 65 . 4 - - - 5 488 . 0 - - - - 66 . 8 - - - 6 488 . 0 - - - - 66 . 8 - - - 7 488 . 0 - - - - 65 . 3 - - - 8 488 . 0 - - - - 65 . 2 - - - H1 488 . 0 HOSE STREAM 64 . 8 250 . 0 H2 488 . 0 - - - - 66 . 8 - - - SRC 488 . 0 SOURCE 66 . 8 730 . 0 SPRINKLER SYSTEM HYDRAULIC ANALYSIS Page 3 DATE : 5/27/2016 \HASS\TEXAS ROAD HOUSE_CHARe2'TESVILLE, VA. SDF JOB TITLE : Attachment #3 PIPE DATA PIPE TAG Q (GPM) DIA (IN) LENGTH PRESS . END ELEV. NOZ . PT DISC . VEL (FPS) HW (C) (FT) SUM. NODES (FT) (K) (PSI) (GPM) FL/FT (PSI) Pipe : 1 -480 . 0 6 . 280 PL 41 . 00 PF 1 . 1 BOR 488 . 0 H . S . 63 . 3 480 . 0 5 . 0 140 FTG 2E2TG PE 0 . 0 1 488 . 0 0 . 0 64 . 4 0 . 0 0 . 006 TL 184 . 00 PV Pipe : 2 -480 . 0 8 . 390 PL 452 . 00 PF 0 . 8 1 488 . 0 0 . 0 64 . 4 0 . 0 2 . 8 140 FTG ET PE 0 . 0 2 488 . 0 0 . 0 65 . 1 0 . 0 0 . 001 TL 542 . 00 PV Pipe : 3 -480 . 0 24 . 980 PL 438 . 00 PF 0 . 0 2 488 . 0 0 . 0 65 . 1 0 . 0 0 . 3 140 FTG T PE 0 . 0 3 488 . 0 0 . 0 65 . 2 0 . 0 0 . 000 TL 679 . 00 PV Pipe : 4 -480 . 0 8 . 390 PL 95 . 00 PF 0 . 2 3 488 . 0 0 . 0 65 . 2 0 . 0 2 . 8 140 FTG T PE 0 . 0 4 488 . 0 0 . 0 65 . 4 0 . 0 0 . 001 TL 154 . 00 PV Pipe : 5 -730 . 0 8 . 390 PL 470 . 00 PF 1 . 4 4 488 . 0 0 . 0 65 . 4 0 . 0 4 . 2 140 FTG ---- PE 0 . 0 5 488 . 0 0 . 0 66 . 8 0 . 0 0 . 003 TL 470 . 00 PV Pipe : 6 -730 . 0 8 . 390 PL 1 . 00 PF 0 . 0 5 488 . 0 0 . 0 66 . 8 0 . 0 4 . 2 140 FTG ---- PE 0 . 0 SRC 488 . 0 SRCE 66 . 8 (N/A) 0 . 003 TL 1 . 00 PV Pipe : 7 0 . 0 8 . 390 PL 482 . 00 PF 0 . 0 5 488 . 0 0 . 0 66 . 8 0 . 0 0 . 0 140 FTG 3ET PE 0 . 0 6 488 . 0 0 . 0 66 . 8 0 . 0 0 . 000 TL 634 . 00 PV Pipe : 8 0 . 0 8 . 390 PL 103 . 00 PF 0 . 0 6 488 . 0 0 . 0 66 . 8 0 . 0 0 . 0 140 FTG E PE 0 . 0 H2 488 . 0 0 . 0 66 . 8 0 . 0 0 . 000 TL 134 . 00 PV Pipe : 9 250 . 0 8 . 390 PL 78 . 00 PF 0 . 1 4 488 . 0 0 . 0 65 . 4 0 . 0 1 . 5 140 FTG T PE 0 . 0 7 488 . 0 0 . 0 65 . 3 0 . 0 0 . 000 TL 137 . 00 PV Pipe : 10 250 . 0 8 . 390 PL 229 . 00 PF 0 . 1 7 488 . 0 0 . 0 65 . 3 0 . 0 1 . 5 140 FTG T PE 0 . 0 8 488 . 0 0 . 0 65 . 2 0 . 0 0 . 000 TL 288 . 00 PV Pipe : 11 250 . 0 6 . 280 PL 158 . 00 PF 0 . 3 8 488 . 0 0 . 0 65 . 2 0 . 0 2 . 6 140 FTG 2E PE 0 . 0 Hl 488 . 0 H . S . 64 . 8 250 . 0 0 . 002 TL 202 . 00 PV ATTACHM 'T#4 PAGE 1 OF 3 WATER SUPPLY SITE SURVEY Name PROJECT:Texas Roadhouse FIRE HYDRANT DEMAND LOCATION:455 Albermale Sauare Albermale County CITY/STATE:Charlottesville,VA Gauge Static(psi) Residual(psi) flow(gpm) Hydrant Building FFE(ft) Elevation(ft) 68 62 1744 488 488 Outlet Outlet Outlet Hydrant Outlet Hydrant Hydrant Hydrant Pitot#3 Pitot#4 Diameter#1Cocient#1 Pitot#1(psi) Diameter coefficient#2 Pitot#2(psi) Diameter#3 Coefficient Diameter Coefficient effi (in) #2(in) (in) #3 (Psi) #4(In) #4 (Psi) 2.5 0.9 27 2.5 0.9 27 Gauge Hydrant Location: Hydrant#10546 Flow Hydrant Location: Hydrant#12667 and Hydrant#12673 Test By: Albermale County Service Authority Date: 8/11/2015 Time: 1:00 P.M. Backflow Prevention: Size: Type: Mfg: Model: Water Meter: Size: Mfg: Model: 70 ------------------------------- _• A Observed Flow Test Point 60 -- -- ------ ®®® ���•Raw Water Flow Test 50 — --------------- —'�r�--- • a, 40 ------------------------ 4.•. - • #4 Below (142: 30 ----------- -- --®---®®®®®®—®— —#7 Below 20 ------- --- — -------- #9 Below 10 ®--------- ------ • Fire Hydrant Demand 0 0 400 800 1200 1600 2000 2400 2800 3200 3600 4000 Flow(gpm) Distributed Fire Flows (gpm) 0 4880 I Static(psi) Residual(psi) Total Fire Flow Demand 1. Pressure available at test 68 28.0 gpm psi 2. Elevation Adjustment 0 Included in 4880 20 Calcs 3. Pressure loss due to friction 0 Included in Calcs Pressure at remote hydrants 4. upstream of BFP&meter 68 20 5. BFP loss/preload 0 0 6. Water meter loss 0 0 Pressure at remote hydrants 7. downstream of BFP&meter 68 20 8. Safety factor 0 0 Available combined pressure at 9. Total Fire Flow Demand 68 20.0 Telgian Corporation SPRINKLER SYSTEM HYDRAULIC ANALYSIS Page 2 DATE: 5/31/2016 \HASS\TEXAS ROAD HOUSE_CHAR 'TESVILLE, VA. SDF Neigo,JOB TITLE : Attachment #4 WATER SUPPLY DATA SOURCE STATIC RESID . FLOW AVAIL . TOTAL REQ ' D NODE PRESS . PRESS . @ PRESS . @ DEMAND PRESS . TAG (PSI) (PSI) (GPM) (PSI) (GPM) (PSI) SRC 68 . 0 62 . 0 1744 . 0 20 . 1 5360 . 0 AGGREGATE FLOW ANALYSIS : TOTAL FLOW AT SOURCE 5360 . 0 GPM TOTAL HOSE STREAM ALLOWANCE AT SOURCE 0 . 0 GPM OTHER HOSE STREAM ALLOWANCES 5360 . 0 GPM TOTAL DISCHARGE FROM ACTIVE SPRINKLERS 0 . 0 GPM NODE ANALYSIS DATA NODE TAG ELEVATION NODE TYPE PRESSURE DISCHARGE (FT) (PSI) (GPM) BOR 488 . 0 HOSE STREAM 17 . 3 480 . 0 1 488 . 0 - - - - 18 . 3 - - - 2 488 . 0 - - - - 19 . 1 - - - 3 488 . 0 - - - - 19 . 1 - - - 4 488 . 0 - - - - 19 . 3 - - - 5 488 . 0 HOSE STREAM 20 . 0 4880 . 0 6 488 . 0 - - - - 20 . 0 - - - 7 488 . 0 - - - - 19 . 3 - - - 8 488 . 0 - - - - 19 . 3 - - - H1 488 . 0 - - - - 19 . 3 - - - H2 488 . 0 - - - - 20 . 0 - - - SRC 488 . 0 SOURCE 20 . 1 5360 . 0 SPRINKJ•FR SYSTEM HYDRAULIC ANALYSIS Page 3 DATE: 5/31/2016 \HASS\TEXAS ROAD HOUSE_CHAR: ;TESVILLE, VA. SDF JOB TITLE : Attachment #4 PIPE DATA PIPE TAG Q (GPM) DIA (IN) LENGTH PRESS . END ELEV. NOZ . PT DISC . VEL (FPS) HW (C) (FT) SUM. NODES (FT) (K) (PSI) (GPM) FL/FT (PSI) Pipe : 1 -480 . 0 6 . 280 PL 41 . 00 PF 1 . 1 BOR 488 . 0 H . S . 17 . 3 480 . 0 5 . 0 140 FTG 2E2TG PE 0 . 0 1 488 . 0 0 . 0 18 . 3 0 . 0 0 . 006 TL 184 . 00 PV Pipe : 2 -480 . 0 8 . 390 PL 452 . 00 PF 0 . 8 1 488 . 0 0 . 0 18 . 3 0 . 0 2 . 8 140 FTG ET PE 0 . 0 2 488 . 0 0 . 0 19 . 1 0 . 0 0 . 001 TL 542 . 00 PV Pipe : 3 -480 . 0 24 . 980 PL 438 . 00 PF 0 . 0 2 488 . 0 0 . 0 19 . 1 0 . 0 0 . 3 140 FTG T PE 0 . 0 3 488 . 0 0 . 0 19 . 1 0 . 0 0 . 000 TL 679 . 00 PV Pipe : 4 -480 . 0 8 . 390 PL 95 . 00 PF 0 . 2 3 488 . 0 0 . 0 19 . 1 0 . 0 2 . 8 140 FTG T PE 0 . 0 4 488 . 0 0 . 0 19 . 3 0 . 0 0 . 001 TL 154 . 00 PV Pipe : 5 -480 . 0 8 . 390 PL 470 . 00 PF 0 . 7 4 488 . 0 0 . 0 19 . 3 0 . 0 2 . 8 140 FTG ---- PE 0 . 0 5 488 . 0 H . S . 20 . 0 4880 . 0 0 . 001 TL 470 . 00 PV Pipe : 6 -5360 . 0 8 . 390 PL 1 . 00 PF 0 . 1 5 488 . 0 H . S . 20 . 0 4880 . 0 31 . 1 140 FTG ---- PE 0 . 0 SRC 488 . 0 SRCE 20 . 1 (N/A) 0 . 122 TL 1 . 00 PV Pipe : 7 0 . 0 8 . 390 PL 482 . 00 PF 0 . 0 5 488 . 0 H. S . 20 . 0 4880 . 0 0 . 0 140 FTG 3ET PE 0 . 0 6 488 . 0 0 . 0 20 . 0 0 . 0 0 . 000 TL 634 . 00 PV Pipe : 8 0 . 0 8 . 390 PL 103 . 00 PF 0 . 0 6 488 . 0 0 . 0 20 . 0 0 . 0 0 . 0 140 FTG E PE 0 . 0 H2 488 . 0 0 . 0 20 . 0 0 . 0 0 . 000 TL 134 . 00 PV Pipe : 9 0 . 0 8 . 390 PL 78 . 00 PF 0 . 0 4 488 . 0 0 . 0 19 . 3 0 . 0 0 . 0 140 FTG T PE 0 . 0 7 488 . 0 0 . 0 19 . 3 0 . 0 0 . 000 TL 137 . 00 PV Pipe : 10 0 . 0 8 . 390 PL 229 . 00 PF 0 . 0 7 488 . 0 0 . 0 19 . 3 0 . 0 0 . 0 140 FTG T PE 0 . 0 8 488 . 0 0 . 0 19 . 3 0 . 0 0 . 000 TL 288 . 00 PV Pipe : 11 0 . 0 6 . 280 PL 158 . 00 PF 0 . 0 8 488 . 0 0 . 0 19 . 3 0 . 0 0 . 0 140 FTG 2E PE 0 . 0 H1 488 . 0 0 . 0 19 . 3 0 . 0 0 . 000 TL 202 . 00 PV