HomeMy WebLinkAboutWPO201500083 Review Comments 2015-12-19COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 Project title: Project file number: Plan preparer: Owner or rep.: Plan received date: Date of comments: Reviewers VSMP Permit plan review Earlysville Business Park MIA WP0201500083 Meridian Planning Group 4F LLC 27 October 2015 6 January 2015 4 December 2015 28 January 2016 Max Greene [tmiller@meridianwbe.com] County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The application may be resubmitted for approval if all of the items below are satisfactorily addressed. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. A SWPPP was not found in the submittal package. Please use the Albemarle County SWPPP template for help with this requirement. The template can be on this link: http://www.albemarle.org/upload/images/forms_center/departments/Community Development/for ms/Engineering and _WPO _Forms/Stormwater Pollution _Prevention _ Plan_ SWPPP_template.pdf 2 Documents in the SWPPP have not been signed by the owner. The SWPPP documents can be left at the front office counter for up to 2 days. Please let me know when I can leave the documents at the front counter for signature. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. PPP appears to be addressed on the plan sheet. The County would prefer the SWPPP template utilized due to this document being a "Living" document that is to be kept up to date with the SWPPP as the site develops. However, the plan will suffice as long as it meets the Virginia DEQ standards and regulations. Additional document pages may need to be added to the plan as the project progresses. Project description appears addressed at this time. The PPP will need to show the locations on the plan for the preconstruction meeting. The owner, contractor and inspector can address this issue at the Pre -construction meeting. Engineering Review Comments Page 2 of 3 C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is approved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17-403. A SWM agreement will be required for final approval. Please contact Ana Kilmer (akilmer(c-r�,albemarle.org ) for information and SWM Agreement template requirements. If an existing SWM agreement exists for this site then it may need to be updated to match this plan and information prior to issuance of a grading permit. Please contact Mrs. Ana Kilmer (akilmer(&albemarle.org) for additional information. D. Erosion and Sediment Control Plan (ESOP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is approved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Existing site conditions are not shown correctly. Please show the actual existing site conditions. This project is believed to be submitted to replace the existing site stormwater management and should be explained in written form to better clarify the action instead of showing what might have been previous site conditions. 2. Plan appears to show existing basin to be removed but does not address how the site will be graded and armored from erosion. Please clarify on plan. 3. Please show the construction entrance location on the plan. The existing asphalt can be utilized if denoted on the plan per VESCH. 4. Please show the limits and type of vegetation on the plan. Comments appear addressed with this submittal. The basin removal will need to be performed in a manner that does not allow for the discharge of sediment laden waters from the site. This will require coordination with the County VSMP Inspector. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process; After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. Engineering Review Comments Page 3 of 3 After bonding and agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; htip://www.albemarle.org/deptforms.asp?department=cdeng)ypo File: E1_vsmp_review projectname.doc 4' • ERIDIAN PI j LLC .11; IL.r$...51�:'}� p,LLC Engineering• Surveying• Planning 440 Premier Circle,Suite 200 Charlottesville,VA 22901 Phone:434.882.0121 December 29,2015 www.meridianwbe.com Max Greene Albemarle County RE: WPO201500083—EARLYSVILLE BUSINESS PARK Dear Max; Enclosed are two copies of the revised SWM and Erosion Plans for Earlysville Business Park. The following are responses to the comments in your letter dated December 4, 2015. A. Stormwater Pollution Prevention Plan(SWPPP) • A copy of the Albemarle County SWPPP is attached. B. Pollution Prevention Plan(PPP) • A copy of the Albemarle County SWPPP is attached. C. Stormwater Management Plan(SWMP) • A stormwater management agreement will be submitted under separate cover. D. Erosion and Sediment Control(ESCP) • There is a description regarding the existing conditions on the top of Sheet C-800. • Refer to Sheet C-802 for details on removing the existing sediment basin. • The Construction Entrance is shown on Sheet C-801. • The limits of type of existing vegetation has been added to the plans. Please let me know if you need additional information. Sincerely, Timothy Miller,P.E.,L.S. Principal Page 1 �pF A vt�r�1Q COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902 -4596 Phone (434) 296 -5832 Fax (434) 972 -4126 Project title: Project file number: Plan preparer: Owner or rep.: Plan received date: Date of comments: Reviewers: VSMP Permit plan review Earlysville Business Park MIA WP0201500083 Meridian Planning Group 4F LLC 27 October 2015 4 December 2015 Max Greene [tmiller @meridianwbe.com] County Code section 17 -410 and Virginia Code §62.1- 44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The application may be resubmitted for approval if all of the items below are satisfactorily addressed. The VSMP application content requirements can be found in County Code section 17 -401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17 -405. A SWPPP must contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary. A SWPPP was not found in the submittal package. Please use the Albemarle County SWPPP template for help with this requirement. The template can be on this link: http : / /www.albemarle.org /upload/ images / forms _center /departments /Community Development/for ms/Engineering and _ WPO_Forms /Stormwater_ Pollution _ Prevention _ Plan_ SWPPP_template.pdf B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17 -404. PPP appears to be addressed on the plan sheet. The County would prefer the SWPPP template utilized due to this document being a "Living" document that is to be kept up to date with the SWPPP as the site develops. However, the plan will suffice as long as it meets the Virginia DEQ standards and regulations. Additional document pages may need to be added to the plan as the project progresses. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25- 870 -108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved, and the reasons are provided in the comments below. The stormwater management plan content requirements can be found in County Code section 17 -403. A SWM agreement will be required for final approval. Please contact Ana Kilmer (akilmergalbemarle.org ) for information and SWM Agreement template requirements. Engineering Review Comments Page 2 of 3 D. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1- 44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17 -402. 1. Existing site conditions are not shown correctly. Please show the actual existing site conditions. This project is believed to be submitted to replace the existing site stormwater management and should be explained in written form to better clarify the action instead of showing what might have been previous site conditions. 2. Plan appears to show existing basin to be removed but does not address how the site will be graded and armored from erosion. Please clarify on plan. 3. Please show the construction entrance location on the plan. The existing asphalt can be utilized if denoted on the plan per VESCH. 4. Please show the limits and type of vegetation on the plan. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re- submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2 -4 PM on Thursdays, should you require a meeting to discuss this review. Process; After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2 -4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. After bonding and agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre - construction conference. Applicants will need to complete the request for a pre - construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre - construction conference will be scheduled with the County inspector. At the pre - construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that Engineering Review Comments Page 3 of 3 work may begin. County forms can be found on the county website forms center under engineering; hl!p://www.albemarle.org/deptforms.asp?department=cdengMMo File: E1_vsmp_ review projectname.doc r vim€' Max Greene From: John Anderson Sent: Wednesday, December 02, 2015 12:33 PM To: Max Greene Subject: FW: Earlysville BP Attachments: Stormwater Pollution_Prevention_Plan_SWPPP_tem plate_revicert_040815ja.doc From:John Anderson Sent: Friday,September 11, 2015 9:30 AM To: 'Tim Miller'<tmiller@meridianwbe.com> Subject: RE: Earlysville BP Tim, I'd like to help,will work on/off this weekend—brought enough past-due projects home to keep me going(10+projects). If you like, consider items below, and respond. I'll do what I can. Please do not consider this a review... it's a preview. Items: 1. C-602—Why is there a club-head shape shown as Limits of Minor Site Plan Amendment? What features are within Limits at this location? Anything VSMP-related? 2. C-601 —Show proposed contours required to construct New Office building/New Asphalt parking,unless pad ready/no proposed grading. 3. List/label Limits of Disturbance(=x.xx Acre). 4. Show drainage divides,if any. 5. Provide SWPPP [Template Attached] 6. Note below asks whether"the county would have any objections to using this BMP method." All DEQ BMP Clearinghouse methods are available. Another option: offsite nutrient purchase,if: Area of disturbance<5 Ac,or total phosphorus load reduction<10 lb/yr. 7. The more meaningful answer is whether county objects to this design. If you like, send: VaRRM .xls(file itself); pre-/post-development drainage maps; Narrative;plan/profile(DETAILS) for new SWM basin; and sheet/s with Construction-Maintenance Notes taken directly from the BMP specification/s. We require this. We do not assume contractors have adequate guidance to construct BMPs. We do not consider reference to on-line design specifications adequate to serve developer, contractor,or inspector needs. 8. Provide Qio(CFS)entering Spec. 2 BMP/ELS. Provide length of ELS. Length of ELS Lip= 13 lin. Ft.per each 1 cfs of inflow if area has 90%Cover. (Table 2.2.) 9. Identify soil types. 10. Correlate NRCS soil legend/soil Map names with hydrologic soil group/s(Websoil survey- http://websoilsurvey.sc.egov.usda.gov/App/WebSoilSurvey.aspx). Phosphorus reduction credit varies depending upon Hydrologic Soil Group—A,B,C,D. 0.94,rvious acres droning to 75%runoff valine reduction 64 conserved open space for treated area 4.75 -44,1 tuf acres draining to ?SY,runoff volume reduction 4 66 9.a 9heetFbw to Conservation Area with AlS Sods(Spec 92) conserved open sp c* for vowed area 0.75 i ringworm*acres a airningto SOY runoff vdunereduction €& conserved open sp ce tor treated area 0 S turf acres draining to SO%ninon reduotion Wort* 67 9.b.SheetflowtoConservation AMA vithCIO So*(Spec*2) conssrwdopenspace for treated area 0.S0 e y (!Q Mrpetviousacres+9/ming to SO/,tunott volume reduction conserved c eon space for treated area 0 50 9 o%earths.to Vegetated Fitter Strip ar A Soh or Compost oaf acres draining to WC':rruwtf reduouon oaamra i 3AnNoodad WM So at Mpg**2&#41 contervedopen vace lot treated&ma 0,50 11. Provide/show compliance with 9VAC25-870-66.D.—Sheet Flow. Explain via calculation/Narrative that entire post-developed site runoff routes to New basin,then ELS; that final release is sheet flow. 1 12. Alternatively: provide/show compliance with 9VAC25-870-66.B_3. -Energy balance LINK: http://lis.virginia.gov/cgi-bin/legp604.exe?000+reg+9VAC25-870-66 13. Provide DATA/Routings for New basin. . r` 1f5 it t1 i?—Detention only? This basin appears intuitively necessary,is likely necessary to comply with 9VAC25-870-66. 14. The critical data for the New SWM basin is post-developed peak Qio-this is required to design/size ELS. (13' / CFS). 15. As a favor(I can't take this on now),please check design against Open Space/Filter Strip design Criteria, Spec. 2, Table 2.2.—Slope/Min.Width, in particular. LINK: http://www.vwrrc.vt.edu/swc/documents/2013/DEQ%20BMP%20Spec%20No%202 SHEET%20FLOW_Final% 20Draft_v1-9 03012011.pdf VA DEQ STORMWATER DESIGN SPECIFICATION NO.2 SHEET FLOW TO FILTER OR OPEN SPACE Table 2.2.Filter Strip Design Criteria Medan barn Cartaarvrd Open Space Vegetated FMK Ship Soil and Vegetative Amended soils and dense turf Cover Undisturbed sods and native cover or landscaped with (Sections 6.1 and vegetation herbaceous cover,shrubs,and 6.2) trees 1%t to 4%Slope-Minimum 35 0.5%to 3%Slope-Minimum 3511 A width Overall Slope and width 4%to 6%Slope-Minimum 50 R Width(perpendicular 3%to 6%Slope-Minimum 50 ft width to the flaw) width 6%to B%Slope-Minlnun 65 ft (Section 5) The hist 10 f1,of filter must be 2%or *dm less In all cases 2 The firs)1011.of Oilier must be 2% or less in all cases Sheet Flow Maximum flow length of 150 fl,from adjacent pervious areas: (Section 5) Maximum Sow length of 75 tt,kom adiaoent impervious areas Length of ELS('Lip•131in.ft.per each l cfs of inflow If area has 90% Concentrated Flow Covers Length of ELS 6Lip=13 link per Length=40 lin.ft,per 1 cls for each 1 cfs of inflow(13 Iln.11,min; {Section 6.31 forested or re-forested Areas 4 130 lol.fl,max.) (ELS s length.13 lin ft.min;130 tin.1l max.) Located outside the limits cd (Construction Stage diSecbon 6) sturbance and protected by ESC Prevent compacbtxt heavy controls Treat small areas of IC(e.g., Typical Applications Adjacent to stream or wetland buffer 5.000 sr)andtor turf-Intensive land (Section 5) or fixes!conservation area uses(sports fields.golf courses) close to source Compost 5 Amendments No Yes(8,C.and D soils) (Section 6.1) Boundary Spreadera GD°at top of fitter (Section 6.3) GD at top of finer PB a at toe of filter 'A minimum of 1%is recommended to ensure positive drainage. 2 For Conservation Areas with a varying slope,a pro-rated length may be computed only If the first 10 R is 2%or less a Vegetative Cover is described In Section 6.2, `where the Cunsened()pen Space is a mixture of native grasses,herbaceous cover and forest (or re-forested area),the length of the ELS a Lip can be established by computing a weighted average of the lengths required for each vegetation type. Refer to Section 6.3 for design criteria 5 The plan approving authority may waive the requirement for compost amended sods for filler strips on B soils under certain conditions(see Section 6.1). s ELS=Engineered Level Spreader. GD=Gravel Diaphragm; PB=Permeable Berm 16. C-601 —Will critical slopes be impacted? [yellow,below] If so,has project obtained critical slopes waiver approval via site plan amendment review process? -Waivers are coordinated through Planning Division,not Engineering. 2 a, New korm Water ",. unpgemenk Basi { ' Retex to.0,o s ! New �. If design meets BMP specifications,we accept design as compliant. Care at this stage should limit comments during regular submittal review. My workload tilts unmanageable for the moment—we'll do our best. I hope this is helpful,Tim. Take care, From:Tim Miller [mailto:tmiller@meridianwbe.com] Sent: Friday,September 11, 2015 8:02 AM To:John Anderson<janderson2@albemarle.org> Cc: 'Jeremy Fox'<jfox@meridianwbe.com> Subject: FW: Earlysville BP John, We met a few weeks ago on the Earlysville Business Park site plan amendment. It was determined during that meeting that since the Owner did not have a current DEQ land disturbance permit that the amendment would have to meet the current regulations. I have revised the SWM design to comply with current regulations. The water quality measure is BMP Spec No. 2 Sheet flow. Attached are plans showing the BMP. Can you review it and let me if the county would have any objections to using this BMP method. If there are no objections then I will submit the plans and calculations for review and approval. Given the confusion over this project I am trying to reduce the time it will take to get this approved. The Owner is quite upset about how the requirements change every time we submit plans. Anything you can do to help would be appreciated. Thanks, Tim Miller, P.E., L.S. Principal Meridian Planning Group, LLC 3 411110' `*41.00 1413 Sachem Place,Suite One Charlottesville,VA 22901 434.882.0121 www.meridianwbe.com 4