HomeMy WebLinkAboutWPO201600067 Review Comments WPO VSMP 2017-03-13COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP Permit plan review
Project title: Broderick May Property
Project file number: WP0201600067
Plan preparer: Shimp Engineering. [Justin@shimp-engineering.com]
Owner or rep.: Broderick May [brodmay@comcast.net]
Plan received date: 28 Oct 2016
Rev. 1 Date Received: 08 Dec 2016
Rev. 2 Date Received: 28 Feb 2017
Date of comments: 9 Nov 2016
Rev. 1 comments: 4 January 2017
Rev. 2 comments: 13 Mar 2017
Reviewers: Geoff Elsie -VESCP
Emily Cox — Mitigation, SWM
Rev. 1: Geoff Elsie -VESCP
Emily Cox — Mitigation, SWM
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is approved. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Not Needed
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Not Needed
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. Per county code section 17-303, this plan is exempt from the VSMP requirements
2. Please submit 2 additional copies of the plan for approval.
Engineering Review Comments
Page 2 of 3
D. Erosion and Sediment Control Plan (ESOP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. Confirm that all required Army Corp of Engineers and VDOT permits have been obtained. Rev. 1:
Provide written documentation from VDOT and USACE that permits have been obtained
or are in the approval process. Rev 2: Comment Addressed.
2. Need Underground Utility Easement marked with Deed Book Reference. Rev. 1: Comment
addressed
3. Clarify control notation at Box Culvert. Outlet Protection called out with a construction detail for a
Temporary Diversion Dike. Rev. 1: Comment addressed
4. Show beginning and end of EC-2 matting along Conveyance Channels. Rev. 1: Comment
addressed
5. Notation for Silt Fence at Silt Trap. Rev. 1: Comment addressed
6. Add installation of Culvert 2 to the sequence of construction. Also, provide adequate diversion for
the intermittent stream during construction. Rev. 1: Provide detail to plan showing Type B
Utility Stream Crossing. Rev 2: Comment Addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
Engineering Review Comments
Page 3 of 3
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
hitp://www.albemarle.org/deptfomis.asp?department--cdeng"o
File: wpo201600067