Loading...
HomeMy WebLinkAboutSUB198900228 Calculations (3) 1 PEACOCK HILL WATER COMPANY WATER STORAGE AND DISTRIBUTION SYSTEM CONSTRUCTION PEACOCK HILL SECTION THREE ALBEMARLE COUNTY, VIRGINIA MARCH 14, 1980 William S.Roudabush, Inc. Engineers, Surveyors and Land Planners 914 Monticello Road Charlottesville, Virginia 22901 4.0 Jahn William Greene 70. 6458 4 For the purpose of this construction, the specifications herein will be a suppliment to the specifications submitted and approved for sections one and two. All work proposed for section three is already covered in the earlier specifications except the booster pumps and the 13,200 gallon storage tank. These specifications include complete sections on the pumps and storage tank and suppliments for the description articles for the distribution system and service connections. TABLE OF CONTENTS General Technical Provisions GT-1 Special Technical Provisions STI-1 Section I Pumps STI-1 Section II Storage Tank STII-1 Section III Water Distribution System STIII-1 Section IV Water Service Connections STIV-1 GENERAL TECHNICAL PROVISIONS The following General Technical Provision articles from Section One specifications: Article A. Underground Pipelines Article B. Concrete Article C. Site Preparation, Excavation and Embankment Article E. Crusher Run Stone Article F. Seeding, Fertilizing, and Mulch Article G. Welding Article H. Test During Construction Article I. Electrical Work Article K. Disinfecting Water Lines GT-1 GENERAL TECHNICAL PROVISIONS w s . Article A. UNDERGROUND PIPELINES A.1 Transportation and Storage A.1 .1 All pipe shall be transported and stored as recom- mended by the manufacturer. Particular care shall be exercised to avoid damage to, or contamination of, the jointing surfaces and material. No chipped, cracked or otherwise damaged pipe will be used in the work. F A.2 Excavation and Preparation of Trenches _ - • A.2.1Laying Condition 1 - Stone Bedding Throughout. _ A.2 .1 .1 All open-cut trench excavation shall be carried to a depth of 6 inches below the design elevation of the outside bottom of the pipe. 3 . - Crusher run stone of maximum size 12 inch shall be placed and tamped in the trench so that the bottom quadrant of the pipe will be bedded in continuous contact with the prepared trench bottom. Unauthorized undercutting shall be back- filled with crusher run stone tamped in place. ` Space for joint couplings shall be so prepared that bearing will be continuous along the pipe `-11barrel and no load carried by the joint. Trenches shall be kept dry during preparation of the bottom, installation of pipe, and placing of selected backfill. Width of trenches in which - _ - pipe is to be installed shall be such as to pro- ] . vide adequate space for proper jointing but not greater than the external diameter of the pipe plus 24 inches. Wherever, during excavation, the presence of incipient slides is noted, the trench walls shall be restrained by adequate sheeting and shoring, Not more than 200 feet - GT-A1 of trench shall be opened in advance of pipe laying. At the end of each day's operation, pipe shall be adequately capped or plugged J to prevent water or other material from entering the pipe. • A.2.2 Laying Condition 2 Stone Bedding !Or Special Conditions only. A.2 .2 . 1 Trenches shall be excavated to the depths shown on the plans with special attention paid to . the minimum cover designates on the drawings. Width of trenches in which pipe is to be installed shall be such as to provide adequate space for proper jointing but not greater than the external diameter of the pipe plus 24 inches. If Iedge rock or boulder formations are encountered, the trench shall be excavated 6 inches below grade and backfilled to grade with a compacted minimum depth of 6 inches of crusher run stone of maximum 1-1-inch size or other suitable material approved by the Engineer. Trenches shall be kept dryduring preparation of the bottom. The bed for the pipe shall be free of rock edges, large stone or other material which could be injurious to the pipe and shall be shaped so that at least the lower quadrant of the pipe will be in complete contact with the trench bottom. Spaces for joints shall be prepared so that bearing will be continuous along the barrel of the pipe and no load taken•by the joints. Wherever, during excavation, the presence of incipient slides is noted, the trench walls shall be restrained by adequate sheeting and shoring. Not more than 200 feet of trench shall be opened -• • in advance of pipe laying. At the end of each day's operation, pipe shall be adequately capped or plugged to prevent water or other material from entering the pipe. A.3. Installation of Pipe A.3.1 Pipe shall be protected during handling against impact shocks and free fall. Pipe shall be kept clean at all times and no pipe shall GT-A2 tINIONMIMIONANIMINWIIIIMNINIIiella gi- fal . be used in the work which does not conform to the _11.` appropriate ASA or ASTM standard. All pipe shall be laid with ends completely seated, carefully centered ' t • • and true to line and grade. No pipe shall be laid on i _ frozen ground. Not more than 200 feet of trench shall be opened in advance of pipelaying unless specificall; • authorized by the Engineer. IAfter installation, for laying condition #1 "additional r crusher run stone shall be manually tamped around the pipe to provide complete bedding for the bottom half of the pipe. Extreme care must be exercised so as not to disturb pipe alignment or grade during this tamping operation. « : t Pipe jointing methods shall be strictly as recommended by the manufacturer. A.4 Backfill 1 A.4.1 Backfilling shall be accomplished as soon as practicabl after the pipe has been installed and approved by the Engineer. Trenches shall be kept dry until backfill is placed. Material used for backfilling shall contain no stones having any dimension greater than 6 inches, frozen earth, debris, or earth with an exceptionally high _void content. For backfill up to a level of 2 feet over the top of the pipe, only selected material containing ` no stones shall be used, and the backfill shall be placed in uniform layers not exceeding 6 inches in depth up each side. •Each layer shall be placed, then carefully and uniformly tamped, so as to eliminate the possibility of lateral displacement. • 11 - In roadways, streets, sidewalks, and lawns the ?` - entire depth of backfill shall be tamped in 6 inch layers. If subsidence occurs after pavement or concrete is placed, the contractor shall restore as directed by the Engineer at no cost to the Owner. In fields and other areas not involving structures, streets or utility lines backfill shall be tamped in 6 inch layers to a minimum depth of 2 feet over the pipe; remaining backfill may be placed without tamping provided the fill is compacted by rubber- tired earthmoving equipment and mounded to allow for future settlement. Tamping of the material.to GT-A3 a height of at least 24 inches over the top of the pipe shall be performed manually. All earth material required to be tamped shall be compacted at optimum moisture content to 95% of maximum density as compared:to the density of the same material when tested in accordance with AASHO T-99. 4! GT-A4 Article B. CONCRETE B A Materials •i B.1.1 Cement shall be Portland, type I, conforming to ASTM designation C-IS0. Use only one brand, • such brand to be of American manufacture. Have cement delivered and stored in canvas bags or other - strong, well made packages. Use no cement from bags containing lumps or caked cement. Use no cement salvaged from discarded or used bags. B.1.2 Air entraining admixture shall be ASTM C-260. B.1.3 Aggregates shall be ASTM C-33. Use no pit- • run or naturally mixed aggregates. Store fine and coarse aggregates separately and keep all aggregates clean. Use agregates from only one source. Do not use aggregates containing lumps of frozen or partially cemented material. Use sand consisting of clean, sound, durable grains free from dirt, dust, clay or other harmful substances. B.1.4 Water shall be potable unless otherwise approved by the Engineer. B.1.5 Reinforcing steel shall be ASTM A-432 Billet Steel, 60 ksi yield. Use new deformed, billet steel bars for concrete reinforcement. Use no steel which has been bent and straightened or steel with kinks and sharp bends. Use only clean steel free from dirt, detrimental scale, paint, oil, or other foreign substances. For bent bars, cold bend to the shape shown on the Plans as follows: Stirrups and tie bars shall be bent around a pin having a diameter not less than two (2) times the ��. minimum thickness of the bar. Bends for other bars shall be made around a pin having a diameter not less than 6 times the minimum thickness except for bars larger than 1 inch in which case the bends shall be made around a pin having a diameter not • less than 8 times the minimum thickr.'ss. Construction joints shall be placed where detailed on the Plans and only at locations otherwise approved by the Engineer. Cold joints will not be allowed in any approved pour of concrete. GT-B1 • B.1.6 Waterstops shall be Vinylex, catalog No. RB6-38H, or equal. Splice as recommended by the manufacturer in such a manner that there will be no discontinuity in • strength or water resistance. Use waterstops at all con- • struction joints subject to any water pressure or moisture, whether they are detailed on PIans or not. B.1.7 Concrete shall be 3,000 psi (AE) . _ B.2 Forms B.2.1 Forms shall be designed to withstand the liquid head exerted by the wet concrete. They shall be set true to the lines and grades shown on the Plans and shall be cleaned and oiled before placing concrete. Reinforcing steel shall be securely tied in place in accordance with the spacing shown on the Plans. Use mortar-tight forms sufficiently rigid to prevent displacement and sagging. Use only smooth forms free from irregularities, dents, sags, and holes. Arrange internal ties so no metal will show in the concrete surface or discolor the surface when exposed to weathering. Side forms may be removed after the concrete has set sufficiently to resist damage from removal operations. Forms supporting the weight of con- crete shall remain in place until the concrete has reached its specified twenty-eight day strength. B.3 Placement of Reinforcement B.3.1 Do not deliver reinforcement until Engineer has approved bar schedules and bending diagrams. Accurately place reinforcement and anchor it sufficiently to prevent movement during placing and setting of con- crete. Tie bars at all intersections where bar spacing exceeds 12 inches. If spacing is twelve (12) inches or less tie bars at alternate intersections. Maintain proper distance from forms by stays, blocks, ties, hangers, or other approved supports.pports. Use precast mortar blocks of approved shapes and dimensions or approved metal chairs. Use only galvanized metal for chairs which are in contact with the external surface of the concrete. Do not use pebbles, pieces of broken stone or brick, metal pipe or wooden blocks. Maintain minimum distance of one and one-half (11) inches between bars. Do not place concrete until reinforcement has been in-' spected in place. GT-B2 Article C. SITE PREPARATION, EXCAVATIONS & EMBANKMENT CA Sitere aration P P C.1.1 The contractor shall clear and remove from)areas to be excavated or filled, all obstructions and/or objectionable material within the limits of construction. This shall include all trees, stumps, roots, vines, debris and other extraneous matter. If the contractor elects to dispose of cleared and grubbed materials by burning on the site, he shall place his burn piles in areas where no damage to any remaining vegetation or property will result from his operations. All local fire regulations shall be observed when burning waste material. Remove top soil from all areas to be excavated and from all areas on which fill is to be placed, stockpile and respread as directed. C.2 Excavation C.2.1 Classification C.2. 1.1 Solid Rock - all undisturbed natural ledge rock and rock in bedded deposits or unstratified masses with such hardness as to be unpickable or necessitate drilling and blasting in its re- moval. Includes boulders of over one (1) cubic yard volume. C.2. 1.2 Common - all Original excavation except Solid Rock. Removal of top soil or fill material from stockpiles previously excavated is inci- dental work and not included as excavation. • C.2.2 Excavation for area site work and road construction shall be to the lines and grades shown on the Plans. If rock is encountered during excavation, such rock shall be removed six inches below finished grade, and back filled with select material. If pervious or otherwise unsuitable material is en- countered during excavation, such material shall be excavated 18 inches below finished grade and back- filled with select material placed in six inch layers and compacted to 95% of maximum density when tested by AASHO Method T-99. If any evidence of solution channels in underlying rock is encountered, work in this area will be stopped and GT-C1 - this fact will be brought to the Engineer's attention immediately, in order that a suitable course of action may be determined. Saturated soil, excavated near the water table may not be used for embankment until it has been sufficiently dried to allow for proper compaction. C.2.3 Excavation for structures shall be to lines and grades- shown on the plans. In the event that open pit excavation will not permit compliance with special conditions noted, provide the necessary sheeting and shoring. Foundations shall be approved by the Engineer. Unauthorized under- cutting shall be backfilled with concrete at the Contractor's expense. No foundation shall be placed on disturbed soil, unless specifically authorized by the Engineer. If rock is encountered during structure excavation, unless otherwise specified, the rock shall be excavated a minimum of six inches below plan grades. Backfill to plan grade with compacted sand material consisting of clean, well graded and washed components free from earth or organic substances. Crusher run stone backfill (fully compacted) may be substituted for sand if all provisions of Article E of these Specifications are met. Sand and stone blankets for structures shall be wetted just prior to the placement of concrete thereon. • C.2.4 Solid Rock Excavation • C.2.4. 1 When the use of explosives is necessary the contractor shall exercise the utmost care to insure the safety of life and property. He shall be responsible for any and all damage resulting from the use of explosives in the performance of the work by him, his agents or employees. Ex- , plosives shall be stored in a secure manner in compliance with local laws and regulations. Storage facilities shall be clearly marked • "DANGEROUS - EXPLOSIVES". C.2.4.2 Comply with all governmental laws and regulations pertaining to transportation, storage, and use of explosives. Use proper blasting mats for all operations. GT-C2 C.2.5 Protection - Furnish, erect and maintain sheathing and bracing as necessary to support the sides of any excavation at no additional cost to the Owner. Erect necessary barricades, bridges, warning lights, and other devices to adequately protect life and property at no additional cost to the Owner. C.3 Embankment C.3.1 Embankment for area grading and road construction shall contain no rock or other foreign matter. Build up in maximum six inch layers and compact to 95% t. ' of maximum density when tested by AASHO Method T-99. During compaction, maintain moisture content of soil between 95% and 110% of the optimum as determined by test. C.3.2 _ Backfill for structures shall contain no rock or other foreign matter. • Backfill shall be placed in maximum six inch layers and compacted to 98% of maximum density when tested by AASHO Method T-99. During compaction, maintain moisture content of soil between 95% and 110% of the optimum as determined by test. 4{ • GT-C3 Article E. CRUSHER RUN STONE E .1 Crusher run stone shall have a maximum size of lf inch. It shall consist of hard, durable particles, or fragments of stone, gravel or slag, free from vegetation or other deleterious substances. Shales or other materials that break up and weather rapidly when alternately frozen and thawed or wetted and dried shall not be used. Stone shall have a maximum Los Angeles abrasion percentage of wear of 45%. Crusher run stone shall conform to the following gradation: Sieve Percentage by weight passing Designation square mesh sieve 2 inch 100 1 inch 90-100 3/8 inch 50-85 No. 10 25-50 No. 40 12-30 No. 200 5-15 Should filler material be required, in addition to that in- - herent to the above gradation, to produce a completed mixture of aggregate capable of being processed and com- pacted into a dense well bonded surface, it shall be blended uniformly with the stone material on the site or at the crushing plant. V GT-E1 Article F. SEEDING, FERTILIZING, AND MULCHING F.1 Scope • F.1. 1 Includes spreading topsoil, seeding, fertilizing, and mulching of all areas of raw earch resulting from the construction. The Contractor is responsible for doing everything necessary to establish a satisfactory stand of grass. Topsoil previously stockpiled shall be respread and graded in preparation for the seeding operation. Mini- mum thickness of topsoil shall be three inches, unless otherwise specified. F.2 Materials F.2.1 Fertilizer shall be 10-10-10 applied at the rate of 1,000 lbs. per acre. F.2.2 Agricultural lime shall be applied at the rate of - 2,000 lbs. per acre. F.2.3 Seed the following mixture at the specified rate per acre: 50 lbs. Kentucky 31 Fescue, 2 lbs. White Clover, and 10 lbs. Rye Grass. F.2.4 Mulch shall consist of hay, straw, decomposed leaves or any similar approved material. F.3 Construction Methods F.3.1 After spreading fertilizer and lime at the prescribed rate, the seedbed shall immediately be loosened to a depth of 4 inches in order to incorporate the fertilizer into the soil. F.3.2 After the seed is applied at the prescribed rate, it shall be worked into the soil to a minimum depth of one-half inch. The seeded area shall then be compacted by means of a cultipacker or roller in order to reduce air pockets to a minimum. F.3.3 Mulch shall be spread to a uniform depth of 11 inch, loose - measurement, in a manner which will leave exposed not more than 25% of the area. When necessary, to prevent displz_cement, mulch shall be anchored. GT-F1 F .3.4 Seeding shall only be accomplished between March 1 and June 15 or between August 1 and November 1. F .4 Maintenance F.4. 1 Water, mow and otherwise properly maintain all seeded areas until the project is accepted. Re- place all mulch destroyed by fire, erosion, or other causes. Reseed all areas where original seeding does not "take" as many times as nec- essary for a stand of grass acceptable to the Engineer. r • GT-F2 Article G. WELDING GA - Welding shall be done by operators who have been previously qualified by tests as prescribed in the American Welding Society "Standard Qualification Procedure" to,perform the type of work required. Welding equipment shall be of a type which will produce proper current so that the operator may produce satisfactory welds. The welding machine shall be_ of 200-400 ampere, 25-40 volt capacity.. Electrodes shall be of classification numbers E-6011, E-6012, E-6013, E-6020, and E-6030, and shall be suitable for positions and other conditions of intended use in accordance with the instructions with each container. All welding shall be done by direct current. - The technique of welding employed, the appearance and quality of welds made, and the methods of correcting defective work shall conform to the American Welding Society "Code for Arc Welding in Building Construction," Section 4, Workmanship. Surfaces to be welded shall be free from loose scale, rust, grease, paint and other foreign materials except that mill scale which withstands vigorous wire brushing may remain. A light film of linseed oil may likewise be disregarded. Joint surfaces shall be free from fins and tears. No welding shall be done when the temperature of the base is lower than 0°F. At temperatures between 32'F and (PF the surfaces of all areas within 3 inches of a point where a weld is to begin shall be heated until they are too hot to touch before welding is started. Finished members shall be true to line and free from twists, bends and open joints. 4• Y - GT-G1 Article H . TESTS DURING CONSTRUCTION H .1 Description H .1 .1 All materials and portions of the work shall .be subject to tests to determine compliance with these Specifications at any time during the construction. Ml such tests shall be at the expense of the Owner except as provided below. The Contractor, however, shall furnish the material to be tested (concrete, pipe, steel, or similar items) and-allow reasonable opportunity for such tests. Should any material or work tested fail to meet these Specifications, the Contractor shall replace the defective work or material entirely at his own expense, and he shall likewise pay forall subsequent tests of replaced work or material until the Specifications are met. H .2 Testing - Gravity Sewers and/or Non-Pressure Pipelines. Before being put into service and prior to acceptance of the work, the Engineer will conduct a thorough and complete visual inspection of the work. In addition to a visual inspection, either an infiltration, exfiltration, or air test will be conducted by the Contractor under the supervision of the Engineer. H .2.1 Infiltration test - when in the opinion of the Engineer, ground water Ievel is equal to the highest ground water condition in a normal year, a weir test shall be made of flow of water from sewers in the system. The flow shall not exceed 100 gallons per 24-hour day per inch of pipe diameter per mile of sewer line. H.2.2 . Exfiltration test - when in the opinion of the Engineer, conditions are not adaptable to infiltration test, the Engineer may require an exfiltration test to check for defects. The section so tested shall be plugged watertight at its lower end and the sewer filled with water at least one foot above the top of the pipe at the upper end. In no case shall any section of pipe be subjected to a head in excess of 15 feet without prior approval of the Engineer. Loss of water versus infiltration limits, as well as appearance of leaks, shall be considered in evaluating the results of the test_ GT-H1 H.2.3 Air Test - when in the opinion of the Engineer conditions are not readily adaptable to either an infiltration or exfiltration test, a low pressure air test will be required. The testing equipment, procedure, and results will all be subject to the rigid approval of the Engineer. Results of the air test will be reviewed for compliance with published and widely accepted standards. • H .2 .4 General - all defective work determined by such inspections and tests, shall be immediately repaired and retested until proven to be satisfactory. On completion of such inspections or tests, all foreign matter, including sand, rock or gravel, shall be removed from all sewers and manholes before final acceptance of the lines. The cost of testing (infiltration, exfiltration or air) shall be included in the unit price bid for pipe and manholes. The Contractor shall furnish all equipment, materials (including water) and labor required for such inspection • or tests. All tests will be conducted in the presence of and under the direction of the Engineer. H..3 Testing - Pressure Pipelines. Before being put into service and prior to acceptance of the work, a pressure test shall be conducted, at the Contractor's expense, on all completed pressure pipelines on the project. • The lines shall be filled with water and subjected to a minimum pressure of 50 psi in excess of the rated working pressure of the pipe for a minimum period of 8 hours without evidence of any leakage from the system, in excess of AWWA Requirements, Section C600. The method and equipment for conducting this test and the pressures and time limits of the test shall be subject to the approval of the Engineer. The Contractor shall at his expense furnish the equipment, water and supporting means to conduct this test in the presence of the Engineer. Should the test reveal any weaknesses, breaks or excessive leaks in the line, such defects shall be corrected at the expense of the Contractor, and the system retested at the Contractor's expense, as outlined �► above. The cost of testing shall be included in the appropriate bid items. 11.4 - - Cc-mpaction Tests Compaction tests may be performed to test embankment and back- fill adequacy. - These tests, if performed, will be at the Owner's GT-H2 Iexpense and will not involve the Contractor's labor. However, if tests reveal construction deficiencies and inadequacies, the faulty work shall be corrected and re- - tested at the sole expense of the Contractor. H.5 Equipment Testing l Prior to final acceptance of the work, Mechanical and - Electrical equipment and accessory controls shall be • tested in the presence of the Engineer under simulated conditions matching as closely as possible normal 3 operating conditions. - The cost of making such tests shall be included in the 3 . ' appropriate Bid Items and shall include all equipment, labor and materials -(including water ) necessary to con- duct such tests. Should performance of equipment and/or controls prove substandard or defective, appropriate repairs or replace- ments will be made and the complete test renin at the Contractor's expense as outlined above, until satisfac- . tory performance is obtained. H-. 6 Concrete Testing H . 6.1 Prior to delivery and use of concrete the Contractor shall obtain and submit to the Engineer, + at the Contractor's expense, a certificate from a recognized testing laboratory setting forth details of the concrete mix to be supplied including infor- mation concerning cement and aggregates as well as strength test results. This requirement may be met by a transit mixed concrete supplier by sub- ,] - mission of the required information previously de- veloped for a standard mix. ' a H . 6.2 During construction, take 2 test cylinders from _ each major concrete structure containing 5 or more cubic yards or at least 2 test cylinders from . each day's pour of concrete. From each pair of test - - cylinders, one 7 day and one 28 day test of the com- pressive strength will be made by a recognized testing Ilaboratory and the results of such tests certified to the Engineer. If more than 2 cylinders are taken in any ' day's pour the Engineer will designate the cylinders for which 7 day and 28 day tests are to be _made. Test GT-H3_ -., A . cylinders shall be field cured under conditions as similar 7.1_ as possible to that of the structure from which the cylinder has been obtained and shall be protected at all times from shocks or excessive vibration during storage, handling or '°` transporting. The Contractor will furnish, at his expense, approved cylinder cartons, spading rod, slump cone, - trowels and any other equipment, materials, storage facilitie transportation and assistance necessary in making such __ cylinders and tests. Cost of the actual tests, however, will be the obligation of the Owner. " _::moi ______ --1 1 • .• c.r Y' F I GT-H9 f Article I. ELECTRICAL WORK I.1 Grounding • Ground solidly the raceway system and neutral conductor of the wiring system at main service switching equipment. Bare copper ground con- ductor shall be extended in conduit of tubing from the main service equipment to ground grid or water pipe. Make connection to water pipe using suitable ground clamp or lug. If flang pipe is encountered, make connection with lug bolted to street side of flange connection. Provide grounding grid complete with bare copper conductor and copper-clad steel ground rods. The gounding grid shall be below grade and all con- nections below grade shall be by the Cadwell connection process. Where designated, provide empty conduit for telephone service ground in conformance with Telephone Company requirements.-- Leave No. lb gauge annealed pull-wire in conduit with minimum of 4 feet of slack each end. Provide conduit and wire for extension of ground system to the control panel. Provide ground wire for all motors. 1.2 Motors Motors shall be built in accordance with the latest standards of NEMA and as specified. Motors shall be tested in accordance with the standards of ASA C50 and conforming thereto for'insulation resistance and dielectric strength. Each motor shall be provided with adequate conduit terminal box, adequate starting and protective equipment as specified or required. Ir Unless otherwise specified, each motor shall have sufficient capacity to start and operate the machine . it drives without exceeding the motor nameplate rating, at the driven device speed specified or at any speed and any load which may be obtained by the drive actually furnished. The horsepowers of motors indicated on the drawings are those estimated to be required and are to be used to determine the electrical feeder sizes. The horsepowers GT-I1 specified are also those estimated to be required by the driven equipment when operating at the specified duties and efficiencies. If the actual horsepower required for the equipment proposed to be furnished differs from the specified, or if ' it differs in any way from the value indicated on the drawings, the matter must be adjusted to the Engineer's satisfaction before installation of the equipment. Motors shall be rated for continuous duty at 100% of the rated capacity and the temperature rise shall be based on maximum rise of 40t, above 40°C ambient temperature, unless otherwise specifically specified or indicated on drawings. 3 Unless otherwise specified and/or required, single speed, polyphase motors shall be NEMA Class B or F, squirrel cage, totally enclosed fan cooled, induction motors. Motors shall be especially wound for the voltage specified or indicated. Unless otherwise specified and/or required, two speed, polyphase motors shall be NEMA Class B or F, squirrel cage, totally enclosed fan cooled, two winding, two speed induction motors of torque classi- fication to match load requirement. Each motor shall be selected for quiet operation. Unless otherwise specified and/or rquired, single phase motors shall be NEMA Class B, of the open, capacitor type. Generally, motors under HP shall be single phase. Motors 1/6 HP and under may be split phase type. 1.3 Circuit Breaker Panelboards Where designated, provide automatic circuit breaker panelboards complete with enclosing cabinets, factory r assembled interiors and circuit breakers and busses of capacity indicated. Circuit breakers shall be quick-make, quick-break, trip indicating. Multipole breakers shall have common trip. All circuit breakers shall be in accordance with latest NEMA Standards. GT-I2 . Panel shall consist of a reinforced Galvanized sheet steel frame with bus bars and circuit breakers properly supported to prevent vibration and withstand effects of short-circuit current. Circuit breakers shall be fully interchangeable without disturbing adjacent units. All .terminals shall be solderless type. All busses, straps and connectors shall be plated and sequence phased. Boxes shall be galvanized steel and provide wiring gutter space in accordance with National Electric Code. Fronts shall be sheet steel, equipped with door, hinges, locks keyed alike, directory card holder, and trim clamps, with color as specified. Panelboards shall be Westinghouse Type WEB or approved equivalent. It shall be the Contractor's responsibility to check the physical size of panelboards supplied to verify that all panelboards fit within the space allotted. All surface mounted panelboards shall be mounted on channel or "stood-off' from the wall in approved manner to provide air space behind the panel. Provide a type- written circuit directory for all panelboards. I.4 Conduit and Fittings: Provide galvanized rigid steel conduit. (Porter Duct electrogalvanized conduit, or Triangle Conduit and Cable Corporation hot-dipped galvanized conduit or approved equal.) All conduit shall be a minimum of 3/4" in size unless indicated otherwise. Provide flexible liquid-tight conduit which shall be "Sealtite" or approved equivalent. Fittings for galvanized rigid steel conduit shall be threaded. Fittings shall be suitable for application, location, intended use and type of conduit being installed. 1.5 Wire • Run conductors continuously from outlet to outlet with no splices in between. Junction boxes may be used where required. Wire connectors of insulat- ing material or solderless pressure connectors, properly taped, shall be utilized for all splices in wiring. Copper conductors shall be National Electric Code Type THW insulation unless otherwise noted. GT-13 Copper conductors passing immediately over heaters, near ballasts, or otherwise requiring heat resistant insulation by virtue of condition or location, shall have Type THHN insulation or similar type. Copper conductors for low voltage wiring shall be NEC Type TW insulation No. 16 AWG unless larger size is indicated. I.6 Feeders I:6.1 Provide galvanized rigid steel conduit feeder system in conformance with National Electrical Code and accepted trade practices. Conduit shall be minimum size required for conductors or size indicated. Conceal conduit within walls, above ceilings and/or below floors where possible with parallel runs kept at least 6" from flues, heating pipes and other heated surfaces. Arrange conduit runs so far as possible to eliminate condensate traps. Non-encased conduit shall run parallel to walls, ceilings, and structural members. Right angle turns, consisting of cast metal fittings or symmetrical bends, shall be secured to adjacent members immediately before and immediately following the change in direction. Bends and offsets shall be avoided where possible, but where necessary shall be made with an approved hickey or conduit bending machine. Conduit which has been crushed or deformed in any way shall not be installed. Support conduit on approved galvanized wall brackets, ceiling trapeze, strap hangers, or pipe straps, secured by means of toggle bolts on hollow masonry units, ex- pansion bolts in concrete or brick, and machine screws on metal surfaces. Support conduit in vertical shafts at each floor level by means of U-clamp hangers. Cut conduit square and to accurate measurements, ream ends, remove burrs and obstructions, apply graphite grease to male threads only and make joints up tight with solid electrical contact. Securely fasten conduit to all cabinets, sheet metal outlets, junction and pull boxes with galvanized locknuts and bushings. Provide pull it boxes where feeders turn right angles following long runs or in straight sections of long runs where required to facilitate-pulling conductors into conduit. Conduit - run underground, enclosed in concrete or exterior masonry wall, shall be painted with epoxy material 8 to 10 mils in thickness. Paint shall be Koppers Co. Bitumastic 300, Porter Sheraduct, or approved equivalent. . Provide conduit and raceway fittings that are new stock stored away from weather. GT-I4 I.6.2 Branch Circuits Provide galvanized steel rigid conduit branch circuit system in conformance with National Electrical Code. Motors located nearer floor than ceiling shall be served by conduit run under or at floor. Recep- tacles shall be served by conduit run under floor when so indicated. All raceway run in concrefe and under concrete slab shall be rigid conduit. Conduit, when - larger than 1" shall be located below concrete slab. Locate conduit in slab so as not to weaken structural strength of slab; fasten conduit securely to forms in proper position before concrete is poured. Conduit and tubing shall be minimum 3/4" size or size indicated. Make short connection to motor with maximum of 18" liquid tight flexible conduit. Homeruns may be combined in one conduit, provided all connections are in accor- dance with National Electrical Code requirements and maximum unbalanced current in neutral does not exceed capacity of conductor. Conduit run underground, en- closed in concrete or exterior masonry wall, shall be painted with epoxy material, Koppers Company Bitumastic 300 or Porter Sheraduct or approved equivalent. Branch circuit raceway system installation shall generally conform to installation method described under "FEEDER" paragraph hereinbefore. Provide enclosed safety switch or motor switch as re- quired or indicated for all equipment furnished under this contract or indicated for installation by others at this time, unless furnished with equipment supplied under other Sections of these specifications. All surface mounted disconnecting devices shall be mounted on channel or "stood-off" from the wall in approved manner to provide air space behind device. I.7 Disconnecting Devices I.7.1 Safety switches shall be Westinghouse Electric Corporation, Type HF Heavy Duty or approved equivalent r in NEMA 1 (indoor) or NEMA 3R (outdoor) enclosure. Switches shall be supplied with dual element fuses of size indicated and/or required for fusible safety • switches. GT-15 I.8 Wiring Devices •Wiring devices, so far as practical shall be one manu- facturer unless otherwise noted. Light switches shall be tumble type, rated 20 amperes, 120 volts, single pole or 3-way, as required. Duplex convenience outlets shall be for a parallel and arounding type plug, rated 20 amperes, 120 volts, and be of ivory color. Plates for devices in all areas shall be brushed finished stainless steel. I.� Outlet, Junction, and Pull Boxes Provide outlet boxes where indicated or required and suitable for service intended. Outlet boxes shall meet code require- ments. Anchor boxes securely to building structure in ap- proved manner. Point up around boxes. Provide cast outlet boxes where boxes are mounted on exterior of building. Provide boxes for convenience, telephone and switch outlets as shown on the Plans. The long axis of rectangular boxes shall be vertical. • Provide pull and junction boxes of Code thickness sheet steel, with surface or flush mounting trim as required. Provide cast junction boxes where boxes are mounted on exterior of building. Provide weather-proof gasketed screw • cover pull boxes with interior baffles for separating circuits. All outlet and junction boxes, as far as practical, shall be from one manufacturer, unless otherwise noted. c•r I. 10 Outlet Locations r- Locate outlets approximately where indicated. Coordinate with other trades and relocate outlets when necessary to avoid interference with other work. Ex- - cept as otherwise indicated or specifically specified elsewhere herein, height of outlets_above floor shall be as follows: GT-I6 - • r^ r, • Wall switches 4` - 6" Convenience outlets - - - - 3' - 10" Panelboards 4' - 6" Bracket lights 6' - 10" Clock outlets 6' - 10" Bracket lights over medicine cabinet 6' - 10" I.11 Air Conditioning, Motor, and Control Wiring • Provide all wiring for air conditioning equipment, - 1 motors, combination starters, thermostats, push • buttons, selector switches, running lights, solenoid valves , and any automatic controls and mechanical equipment, unless factory furnished. � . ' All control wiring shall be in accordance with control wiring diagrams approved by Engineer. I.12 Lightning Protection Provide secondary lightning arrestors on main services. I. 13 Fixture Outlets and Supports Drawings show general location of all outlets as near as possible, but no outlet shall be installed until such locations have been approved by the Engineer. Outlets must be fitted with approved supports for fix- tures.. Contractor shall provide any channels required to support fixtures between suspended ceiling structural components. All outlet boxes must be flush with finished surfaces where finished surfaces occur. Out- let box flush device covers shall be used to bring boxes flush with finished surface. When recessed fixtures are to be used, special boxes, when required., shall be provided for connecting fixture. I.14 Lighting Fixtures Where designated, provide lighting fixtures connected to wiring system of building. Equip fixtures with glassware, reflectors, lamps, plaster rings, supports, hangers, and other accessories as required for installation in or on type of ceiling as supplied under other Dig.ision of Specifications and/or as necessary to complete installaticn ready for service. GT-17 All fixtures shall carry Underwriters' Laboratory labels. Fit fluorescent fixtures with high power factor, low noise level CBM certified rapid start Class P, auto- .matic reset ballasts. Furnish standard cool white' 4,500 degrees K fluorescent lamps. Equip incandescent fixtures with inside frosted lamps of wattage as in- dicated. Furnish all fixtures arranged to Abe light tight. Provide fixtures in strict compliance with these specs- fications. Where substitutions are offered, proposed alternate fixtures shall be the equivalent in Engineer's opinion, in all respects, including but not restricted to illuminating efficiency, material, finish, general construction and appearance. When substitutions are to be considered, Engineer may request samples of fix- tures to be submitted before he makes a final decision re- lative to any specific fixture under consideration. Sub- stitute no fixture without written approval of Engineer. I. 15 Conduct megger test of complete wiring systems. Miminum allowable resistance shall be as follows: For circuits of No. 14 or No. 12 wire, 1, 000, 000 ohms. For circuits of No. 10 of larger conductors, a resistance based upon the allowable current-carrying capacity of conductors as fixed in Tables 310-12 through 310-15 of National Electrical Code as follows: 25 to 50 amperes, inclusive 250,000 ohms 51 to 100 amperes, inclusive 100,000 ohms 101 to 200 amperes, inclusive 50,000 ohms 201 to 400 amperes, inclusive 25,000 ohms • 401 to 800 amperes, inclusive 12,000 ohms Over 800 amperes 5,000 ohms Submit record of test to Engineer for approval. Conduct operating test of completed wiring system at such time as directed by Engineer. Equipment shall be demonstrated to operate in accordance with requirements of this specification. Perform tests in presence of . Engineer or his authorized representative. Contractor shall furnish all instruments and personnel required for tests and Owner will furnish necessary electric power. GT-I8 I. 16 Quiet Operation All apparatus, equipment, components and accessories of the systems shall operate under all conditions of load without any sound or vibration which is objection- able in the opinion of the Engineer. In case of moving machinery, sound or vibration noticeable outside of the room in which it is installed, or annoyingly noticeable inside its room, will be considered objectionable. Sound - • or vibration conditions considered objectionable by the Engineer shall be corrected in an approved manner by the Contractor at his expense. I.17 Accessibility ' ' Contractor shall locate all equipment which must be serviced, operated or maintained in fully accessible positions. Equipment which shall be accessible shall include, but not be limited to, valves, traps, unions, expansion joints, dampers, clean-outs, motors, con- trollers, electrical junction or pull boxes, switch-gear, drain points, etc. If required for better accessibility, furnish access panels of a type approved by the Engineer. Access panels shall be of all steel construction with a minimum of No. 16 gauge wall or ceiling frame and a minimum of No. 14 gauge panel door. Equip doors with individual key, non-corrosive concealed hinges, rounded safety cor- ners and flexible anchor straps, except doors for wall panels may be secured with suitable clips and counter- sunk screws. Otherwise all access panels shall be flush with finished wall or ceiling. Where finished sur- face is in acoustic tile, special size and type shall be used. Panel shall be painted with a rust inhibitive primer and after installation, shall be painted with not less than two coats of lead and oil paint to match adja- cent surface. Minor deviations from drawings may be made to allow for better accessibility; changes of mag- nitude or which involve extra cost shall not be made without approval. Where access doors occur in fin- ished spaces, Engineer shall be notified and his approval obtained before locating same. I.18 Cutting and Patching • The Contractor shall furnish and locate all sleeves and inserts required before the floors and walls are built, • or shall be responsible for the cost of cutting and patch- ing required for pipes where sleeves and inserts were not installed, or were incorrectly located. The Contractor shall do all drilling required for the installation of his hangers. GT-19 All holes cut through concrete slabs or arches shall be punched or drilled from the under side. Close up any superfluous openings. All material and methods of application used for any patching, mending, or finishing must conform to the class and quality of original material. Remove all debris from premises daily. I. 19 Identification Suitably mark all thermometer cases, electric switches, starters, relays, thermostats and equipment operating accessories with black laminated plastic plates with white etched letters showing the function and use of equipment, etc. , in non-technical language. Contractor shall identify all exposed electrical power and communication feeder conduits at cabinets, pull boxes and other locations, where directed, by means of color bands and legends. Where feeder conduits are concealed, identify the feeder cable terminating in junction boxes, pull boxes, panel cabinets, terminal cabinets, and other locations, where directed, by means of engraved Bakelite identification tags, no less than 11 inch square by 1/8 inch thick with 5/32 inch top hole; fasten tags with sturdy nylon cord. Identi- fication markings shall be color-keyed for voltage, phase, etc. , and numerically listed or otherwise listed to show function of feeder or equipment served. Contractor shall furnish and install identifying tags on all electrical intercommunication cables, control con- ductors, interlocked or inter-related control circuit conductors in junction boxes, terminal cabinets, device covers, operators, relays, starters, etc. The identification tags shall show origin points, destination points and intermediate identification as required for readily trac- ing circuit wiring. Tags shall be stamped aluminum wrap-around type with black-filled designation mark- ?r ings and shall be securely fastened to the appropriate conductors. Contractor shall furnish and install a directory holder with plexiglass plate and metal frame mounted on in- side of door of each electrical branch circuit and dis- tribution panel-boards and front panes of building main GT-I10 switchboard. The directory shall be neatly typed or lettered with India ink to properly identify each circuit and mounted under plexiglass. I.20 Underground Conduit All underground conduit shall be completely encased in concrete. • • • `.1 V GT-I11 ArticleK . DISINFECTING WATER LINES K . 1 Unless otherwise specified, all water pipe shall be thoroughly disinfected in accordance with the methods set forth in AWWA standard C601-54 . Each section of pipe shall be,flushed, drained, and refilled, care being taken to avoid entraining or entrapping air in the pipe upon refilling. The pipe shall then be subjected to one of the following treatments: K •1 . 1 A chlorine gas water mixture shall be applied at the beginning of the pipe line extension, or any valved section of it, at such a rate that with a slow flow of water into the pipe the chlorine dose shall not be less than 50 parts per million. The treated water shall remain in the pipe for a • minimum of 24 hours, at the end of which period the chlorine residual is not to be less than 5 parts per million. Following chlorination the pipe shall be thoroughly flushed, tested, and if necessary 111 rechlorinated until a satisfactory bacteriological test is obtained. The Contractor shall bear the cost of all bacteriological tests. K . 1 .2 A solution of calcium hypochlorite or such chemical products as HTH, Perchioron and Maxochlor or chlorinated lime may be used in place of chlorine gas. After the pipe has been subjected to a prelim- inary flushing, a 5 percent solution of any of the aforementioned powders shall be injected into the pipe in a manner similar to that required for the addition of the liquid chlorine. Final residual and bacteriological test shall be as specified in Para- graph K . 1 . 1 . K .1 .3 Dry Calcium Hypochlorite or chlorinated lime may be used in such a manner that there shall be 1 lb. of powder, containing70 percent available chlorine for every 1 , 680 gallons of water in the pipe, equiv- s alent to 50 parts per million of available chlorine. The dry powder shall be shaken into a standpipe feed- ing the pipe line, or it may be shaken into each length of pipe as it is laid. The use of chlorine compounds in tablet form may be substituted provided a minimum of 50 ppm of available chlorine results. After the GT-K1 materials are introduced, water shall -be-admitted very slowly so as to avoid washing the powder to the end of the line . After standing for a period of at least 24 hours, the remaining requirements of Paragraph K K . 1 . 1 above shall apply. K .2 The Contractor shall obtain approval of his proposed method for accomplishing disinfection prior to initiation of water line construction. Applicable Health Department regulations shall be followed at all times. • • • y GT-K2 SPECIAL TECHNICAL PROVISIONS SECTION I DUAL BOOSTER PUMPS FOR PEACOCK HILL SECTION THREE ARTICLE 1. DESCRIPTION 1.1 Work under this section includes the furnishing of all materials, equipment, labor and incidentals necessary for the con- struction of dual, in-line booster pumps, housed in the pump shed (to be provided by the Owner) adjacent to the existing 25,000 gallon storage tank. The work shall include but not be limited to the plumb- ing and electrical wiring required to make the pumps operable and functioning. ARTICLE 2. PUMP SYSTEM PIPING 2. 1 Interior water piping shall be galvanized standard-wall treaded steel. Pipe fittings shall be galvanized standard-weight threaded malleable iron. ARTICLE 3. PUMP AND APPURTENANT EQUIPMENT 3.1 The pumping system shall consist of two, parallel, in- line, multistage booster pumps similar and equal to Red Jacket, Big- flo 28 GPM series "DC" submerga pumps model number E 300 TI-11 DC, bronze construction capable of developing 28 gpm at 280 feet of total head. The pump motor shall be 3 horsepower, single phase, 230 volt. 3.2 The pumps shall be housed in a 4 inch minimum I.D. pipe with flanged ends and pressure tight electrical connector for motor leads to make a pump package. ARTICLE 4. VALVES 4.1 Valves for interior piping shall be gate valves with minimum working pressure rating of 200 psi. Valves shall be iron body, bronze mounted, double disc, parallel seat, non-rising stem. All working parts shall be bronze or bronze mounted. Provide valve with handwheels. 4.2 Check valves shall be swing-check type, designed for working pressure of 150 psi with a suitable opening for cleaning without disconnecting from the pipe. The valve shall be all bronze or cast iron body with brass or bronze trim. The pin, seat ring, and disc face shall be of brass or bronze. ARTICLE 5. ELECTRICAL WORK 5. 1 Electrical work shall be performed in accordance with the STI-1 applicable portions of the General Technical Provisions and the National Electrical Code. It shall consist of the wiring and circuitry necessary to energize and control the two booster pumps. Single phase service is presently available for the new pumps. ARTICLE 6. INSTRUMENTATION AND CONTROLS 6.1 Starting and stopping of the booster pumps shall be controlled by the water pressure at the pumps, which reflects the elevation of the water in the high storage tank. A pressure interlock shall also be provided to stop the pumps if the supply tank is low. 6.2 The control system shall automatically perform the following functions: a. start the pump when the water level in the high storage tank is half full. b. stop the pump when the high tank is full. c. stop the pump when the 25,000 gallon tank cannot provide at least 10 feet (23 psi) of head to the supply side of the pump. STI-2 SPECIAL TECHNICAL PROVISIONS SECTION II 13,200 GALLON STORAGE TANK FOR PEACOCK HILL SECTION III ARTICLE 1. DESCRIPTION 1.1 Work under this section includes the furnishing of all materials, equipment, labor, and incidentals necessary for the construc- tion of the storage tank complete, in place, ready for use. It shall include but not be limited to clearing and grubbing, excavation of all materials of any nature including solid rock, site grading, backfilling for structures, landscaping, and installation of exterior piping to a distance of two (2) feet from the tank. 1.2 Material composition and installation practices for the various items of work shall comply with applicable portions of the General Technical Provisions, unless otherwise specified. ARTICLE 2. SITE WORK 2.1 Storage tank site work shall consist of the following items: a. All clearing and grubbing required for site work. b. Earthwork and grading as shown on the Plans. c. Excavation and backfill for structures. d. Landscaping. Site work shall conform to the applicable portion of the General Technical Provisions. 2.2 After completion of the storage tank, the Contractor shall be responsible for returning the access road to a serviceable condition. This shall consist of grading to dress up the roadbed and ditches and placing approximately four (4) inches of crusher run stone for a width of 10 feet. The road shall not be graded or graveled until all heavy construction equipment has left the site. Crusher run stone shall conform to applicable sections of the General Technical Provisions. 2.3 All areas of raw earth resulting from site work shall be topsoiled, seeded, fertilized, and mulched in strict accordance with the General Technical Provisions. 2.4 Final Clean-up - The storage tank site shall be cleaned of all rubbish, debris, trash or extraneous materials of any nature which detract from the appearance of the site. STII-1 All areas of the work shall be left in a neat and present- able condition. There shall be no evidence of soil erosion or distrubance within the work area. The Contractor shall remove all of his plant, equipment and material from the Owner's property within 30 days from the date of final acceptance. ARTICLE 3. 13,200 GALLON STORAGE TANK 3.1 The storage tank shall be approximately 10 feet 6 inches diameter by 20 feet 6 inches long, with a nominal capacity of 13,200 gallons, in full accordance with AWWA D 100 Standards. 3.2 The tank shall be fabricated from 1/4-inch thick steel plate. Welding and miscellaneous metal fabrication shall confoiiu to applicable portions of the General Technical Provisions. The tank supplier shall submit shop drawings and supporting design data to the Engineer for review and approval prior to fabrication of the tank. 3.3 The tank shall be equipped with one 20 inch diameter man- way. The manway shall have a 4-inch steel curb. The roof manway shall be provided with a steel cover with a rim which overlaps the manway curb by two inches. The cover shall be hinged to the curb and shall have a locking hasp. - i- , .- ' .- . •- 3.4 The tank shall have a 6-inch steel overflow pipe firmly attached to the outside of the tank. The outlet end of the overflow pipe shall be fitted with 100-mesh screen. A concrete splash block shall be placed on the ground below the overflow pipe outlet to prevent soil erosion. The overflow pipe shall be painted to match the tank. 3.5 A 4-inch steel gooseneck vent pipe shall be installed on the top of the tank. The open end of the vent pipe shall be fitted with 100-mesh screen. The vent pipe shall be painted to match the tank. 3.6 A 4-inch cast iron drain pipe shall be attached to the bottom of the tank. The outlet end of the drainpipe shall emerge at the natural ground line and shall be fitted with 100-mesh screen. A concrete splash block shall be provided at the outlet end to prevent soil erosion. The connection between drainpipe and tank shall be watertight. 3.7 The tank fill pipe may be of the same material used in the water distribution system. The fill pipe shall have a watertight connection with the tank. The end of the fill pipe shall be equipped with a 4-inch high removable silt stop. 3.8 Gate valves on the drain and fill pipes shall be cast iron with a minimum working pressure rating of 150 psi. Gate valves shall have non-rising stems and "0" ring type pressure seals. All working parts shall be bronze or bronze-mounted. STII-2 .9 A steel ladder, painted to match the tank, shall b- -.:-v-: rely fastene. •e side of the tank closest to the m.. . .e rails shall be 2-inch . :-inch steel bar "•e s used to fasten the side rails to the tank s :va.<< --.401/2-inch by 3/8-inch steel. Rungs shall be 3/4-inch -- . steel bars an. .e spaced 12 inches apart on center -..ove the topmost bracket, there s a ungs and th- -'.- rails shall be separated by 24 inches to facilitate - to the manway. 3.10 The paint for the interior and exterior of the tank shall comply with AWWA Standard D 102-64 "Painting and Repainting Steel Tanks for Water Storage". The paint used on the tank interior must be on the approved paint list of the Virginia State Department of Health. Industrial Paint Company' s "Nocoro" Paint Products are specified as standards of quality and the usual "or equal" clause shall apply. The tank painting requirements shall be as described below. 3.10.1 Surface Preparation: The surface preparation of the tanks shall comply with Specification AWWA D 102-64 and specifically: a. SURFACE PREPARATION: All steel surfaces shall be prepared by the fabricator as in Steel Structures Painting Council SSPC-SP6-63 "Commercial Blast Cleaning" or SSPC-SP8-63 "Pickling" . v After blast cleaning, all surfaces shall be throughly and completely cleaned of any residue or dust before applying primer. b. FIELD SURFACE PREPARATION: After the tank is in place, unprimed areas shall be cleaned by using SSPC-SP6-63 "Commercial Blast Cleaning". The shop primed surfaces shall be cleaned of all dirt and foreign matter. Dust that has settled on any part of the tank as a result of the blast cleaning must be removed before spot priming. Primer must be applied within 24 hours after blast cleaning. 3.10.2 The painting of the tank shall comply with Specification AWWA D 102-64. Brush application of all paint coats preferred. Other method of application must have written approval of the Engineer. a. Interior Painting - FIRST COAT: Nocoro Red Vinyl Coating M-8020. Paint all surfaces with one coat. Dry film thickness 1-1/2 mils. FIELD SPOT COAT: Nocoro Red Vinyl Coating M-8020. All unprimed or abraded areas shall be spot primed. Dry coating thickness 1-1/2 mils. Allow 12 hours before recoating. STII-3 THIRD COAT: Nocoro Aluminum Vinyl Coating M-8023-G. Paint the entire interior surface. Dry film thickness 1 mil. Minimum acceptable dry coating thickness for the 3 coats - 5 mils. Allow tank to dry at least 120 hours (5 days) before the tank is filled with water. b. Exterior Painting - FIRST COAT: Nocoro Red Vinyl Coating M-4983. Paint all surfaces with one coat, to a dry film thickness of 1-1/2 mils. FIELD SPOT COAT: Nocoro Red Vinyl Coasting M-2983. All unprimed or abraded areas shall be spot primed to a dry coating thickness of 1-1/2 mils. Allow 12 hours before recoating. SECOND COAT: Nocoro Vinyl Finish Coat M-7000 Series (see below for correct code number) . Paint the entire exterior surface to a dry film thickness of 1-1/2 mils, making a total of first and second coats 3 mils. Allow 12 hours before recoating. THRID COAT: Nocoro Vinyl Finish Coat M-7000 Series (color to be selected by Owner) . Paint the entire exterior surface to a dry film thickness of 1-1/4 to 1-1/2 mils. The minimum dry coating thickness for the 3 coats must be 4 mils. 3.11 The tank shall be set plumb and securely attached to concrete supports. Concrete and reinforcing steel used in the supports shall be as specified in the General Technical Provisions. 3.12 The tank shall be tested in accordance with the applicable provisions of AWWA Standard D 100-73 Section 12. 3. 13 Disinfection of the tank shall be accomplished as follows: After the paint has thoroughly dried, the tank shall be filled slowly to the overflow level with potable water to which enough chlorine has been added to produce a concentration of 50 ppm in the full tank. The chlorine, either as high-test calcium hypochlorite or liquid chlorine, shall be introduced into the water as early in the filling operation as possible. After the tank has been filled, it shall stand full for 24 hours. At the end of the holding period, the highly chlorin- ated water shall be completely drained to waste and the tank shall be refilled from the regular supply. Bacteriological samples shall be taken and approved by the State Health Department. 3.14 The Contractor shall furnish all materials and equipment, with the exception of water, for the testing and disinfection of the tank. Water will be furnished by the Owner at no cost to the Contractor. ARTICLE 4. MEASUREMENT AND PAYMENT 4.1 No measurement will be made for payment under this Section. 4.2 Payment under this Section will be at the contract lump sum for the storage tank, complete and ready for use. STII-4 • a M SPECIAL TECHNICAL PROVISIONS SECTION III WATER DISTRIBUTION SYSTEM FOR PEACOCK HILL SECTION III ARTICLE 1. DESCRIPTION 1.1 Work under this Section includes the furnishing of all materials, equipment, labor, and incidentals, necessary for the con- struction of the water lines, valves, valve boxes, fittings, complete, in place, ready for use. It shall include but not be limited to clearing and grubbing, excavation of all materials of any nature, including solid rock, trenching, backfilling, and incidentals. 1.2 Material composition and installation practices for the various items of work shall comply with applicable portions of the General Technical Provisions, unless otherwise specified. ARTICLE 2. WATER PIPE AND APPURTENANCES 2.1 Materials 2.1.1 Water pipe shall be "Bell Tite" PVC (polyvinyl chloride) as manufactured by Anesite Division, Clow Corporation, or approved equal. Pipe shall be joined by means of push-on rubber ring joints. The rubber ring joint gasket shall be contained within a bell which is an integral and homogeneous part of the pipe barrel. A lubricant re- commended by the pipe manufacturer shall be used in making the joints. Pipe shall conform to all requirements of commercial standard CS-256-63 for PVC and shall have minimum working pressure rating of 150 psi. Pipe shall bear the National Sanitation Foundation seal of approval and will comply with the requirements for Type 1, Grade 1 (PVC 1120) of the ASTM resin specification D-1784-68, and ASTM designation D-2241, standard specification for PVC pipe (SDR-PR) . 2.1.2 Fittings shall be PVC with push-on joint compatible with the type of pipe used. If PVC fittings are not available for the type and size of pipe used, fittings may be cast iron with mechanical joint ends or cast iron with push-on joints. All fittings shall have a minimum working pressure rating of 150 psi. 2.1.3 Gate valves shall be cast iron with a minimum working pressure rating of 150 psi. Gate valves shall have non-rising stem and "0" ring type pressure seals. All working parts shall be bronze or bronze- mounted. Valve joint ends shall be either of the mechanical or push-on type. 2.1.4 Valve boxes shall be equivalent to Mueller H-13204 plastic valve boxes with cast iron collar and cast iron lid. STIII-1 2.1.5 Blowoff assemblies shall consist of a 1-1/2-inch gate valve with box and cover, and sufficient 1-1/2-inch pipe for discharge to water course or daylight. Underground pipe used in the assembly may be PVC, but above-ground pipe shall be cast iron. Pipe, fitting, and valves used in the assembly shall have quality and strength character- istics compatible with those used in construction of the water main. 2.2 Construction Methods 2.2.1 Valves and fittings shall be installed in accordance with the manufacturer's recommendations. Valve box covers shall be set flush with paved surfaces and 4 inches above ground in fields, woods, and other open areas. 2.2.2 Trenches shall be excavated to a depth sufficient to provide a minimum pipe cover of 36 inches upon completion of earthwork to the lines and grades shown in the Plans. 2.2.3 Water lines shall be installed in accordance with the General Technical Provisions for Laying Condition 2. 2.2.4 All water lines shall be thoroughly tested and disinfected in accordance with the General Technical Provisions. This Contract shall include disinfection of the service connections, which will be installed under a separate contract. 2.2.5 Thrust blocks shall be 3,000 psi (AE) concrete and shall be used at all bends, branch fitting and dead ends. In fill or un- stable soil material, the pipe shall be strapped or otherwise securely fastened to the thrust block. The method of tying pipe to thrust blocks shall be approved by the Engineer prior to construction. ARTICLE 3. MEASUREMENT AND PAYMENT 3. 1 Pipe length shall be based on horizontal measurement in- cluding the space occupied by fittings and valves. 3.2 Payment shall be at the contract unit price per foot of pipe, complete in place, with fittings, valves, collars, encasement, and thrust blocks. STIII-2 SPECIAL TECHNICAL PROVISIONS SECTION IV WATER SERVICE CONNECTIONS FOR PEACOCK HILL SECTION III ARTICLE 1. DESCRIPTION 1.1 Work under this Section includes the furnishing of all materials, equipment, labor, and incidentals necessary for the in- stallation of 30 water service connections at locations to be desig- nated by the Engineer. 1.2 Material composition and installation practices shall comply with applicable portions of the General Technical Provisions, unless otherwise specified. ARTICT,F 2. MATERIALS 2.1 Water service lines shall be 3/4-inch diameter tubing manufactured from polybutylene or polyethylene. Polybutylene tubing shall meet the requirements of Grade II, Type 1 polybutylene as defined by ASTM D-2581. Polyethylene tubing shall meet the require- ments of Type III, Class C, Category 5, Grade P34 polyethylene as defined by ASTM D-1248. Water service tubing shall have a minimum working pressure rating of 150 psi. Tubing shall be marked with size, manufacturer's name, working pressure rating, and National Sanitation Foundation approval for potable water distribution. 2.2 Water meters shall be 3/4-inch Hersey Model MMD or equal approved by the Engineer. The minimum working pressure rating for water meters shall be 150 psi. The meter selected shall be from a manufacturer who can supply compatible accessories for future conver- sion of meters to remote punched card or magnetic tape readout. Meter boxes shall be assembled from lengths of 15-inch I.D. concrete pipe, notched at the base to fit neatly over the service pipe. Each meter box shall be fitted with a cast iron frame and cover equivalent to Ford Catalog No. C31. The meter box lid shall be standard weight, 11-1/2 inches in diameter. As shown on the Plans, the meter shall be installed with a coppersetter and angle meter valve that are compatible with the water meter. ARTICLE 3. CONSTRUCTION METHODS 3.1 Water service connections shall be made by tapping water mains at locations designated by the Engineer. A corporation stop shall be inserted into the top of the main at each connection. The end of the 3/4-inch tubing shall be attached to the corporation stop with a compression fitting. STIV-1 3.2 The 3/4-inch service line shall be laid to the property line and terminated in a meter box, which will be located on the property line. Trenches for service connections shall be excavated to allow a minimum of 36 inches of cover over the tubing. The tubing shall be snaked from side to side in the trench to compensate for contraction and settling of backfill. Tubing shall be installed in accordance with the General Technical Provisions for Laying Condition 2. Backfilling of trenches shall be accomplished in accordance with the General Technical Provisions. 3.3 Following installation of service connections, pressure testing shall be accomplished in accordance with the General Technical Provisions. 3.4 Disinfection of the service connections shall not be included in this Contract, but will be the responsibility of the Contractor for the main lines. ARTICLE 4. MEASUREMENT AND PAYMENT 4.1 Pipe length shall be based on horizontal measurement including the space occupied by fittings and valves. The quantity of water meter assemblies shall be based on the number in place and ready for use. The water meter assembly shall consist of the meter, meter box and cover, crusher run stone within the box, coppersetter, meter angle, valve, and fittings needed to connect the service line to the meter and complete the installation as shown on the Plans. 4. 2 Payment for the service line shall be at the Contract unit price per foot of tubing, complete with any valves and fittings required between water main and meter box. Payment for the meter box assemblies shall be at the Contract unit price per each assembly. 2. Consumption. The present rate of consumption is 155 gallons per day per service. It can be expected that the future rate of consumption will be essentially the same. 3. Yield of source. The present well yields 38 gpm and is stored in a 25,000 gallon tank. An additional 28 gpm well is ready for service when needed. (f.) Fire Flow Requirements Fire flow is not required. Dry hydrants are provided in the area, fed by ponds. (g.) Sewerage system available Sewerage facilities consist of septic tanks for each unit in a cluster, piping to a mass septic tank and then to mass drainfields. The drainfields have all been located and approved by local sanitarians for the State Health Department with the well locations in mind. (h. ) Source of water supply The source for this section is an existing well that was approved and permitted when the system started in 1975. For further information, please refer to the original reports. (i.) Proposed treatment processes Since the source is the existing approved well and chlorination process, please refer to the original report. (j. ) Waste disposal There is no waste disposal from the water treatment process. (k. ) Automatic equipment The automatic. equipment consists of the pressure controls that actuate the pumps. The pressures are set to keep the existing tank at least 80% full. (1.) Project sites 1. Various sites considered. The best possible place to located the pump is at the existing -3-