Road and Drainage Plan Review
Project title: Foothill Crossing HA - Amendment
Project file number: SUB-2016-00237
Plan preparer:
Collins Engineering [scott@collins-engineering.com]
Owner or rep.:
Foothill Crossing, Inc.
Plan received date:
22 November 2016
(Rev. 1)
22 February 2017
Date of comments:
7 February 2017
(Rev. 1)
21 April 2017
Reviewers:
Matt Wentland
Scott,
We have reviewed the plans and have the following comments:
Engineering
1. An amendment to the approved VSMP plan will need to be approved before the road plans can be
approved. (Rev. 1) The plans should also be updated to reflect the WPO amendment. The
changes included in the Glenbrook plans can be done in a later road plan amendment.
2. Provide overland relief between lots 29 & 30 for flows bypassing inlet 26. (Rev. 1) Comment
addressed.
3 . Provide the design calculations for the yard inlets. (Rev. 1) Comment addressed.
Planning — Will Cockrell
-In the landscape sheet, the number of trees does not match the amount shown on the plan. Please
correct and ensure that the plantings table is consistent with the plan.
- Show revisions to the road plan for the additional proposed access on Park Ridge Drive.
VDOT, ACSA, and Fire Rescue currently have no objection to the plan.