HomeMy WebLinkAboutSUB201400207 Bond Estimates 2017-05-12Cascadia Blocks 1-3 Phase 3
Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer)
Plan # SUB201400207
Item
Delphi Drive Ext.
Begin station
End station
aggregate base
blotted or prime&double seal
asphalt base
asphalt surface
curb CG-2
curb CG-6
sidewalk, concrete (6')
ramp CG-12
street name sign
traffic control sign
Street Landscape
guardrail
drop inlet or grate
standard manhole frame top (not inlet)
manhole structure (per ft. rise)
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (60 to 108")
rip -rap, placed
matting, EC-2 or 3
clear and grub (for wooded sites)
cut grading
fill grading
as -built drawings (ik+ price per 0.1 mi.)
survey and layout (price per 0.1 mi.)
mobilization
materials testing
compaction testing
CBR tests (1 every 0.1 mi. per road)
stone depth inspections
pavement inspections
pipe and drainage video inspections
VDOT surety (1 lane)
VDOT maintenance fee (1 In rd, 1 yr)
VDOT admin. Cost recovery fee(1 lane)
No. Unit
Unit Cost
Cost
installed
% compete cost remaining
11 +72.00
18+36.00
road length 664.0 ft
6.0 in d
664.0 ft L 30.0 ft W
697.2 ton
$35.00
$24,402.00
0%
$24,402.00
664.0 ft L 0.0 ft W
0.0 sy
$10.00
$0.00
0%
$0.00
2.5 in d
664.0 ft L 26.0 ft W
264.4 tons
$100.00
$26,435.50
0%
$26,435.50
1.5 in d
664.0 ft L 26.0 ft W
158.6 tons
$120.00
$19,033.56
0%
$19,033.56
0.0 ft
$13.00
$0.00
0%
$0.00
1328.0 ft
$15.00
$19,920.00
0%
$19,920.00
1228.0 ft
$17.00
$20,876.00
0%
$20,876.00
4 ft
$350.00
$1,400.00
0%
$1,400.00
2 each
$200.00
$400.00
0%
$400.00
8 each
$200.00
$1,600.00
0%
$1,600.00
20 Each
20 each
$275.00
$5,500.00
0%
$5,500.00
0 ES @ 3000
0.0 ft
$17.00
$0.00
0%
$0.00
11 each
$3,500.00
$38,500.00
0%
$38,500.00
0 each
$500.00
$0.00
0%
$0.00
81 ft
$450.00
$36,450.00
0%
$36,450.00
15.0 in d
0 ES-1,2 r 0 EC-1
664.0 ft
$35.00
$23,240.00
0%
$23,240.00
24.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$50.00
$0.00
0%
$0.00
18.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$40.00
$0.00
0%
$0.00
18.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$40.00
$0.00
0%
$0.00
96.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$320.00
$0.00
0%
$0.00
2.0 ft d
0.0 ft L ft W
0.0 ton
$60.00
$0.00
0%
$0.00
0.0 ft L ft W
0.0 sy
$2.00
$0.00
0%
$0.00
0.0, ft L ft W
0.0 acre
$24,000.00
$0.00
0%
$0.00
-CY
$4.00
$20,000.00
0%
$20,000.00
cy
$9.00
$0.00
0%
$0.00
664.0 ft L 0.12576 mi.
2 Isum
$2,000.00
$5,000.00
0%
$5,000.00
664.0 ft L 0.12576 mi.
2 Isum
$2,000.00
$5,000.00
0%
$5,000.00
-Isum
$5,000.00
$5,000.00
0%
$5,000.00
664.0 ft L 1.328 inc of 500'
2 each
$200.00
$480.00
0%
$480.00
664.0 ft L 1.328 inc of 500'
2 each
$200.00
$480.00
0%
$480.00
664.0 ft L 1.328 inc of 500'
2 each
$200.00
$480.00
0%
$480.00
664.0 ft L 1.328 inc of 500'
2 each
$200.00
$480.00
0%
$480.00
664.0 ft L 1.328 inc of 500'
2 each
$200.00
$480.00
0%
$480.00
"'Mft
$1.00
$664.00
0%
$664.00
664.0 ft L 0.12576 mi.
2 Lanes
$2,000.00
$5,030.30
0%
$5,030.30
664.0 ft L 0.12576 mi.
2 Lanes
$150.00
$377.27
0%
$377.27
664.0 ft L 0.12576 mi.
2 Lanes
$100.00
$501.52
0%
$501.52
C:\Users\mwentland\Documents\SUB201400207 Cascadia Blocks 1-3 Phase 3 RP bond est 05-12-17.xls 5/12/2017
Cascadia Blocks 1-3 Phase 3
Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer)
Plan # SUB201400207
Item
Delphi Drive Ext.
No. Unit Unit Cost Cost
(installed) % compete cost remaining
cost sum $261,730.15 $261,730.15
contingency $26,173.02 $26,173.02
Total $287,910 $287,910
C:\Users\mwentland\Documents\SUB201400207 Cascadia Blocks 1-3 Phase 3 RP bond est 05-12-17.xls 5/12/2017
Cascadia Blocks 1-3 Phase 3
Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer)
Plan # SUB201400207
Item
Knoll Lane
Begin station
End station
aggregate base
blotted or prime&double seal
asphalt base
asphalt surface
curb CG-2
curb CG-6
sidewalk, concrete (6')
ramp CG-12
street name sign
traffic control sign
Street Landscape
guardrail
drop inlet or grate
standard manhole frame top (not inlet)
manhole structure (per ft. rise)
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (15 to 48")
pipe, rcp, cmp (60 to 108")
rip -rap, placed
matting, EC-2 or 3
clear and grub (for wooded sites)
cut grading
fill grading
as -built drawings (ik+ price per 0.1 mi.)
survey and layout (price per 0.1 mi.)
mobilization
materials testing
compaction testing
CBR tests (1 every 0.1 mi. per road)
stone depth inspections
pavement inspections
pipe and drainage video inspections
VDOT surety (1 lane)
VDOT maintenance fee (1 In rd, 1 yr)
VDOT admin. Cost recovery fee(1 lane)
No. Unit
Unit Cost
Cost
installed
% compete cost remaining
10+00.00
13+25.00
road length 325.0 ft
6.0 in d
325.0 ft L 21.0 ft W
238.9 ton
$35.00
$8,360.63
0%
$8,360.63
325.0 ft L 0.0 ft W
0.0 sy
$10.00
$0.00
0%
$0.00
2
in d
325.0 ft L 19.0 ft W
94.6 tons
$100.00
$9,455.47
0%
$9,455.47
1
in d
325.0 ft L 19.0 ft W
56.7 tons
$120.00
$6,807.94
0%
$6,807.94
or 32gft
$13.00
$4,225.00
0%
$4,225.00
325.0 ft
$15.00
$4,875.00
0%
$4,875.00
0.0 ft
$17.00
$0.00
0%
$0.00
0 ft
$350.00
$0.00
0%
$0.00
2 each
$200.00
$400.00
0%
$400.00
6 each
$200.00
$1,200.00
0%
$1,200.00
Each
2 each
$275.00
$550.00
0%
$550.00
ES @ 3000
0.0 ft
$17.00
$0.00
0%
$0.00
1 each
$3,500.00
$3,500.00
0%
$3,500.00
1 each
$500.00
$500.00
0%
$500.00
10 ft
$450.00
$4,500.00
0%
$4,500.00
15.0 in d
0 ES-1,2 r 0 EC-1
74.0 ft
$35.00
$2,590.00
0%
$2,590.00
18.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$40.00
$0.00
0%
$0.00
18.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$40.00
$0.00
0%
$0.00
18.0 in d
0 ES-1,2 0 EC-1
0.0 ft
$40.00
$0.00
0%
$0.00
96.0 in d
0 ES-1,2 0 EC-1
O.O ft
$320.00
$0.00
0%
$0.00
2.0 ft d
0.0 ft L ft W
0.0 ton
$60.00
$0.00
0%
$0.00
0.0 ft L ft W
0.0 sy
$2.00
$0.00
0%
$0.00
L ft W
0.0 acre
$24,000.00
$0.00
0%
$0.00
_O.O,ft
-CY
$4.00
$4,600.00
0%
$4,600.00
cy
$9.00
$0.00
0%
$0.00
325.0 ft L 0.06155 mi.
1 Isum
$2,000.00
$3,000.00
0%
$3,000.00
325.0 ft L 0.06155 mi.
1 Isum
$2,000.00
$3,000.00
0%
$3,000.00
-Isum
$5,000.00
$5,000.00
0%
$5,000.00
325.0 ft L 0.65 inc of 500'
2 each
$200.00
$340.00
0%
$340.00
325.0 ft L 0.65 inc of 500'
2 each
$200.00
$340.00
0%
$340.00
325.0 ft L 0.65 inc of 500'
2 each
$200.00
$340.00
0%
$340.00
325.0 ft L 0.65 inc of 500'
2 each
$200.00
$340.00
0%
$340.00
325.0 ft L 0.65 inc of 500'
2 each
$200.00
$340.00
0%
$340.00
'74 ft
$1.00
$74.00
0%
$74.00
325.0 ft L 0.06155 mi.
0 Lanes
$2,000.00
$0.00
0%
$0.00
325.0 ft L 0.06155 mi.
0 Lanes
$150.00
$0.00
0%
$0.00
325.0 ft L 0.06155 mi.
0 Lanes
$100.00
$0.00
0%
$0.00
C:\Users\mwentland\Documents\SUB201400207 Cascadia Blocks 1-3 Phase 3 RP bond est 05-12-17.xls 5/12/2017
Cascadia Blocks 1-3 Phase 3
Road and Infrastructure Construction Bond Estimate (roads, site work, storm sewer)
Plan # SUB201400207
Item
Knoll Lane
No. Unit Unit Cost Cost
(installed) % compete cost remaining
cost sum $64,338.03 $64,338.03
contingency $6,433.80 $6,433.80
Total $70,780 $70,780