Subdivision Bond Inspection
Bond Title: Old Trail Village Block 27
File Number: SUB2015-000123
Date of inspection: June 2, 2017
Reviewer: Emily Cox Original Bond Amount: $483,880 [20%=$96,776]
Phone: (434) 296-5832 Current Bond Amount: $483,880
Your bond inspection request has been processed. This list contains an update on the items
received and approved.
Received
Approved
Y
N
Y
N
N/A VDOT
■
❑
Completed inspection request and fee
■
❑
❑ ❑
■
❑
As -built plan, updated, sealed to current date, per As -built policy
❑
■
❑ ❑
■
❑
Copies of recorded plats for right-of-way, easements
■
❑
❑ ❑
■
❑
VDOT approval AM-4.3, or partial completion via punchlist
❑
❑
❑ ■
■
❑
Letter from P.E. certifying improvements are built to plan
■
❑
❑ ❑
❑
■
Current certification form completed by owner/developer
❑
■
❑ ❑
■
❑
CBR test reports for each road
❑
■
❑ ❑
■
❑
Stone depth and material inspection reports (or core tests)
❑
■
❑ ❑
■
❑
Pavement depth and material inspection reports (or core tests)
■
❑
❑ ❑
■
❑
Compaction test reports for fill areas under road
■
❑
❑ ❑
❑
■
Pipe trench inspection reports
❑
❑
■ ❑
■
❑
Pipe interior inspections reports and video
❑
■
❑ ❑
■
❑
Concrete test reports for structural concrete, curbing, aprons, etc.
■
❑
❑ ❑
❑
■
Structural inspection reports for any bridges or box culverts
❑
❑
■ ❑
❑
■
county road name signs and posts, or a sign agreement for alt. posts
❑
❑
❑
Updated bond amount based on completed work: $107,300.00
(See attached Bond Estimate form for breakdown of bond amount and remaining items.)
Notes:
As -built Plan:
• Please provide as -built landscaping sheet.
• Please show all pavement markings.
• Please show the final pavement design.
Field Visit:
• Several signposts were not vertical. Please ensure they are all installed correctly.
• Please install the no parking signs as shown on the approved plan.
• Please install landscaping as shown on the approved plan. It appears to be about 50% complete.
• One CG-12 had several severe cracks. It appeared to already be marked with orange paint, but
please ensure these cracks are fixed.
Other:
• CBR testing results were not provided for all roads.
• Provide stone depth for all roads.
• Provide certification of completion.
• Complete all items on VDOT punchlist.
• Pipe video: several pipes appear to have debris in them, please flush/clean the pipes.
• Provide stone depth reports
Please refer to on-line content at http://www.albemarle.org/deptfonns.asp?department=cdengw�o for
checklists and procedures.