HomeMy WebLinkAboutSDP201600070 Review Comments Initial Site Plan 2016-01-05COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 January 5, 2016 Mike Myers 172 South Pantops Drive, Suite A Charlottesville, VA 22902 mmyersAdominioneng com RE: SDP201600070 Springhill/Towneplace Suites — Initial Site Plan Dear Mr. Myers: The Site Review Committee has reviewed the development proposal referenced above. Initial comments from the following divisions of the Department of Community Development and other agencies, as applicable, are attached: Albemarle County Planning Services (Planner) Albemarle County Engineering Services (Engineer) Albemarle County Information Services (E911) Albemarle County Building Inspections Albemarle County Architectural Review Board (attached) Albemarle County Department of Fire Rescue Albemarle County Service Authority (attached) Rivanna Water and Sewer Authority Virginia Department of Transportation (attached) Comments reflect information available at the time the proposal was reviewed and should not be considered final. However, the Site Review Committee has attempted to identify all issues that are required to be resolved prior to final approval. The applicant should work with each of the reviewers individually to address the comments provided. Once all of the comments have been addressed, the Lead Reviewer will request copies for final signature by each reviewer. Please contact me at your earliest convenience if you have questions or require additional information. Sincerely, J.T. Newberry Senior Planner CC: Daly Seven 1420 Lee Jackson Highway Lynchburg, VA 24503 SSQ, LLC 3002 Berkmar Drive Charlottesville, VA 22901 Albemarle County Planning Services (Planner) — J.T. Newberry, jewberry a,albemarle.org — Requested changes 1. [Section 32.6.2(h)] — On the final site plan, on Sheet SP1, please add signature lines for all of the members of the Site Review Committee. 2. [General Question/Comment] — On Sheet SP2, under Parking Requirements, how many total ADA spaces are required? Please consolidate this information for clarity (see also comments from Building Official below). 3. [Section 32.5.2(a)] — Sheet SP1 notes the Prior Zoning Approvals, but does not also show their conditions. Please update this section on the final site plan. As a reminder, Condition #3 of the special use permit requires the ARB to approve the landscape plan prior to final site plan approval. 4. [Section 32.5.2(a)] — Sheet SP2, under Building Setbacks, please remove the language that states "(whichever is more restrictive)". 5. [Section 32.5.2(i) and (m)] — On Sheet SP6, should the proposed access easement to the "future development parcel" be enlarged to encompass both sides of the access aisle? 6. [Section 32.5.2(i)] — Will this site have any outdoor lighting? If so, please submit a photometric plan. A photometric plan may be necessary to confirm compliance with Section 4.17.4(b) even if no lighting above 3,000 lumens is proposed. 7. [Section 32.5.2(p)] — Will there be enough plantable area to provide the required landscaping within a parking area under Section 32.7.9.6? Albemarle Co. Planning Services (Architectural Review Board) — Margaret Maliszewski, mmaliszewskigalbemarle.org 1. See attached. Albemarle County Engineering Services (Engineer) — Emily Cox, ecox(&albemarle.org — Requested changes 1. Ensure all Radii are labeled. 2. Note that WPO plan will be necessary at time of final site plan. 3. Note that more information will needed for retaining walls at time of final site plan Albemarle County Department of Fire Rescue — Robbie Gilmer, railmergalbemarle.org — Requested changes 1. Fire flow test required before final approval. Please attach a copy of the test to the final plans. 2. Add a note to the plans stating a Fire Department Knox Box is required. Albemarle County Information Services (E911) — Derek Bedarf, dbedarf(c-r�,albemarle.org — No objection Albemarle County Building Inspections, Jay Schlothauer, jschloth@albemarle.org —No objection 1. Based on the total number of parking spaces (192), seven of them must be barrier -free. Provide one more barrier -free parking space with its associated striped access aisle. Albemarle County Service Authority — Alex Morrison, aorrison@serviceauthority.org 1. See attached. Rivanna Water and Sewer Authority — Victoria Fort, vfort&rivanna.org, 434-977-2970, ext. 205 — Requested changes 1. There is a proposed connection to the 21" RWSA Sewer Interceptor parallel to Hillsdale Drive. RWSA must review and approve utility plans before a connection will be allowed. Additionally, there is an existing 4" lateral connection where the new sewer connection is proposed, so the design will have to be revised to show existing utilities and eliminate this conflict. Virginia Department of Transportation — Adam Moore, Adam.Moore(cr�,vdot.vir ig nia.gov — See attached COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 MEMORANDUM TO: JT Newberry FROM: Margaret Maliszewski RE: ARB-2016-70: Springhill Townplace DATE: December 13, 2016 On August 15, 2016 the ARB completed a review of the above -noted request, which included the review of both an original plan and a revised plan. Subsequently, the applicant submitted an Initial Site Plan to the County. Because the Initial Plan is consistent with the plan previously reviewed by the ARB, another ARB review is not needed at this time, and I am forwarding the ARB's preliminary comments to be used as Initial Site Plan comments. • Regarding requirements to satisfy the design guidelines as per § 18-30.6.4c (2), (3) and (5): A Certificate of Appropriateness is required prior to final site plan approval. The following items shall be addressed in the final site plan submittal: 1. Provide material and color samples for review. 2. Provide a mix of shrubs in an irregular pattern to screen the dumpster from the EC street. 3. Provide a dumpster screen detail in the site plan. Shift the parcel line or shift the dumpster location so that the dumpster is entirely on the hotel parcel after subdivision. 4. Clarify on the drawings the location and appearance of the elevator penthouse and any associated equipment. 5. If existing trees are proposed to remain on -site or off -site in the landscape easement after construction, indicate their location, size and species on the plan. 6. Add trees 2'/2" caliper at planting, 40' on center, along the southern side of the southern access drive. 7. Revise the plan to define the planting area for the trees to be added along the EC frontage. 8. Increase the depth of the planting area for trees on the south side of the parking lot or clarify how the trees will thrive in the minimal planting area provided. 9. Intersperse trees along the north side of the building, particularly at the east end, and place them to coordinate with the architectural design. 10. Identify on the plan the material, manufacturer and color proposed for the retaining walls. 11. Include the standard window glass note on the architectural drawings: "Visible light transmittance (VLT) shall not drop below 40%. Visible light reflectance (VLR) shall not exceed 30%." Provide specs and a glass sample for review. 12. Add the standard mechanical equipment note to the architectural drawings: "Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated." ***Additional requirements: 1) the landscape plan shall reflect the plant size requirements in the Entrance Corridor Design Guidelines, and 2) the final site plan submittal shall include all items on the ARB Final Site Plan checklist. Regarding recommendations on the plan as it relates to the guidelines: o None. • Regarding recommended conditions of initial plan approval: o None. • Regarding conditions to be satisfied prior to issuance of a grading permit: o None. Albemarle County Service Authority TO: JT Newberry FROM: Alexander J. Morrison, P.E., Civil Engineer DATE: January 5, 2017 RE: Site Plan Technical Review for: SDP201600070: SpringhiII/Town place Suites - Initial The below checked items apply to this site. X 1. This site plan is within the Authority's jurisdictional area for: X A. Water and sewer B. Water only C. Water only to existing structure D. Limited service X 2. An 8 inch water line is located approximately 20' distant. 3. Fire flow from, nearest public hydrant, located distant from this site plan, is Gpm + at 20 psi residual. X 4. An 8 inch sewer line is located approximately on site distant. 5. An Industrial Waste Ordinance survey form must be completed. X 6. No improvements or obstructions shall be placed within existing or future easements. 7. and plans are currently under review. 8. and plans have been received and approved. 9. No plans are required. X 10. Final water and sewer plans are required for our review and approval prior to granting final site plan approval. 11. Final site plan may/may not be signed. X 12. RWSA approval for water and/or sewer connections. 13. City of Charlottesville approval for sewer. X Comments: Water and sewer construction plan review by the ACSA is required at the final site plan stage. RWSA review and approval of sewer connection is required. Conflicts are shown over the existing ACSA sewer on site. Offsite easements may be required. 168 Spotnap Road • Charlottesville • VA 22911 • Tel (434) 977-4511 • Fax (434) 979-0698 www.serviceauthority.org Charles A. Kilpatrick, P.E. Commissioner COMMONWEALTH of VIRGINIA DEPARTMENT OF TRANSPORTATION 1601 Orange Road Culpeper Virginia 22701 January 3, 2017 County of Albemarle Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Attn: J.T. Newberry Re: Springhill/Towneplace Suites — Initial Site Plan SDP-2016-00070 Review #1 Dear Mr. Newberry: The Department of Transportation, Charlottesville Residency Transportation and Land Use Section, has reviewed the above referenced plan as submitted by Dominion Engineering, dated 13 May 2016, and offers the following comments: I . Show and Iabel existing ROW for each road that appears on the plans. 2. CG12's at the proposed entrance should be in line with the existing/proposed sidewalks, parallel to Route 29 and perpendicular to the entrance. 3. Please explain the jagged nature of the proposed sidewalk north of the entrance. 4. As per discussion with VDOT personnel during the 5/2/2016 County pre -application meeting, an access management exception for entrance spacing is required. 5. The proposed emergency access entrance, as proposed, could create problems whereas it could be perceived as a standard entrance. Drivers would pull in and be blocked by the bollards and otherwise unable to safely get back on to Route 29. We recommend providing mountable curb with "grasscrete" or other mountable grass surface to extend to at least the edge of ROW. 6. Provide drainage area maps (pre and post) and drainage calculations. 7. Complete drainage information will be required on the final site plan. More detail on Route 29 runoff and how it will be managed will be required. 8. Note that final site plan must show conformance with the VDOT Road Design Manual Appendices B(1) and F, as well as any other applicable standards, regulations or other requirements. Please provide two copies of the revised plan along with a comment response letter. If further information is desired, please contact Justin Deel at 434-422-9894. VirginiaDOT.org WE KEEP VIRGINIA MOVING January 3, 2017 J.T. Newberry Page 2 A VDOT Land Use Permit will be required prior to any work within the right-of-way. The owner/developer must contact the Charlottesville Residency Transportation and Land Use Section at (434) 422-9399 for information pertaining to this process. Sincerely, od4414- q . I't dllliCJ Adam J. Moore, P.E. Area Land Use Engineer Charlottesville Residency VirginiaDOT.org WE KEEP VIRGINIA MOVING