HomeMy WebLinkAboutZMA199500005 Action Letter
-~
--. .2MÆ- QS - 05 --
.
COUNTY OF ALBEMARLE
DepL of Planning & Community Development
401 Mcintire Road
Charlottesville, Virginia 22902-4596
(804) 296-5823
June 23, 1995
Wendell Wood
W oodbriar Associates,
P. O. Box 5548
Charlottesville, VA 22905
RE: ZMA-95-05 Woodbriar Associates
Tax Map 320, Parcell, and Tax Map 320 Section 3 Parcels A and 83
,
Dear Mr. Wood:
The Albemarle County Board of Supervisors, at its meeting on June 14, 1995, approved as
recommended by the Planning Commission (amended agreements are outlined below) , the
above-noted requ~st for relief of Pr~.ffer 12 of ZMA -91-13, W oodbriar Associates, in order to
allow relief of phasing requirement and clarification of phase completion, zoned PRD.
Agreement #12:
No more than two phases with signed site plans or subdivision plats
shall be under simultaneous development. This phasing limitation shall
not be interpreted as limiting the construction of infrastructure (ro~ds
utilities, drainage, etc.). The development shall proceed in the
following order: Phase 3A, 3B, 3C, the completion of Phase 7, lA, 6, 5
and 4. Phase IB may be developed following completion of Phase lA. Phase
8 shall not be subject to the phasing order. A phase shall be considered '.
complete for purposes of satisfying phasing requirements when the following is
complete:
1. All public roads shown in the phase have been given final inspection by the Virginia
Department of Transportation (VDOT) Charlottesville Residency. A complete
assembly package has been submitted to the residency. The maintenance fee has been
paid and the one-year VDOT performance bond has been posted;
.
r;
.
~-
.
r-.
Page 2
June 23, 1995
2.. All private roads shown in the phase have been completed to the satisfaction of the
County Engineer and all road bonds have been released;
3. All necessary water and sewer lines shall have been installed and dedicated with the
exception of individual connections.
,
Agreement #8:
Staff approval of recreational facilities to include: one tot lot with Phase 3C and one tot
lot with Phase IB; the dedication of open space with the approval of Phases 4 and 5 for
the passive recreational area which shall include construction of walking/jogging trails;
and, the primary recreation area south of Camelot shall be built or bonded for its
construction prior to final plat approval of Phase 4. This recreational area shall be built
prior to completion of Phase 4 and shall consist of a basebalVrnulti-purpose field, two
basketball courts, playgroup equipment and picnic facilities. All recreation facilities shall
be installed by the developer.
If you should have any questions or comments regarding the above-noted action, please do not
hesitate to contact me.
, .
VWC/jcw
cc: Amelia McCulley
Jo Higgins
Lee Catlin