HomeMy WebLinkAboutSDP201700042 Review Comments Final Site Plan and Comps. 2017-08-29COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, North Wing
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Memorandum
To: Michael F. Myers, PE (mmerss(&dominioneng com)
From: Tim Padalino, AICP
Division: Planning
Date: August 28, 2017
Subject: Review Comment Letter UPDATES
SDP201700042 — Springhill / Towneplace Suites (Final Site Plan dated July 12, 2017)
The major site plan amendment referred to above (dated July 12, 2017) has been reviewed by the Department
of Community Development and other applicable agencies. Additional review of the final site plan has
resulted in new comments; please see UPDATE comments below, in bold font.
The Planning Division will approve the above -referenced final site plan after the outstanding issues
identified in this letter have been addressed and resolved to the satisfaction of the applicable reviewer.
Additional comments or conditions may be added or eliminated based on further review.
Please work directly with each reviewer to address and resolve their comments. Approvals from each
reviewer or outside agency should be forwarded to the lead planner upon receipt.
Please contact me at your earliest convenience if you have questions or requests for assistance, or if require
any clarification or additional information.
Sincerely,
1� put.�
Tim Padalino, AICP
Senior Planner
(434)-296-5832 x 3088
ttpadalino&albemarle.org
Page 1 of 3
Albemarle County Planning Services (Planner) — Tim Padalino, tpadalino(c�r�,albemarle.org — Requested changes:
1. Please continue to coordinate directly with ARB staff to obtain the required Certificate of Appropriateness.
Please see the attached review comments from Ms. Margaret Maliszewski, Chief of Planning/Resource
Management, dated August 11.
2. Please continue to coordinate directly with Engineering Services to address and resolve all issues identified in
the most recent review comments. Please see the attached review comments from Mr. David James, Civil
Engineer I, dated August 23.
3. Please continue to coordinate directly with Building Inspections to address and resolve the issue of accessible
parking spaces. Please see the attached review comment from Mr. Michael Dellinger, Albemarle County
Building Official, dated July 25.
The issue appears to be whether a minimum of six (6) ADA accessible spaces are required [as indicated by the
Parking Requirements notes on Sheet SP2 which state that "6 total accessible spaces" are required "with 1 being
van accessible," citing "ADA Standard for Accessible Design Section 4.1.2 (5)(A)"]; or if a minimum of seven
(7) ADA accessible spaces are required [as indicated by Building Inspections, citing Mr. Jay Schlothauer's
review comments (dated December 9, 2016) pertaining to the initial site plan for this project (SDP201600070)].
4. Please continue to coordinate directly with ACSA. Please see the attached review comments from Mr.
Alexander Morrison, PE, dated August 14, which request three (3) copies of the construction plans, along with
water and sewer data sheets, for ACSA review. This review comment was previously forwarded to you on
August 15.
5. Please continue to coordinate directly with VDOT to address and resolve all issues identified in the most recent
review comments. Please see the attached review comments from Mr. Adam Moore, PE, dated August 10.
6. UPDATE: Please remove the "Proposed Subdivision Line" and corresponding annotation from the final site
plan. Although that information is intended to be helpful, the final site plan is not the appropriate document on
which to include such information. The regulatory review of proposed division(s) of property(s) must occur via
submission and review of a subdivision plat, and should be kept separate from site plan submission and review.
To separately pursue the proposed division of the "Future Development Parcel," a plat of division must be
prepared and submitted pursuant to Subdivision Ordinance Section 14-207 ("two -lot subdivisions"), inclusive
of the required $581.00 application fee per Subdivision Ordinance Section 14-203(B)-1(a).
7. UPDATE: [Section 14-303(E)]: Please remove easements which are not required for this final site plan (such
as the "Proposed Access Easement" for the "Future Development Parcel" or the "Proposed 24' Interparcel
Access Easement"). Easements which are required for this Final Site Plan (such as the "Proposed 20' Drainage
Easement," per Zoning Ordinance Section 17.32.7.4.2) must be identified using bearings and distances and/or
other acceptable dimensions standards. Please revise accordingly.
However, if the "Proposed Access Easement" to the "Future Development Parcel" must remain on the final site
plan for any particular reason: please provide explanation of that reason; add a note to Sheet SP6 to briefly
explain the use or necessity of the proposed access easement; and please revise the width of the proposed access
easement to ensure it is wide enough to provide a lane for ingress as well as a lane for egress between the future
development parcel and Route 29.
8. UPDATE: A corresponding easement plat depicting all required easements must be prepared and submitted
pursuant to Subdivision Ordinance Section 14-208.2 ("Easement plats"), inclusive of the required $215.00
application fee per 14-203.3(D)-3. The required easement plat must be reviewed, approved, and recorded prior
to County approval of the final site plan.
9. UPDATE: Note #3 on Sheet SP6 indicates that the "Existing Flaming Wok to remain open until such time that
grading is performed on future development parcel that will result in the loss of utility service or safe customer
access. " This note leaves open the possibility that both the existing restaurant and future hotel could be in
operation concurrently. If the applicant wishes to preserve the possibility for those two uses to occur on the
same property at the same time, then it must be demonstrated on the final site plan that the subject property
contains all necessary improvements as required by County Code to support the concurrent use of TMP #61Z-
03-2 for hotel and restaurant operations.
Therefore, if the existing restaurant use is to be continued or if the existing restaurant structure is to remain in
Page 2 of 3
place at any time after the hotel use has been commenced, please demonstrate compliance with the minimum
parking requirements (aggregated for all uses on the subject property), as specified in Zoning Ordinance Section
4.12.6. If the existing restaurant use is to be discontinued or if the existing restaurant structure is to be
demolished prior to the hotel use being commenced, please remove or otherwise modify Note #3 on Sheet SP6.
Albemarle County Architectural Review Board (ARB) — Margaret Maliszewski, mmaliszewskikalbemarle.org —
Requested Changes (see attached).
Albemarle County Engineering Services (Engineer) —David James, diameskalbemarle.org — Requested Changes
(see attached).
Albemarle County Building Inspections — Michael Dellinger, mdellingerkalbemarle.org — Denied (see attached).
Albemarle County Department of Fire Rescue — Shawn Maddox, smaddox(&albemarle.org — No Objection (see
attached).
Albemarle County Information Services (E911) — Elise Kiewra, ekiewra@albemarle.org— No Objection (see
attached).
Albemarle County Service Authority (ACSA) — Alex Morrison, PE, aorrison(&serviceauthority.org_— Requested
Changes (see attached).
Virginia Department of Transportation — Adam Moore, PE, Adam.Moorekvdot.vir ig nia.gov — Requested
Changes (see attached).
Rivanna Water and Sewer Authority (RWSA) — Victoria Fort, PE, vfortnxivanna.org — Pending:
To date, no review comments have been received from RWSA. All review comments from RWSA will be
forwarded to the Primary Contact upon receipt. Note: The Initial Site Plan review comments indicate that the
primary issue involving RWSA is the requirement for RWSA to review and approve the proposed sewer
connection(s).
Page 3 of 3