HomeMy WebLinkAboutSP200300091 Action Letter Special Use Permit 2004-05-20COUNTY OF ALBEMARLE
Department of Community Development
Planning
401 McIntire Road, Room 218
Charlottesville, Virginia 22902-4596
(434) 296 - 5823
Fax (434) 972 - 4012
May 20, 2004
Lori Garrett
Glave & Holmes Associates
801 E. Main Street, Suite 300
Richmond, VA 23219
RE: SP-03-91 Kappa Sigma International Memorial Headquarters; Tax Map 91, Parcel 16
Dear Ms. Garrett:
The Albemarle County Board of Supervisors, at its meeting on May 12, 2004, by a vote of 6:0, approved
the above -noted request to allow the fraternal headquarters for Kappa Sigma International in accord with
Sections 13.2.2.2 & 5.1.02 of the Zoning Ordinance. Please note that this approval is subject to the
following conditions:
1. The site shall be developed in general accord with the plans, entitled Kappa Sigma Fraternity
Headquarters, dated April 2, 2004;
2. Lighting of the site shall be limited as follows:
a. Light levels at the property line shall be no greater than 0.001 foot candles;
b. No flood lighting of the building is permitted;
C. Only the parking lot north of the building shall be allowed pole lights;
d. Utilize bollard type lights in place of pole lights whenever possible. Use only full cutoff
fixtures; and
e. Site and building illumination shall be limited to the satisfaction of the ARB.
3. Final site plans shall show a reservation, or provide a note, for future vehicular and pedestrian
connections to adjacent parcels to the north and south;
4. Final site plans shall show a pedestrian connection from the future pedestrian/bike pathway on
Route 20 into the site;
5. A right turn and taper shall be constructed at the entrance in Route 20 to the satisfaction of
VDOT;
6. Landscaping shall be provided to limit the impact of the storm water area on the Entrance Corridor
to the satisfaction of the ARB; and
7. The Applicant shall construct public water service to the site via extension of the existing
Albemarle County Service Authority water line located on the west side of Route 20 and public
sewer service via extension of the existing Albemarle County Service Authority sewer line located
along Route 20 and the Cow Branch Creek, generally as provided in the report entitled,
Preliminary Engineering Report Water and Sewer Facilities for kappa Sigma Headquarters by
Draper Aden Associates, dated March 30, 2004.
In the event that the use, structure or activity for which this special use permit is issued shall not be
commenced within twenty-four (24) months after the issuance of such permit, the same shall be deemed
abandoned and the authority granted thereunder shall thereupon terminate. For purposes of this section,
the term "commenced" shall be construed to include the commencement of construction of any structure
necessary to the use of such permit within two (2) years from the date of the issuance.
Page 2
May 20, 2004
Before beginning this use, you must obtain a zoning clearance from the Zoning Department. Before the
Zoning Department will issue a clearance, you must comply with the conditions in this letter. For further
information, please call Jan Sprinkle at 296-5832.
If you should have any questions or comments regarding the above -noted action, please do not hesitate to
contact me.
Sincerely,
9";44t"A
David B. Benish
Chief of Planning
DBB/jcf
Cc: Amelia McCulley Jack Kelsey