HomeMy WebLinkAboutWPO201500098 Review Comments WPO VSMP 2016-12-01Short Review Comments Report for:
WPO201500098
SubApplication Type:
Wintergreen Farm - VSMP
Stormwater Management/BMP Plan
Erosion and Sediment Control Plan
Date Completed:01/07/2016
Reviewer:Justin Deel CDD Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:02/18/2016
Reviewer:John Anderson CDD Engineering
Review Status:Requested Changes
Reviews Comments:Dropbox .PDF e-review; e-comments [JA email 2/18/2016 3:14 AM] -Available in RMS documents
Division:
Date Completed:03/10/2016
Reviewer:John Anderson CDD Engineering
Review Status:Requested Changes
Reviews Comments:
SWPPP
1. General VPDES Permit Registration Statement Estimated Area to be disturbed, 51.55 Ac.,
does not match plan, 47.4 Ac. (.PDF Attached to FGM email: 2/18/2016 9:07 AM). Please reconcile.
2. Nature of Activity project description Area of Disturbance does not match Registration
Statement. Please reconcile.
3. Provide concrete washout draining to trapping device for site entrances on Sunset Ave. Ext.
and Ambrose Commons.
4. Sign/date Sec. 9
5. Title Sheet –Delete Retaining Walls note.
6. Revise Title sheet critical slopes Note. There are proposed impacts to critical and preserved
steep slopes.
7. Sheet 10 shows utility impacts to critical slopes on Lots 17, 24-27, and preserved steep
slopes on Lots 27 and 28. Label preserved steep and critical slopes on sheets 3, 4, 8, 10, 12,
especially in areas or on Lots with utility impacts.
8. Remove utility (easement) lines in floodplain/stream buffer, sheet 3, since not pre-existing.
9. Show development area/rural area line on sheets 3 and 4.
10. Turn on Lot # and street name labels, sheet 4.
11. Sheet 2 –slopes labeled existing managed steep west of floodplain are existing critical
slopes; revise label.
12. Important: Include Notes that specifically direct ACSA/ACSA utility contractor to limit clearing,
excavation, trenching to minimum necessary to install 8” sanitary transmission line across critical or
steep slopes. Provide notes that assure impacts will be limited as much as possible.
13. If 8.71 Ac. of forest/protected open space are protected from future development via the plat,
please be advised Deeded easement must be reviewed and approved by the County Assistant
Attorney’s office [ref. February 18, 2016 3:15 AM email to Collins Engineering].
Also: ref. email to Applicant/
February 18, 2016 3:15 AM
Thu 3/10/2016 5:18 PM
janderson2 3/10/2016 5:19 PM
Division:
Date Completed:06/21/2016
John Anderson
Page:1 of 2 County of Albemarle Printed On:September 21, 2017
Reviewer:John Anderson CDD Engineering
Review Status:See Recommendations
Reviews Comments:Collins Engineering' bond estimate sent to A. Kilmer without modification [6/21/2016 5:57 AM].
Collins Engineering deserved immediate response since CE estimate sent to reviewer as e-mail
Attachment, 5/23/2016 10:03 AM.
Though out of office 27-May thru 13 Jun, CE support deserved equivalent care and attention.
I regret delinquent response.
janderson2 6/21/2016 6:02 AM
Division:
Date Completed:03/12/2016
Reviewer:John Anderson CDD Engineering
Review Status:Requested Changes
Reviews Comments:E-PLAN: FGM Email, March 11, 2016 3:18 PM
A.Long Email, March 11, 2016 2:41 PM (resent, 3/14/2016 10:38 AM)
E-REVIEW: JA Email, March 12, 2016 12:05 PM
[Also, please see, JA Email, 3/15/2016 8:10 AM]
Division:
Date Completed:03/29/2016
Reviewer:John Anderson CDD Engineering
Review Status:See Recommendations
Reviews Comments:Remaining:
-Retaining Wall design -required for WPO Approval since integral to SWM facility design.
-Deed/covenant restrictions (8.71 Ac.) -Applicant acknowledges deed will be provided with Final Plat.
-Landscaping vegetation hardier than grass is required for slopes steeper than 3:1 (Ref. sheet 6,
ROAD Plan). Transfer Note requiring Juniper plantings to WPO sheets 8, 10, 12.
Division:
Date Completed:04/07/2016
Reviewer:John Anderson CDD Engineering
Review Status:See Recommendations
Reviews Comments:As follow-up: provide print/legible copy (or .PDF file) of retaining wall design. Certain information on
Wintergreen Farm Retaining Wall Plans prepared by Dominion Engineering Associates, H. M. Moore,
PE, dated 3.28.16 is unreadable.
-Deed/covenant restrictions (8.71 Ac.) -Applicant acknowledges deed will be provided with Final Plat.
Division:
Date Completed:06/22/2016
Reviewer:John Anderson CDD Engineering
Review Status:Approved
Reviews Comments:Engineering review comments addressed with this or prior submittal.
Wintergreen Farm Retaining Wall Plans (Dominion Engineering Associates, H. M. Moore, PE, dated
3.28.16) are legible.
-Deed/covenant restrictions (8.71 Ac.) -Applicant acknowledges deed will be provided with Final Plat.
Division:
Date Completed:12/01/2016
Reviewer:Ana Kilmer
Review Status:Approved
Reviews Comments:11/18/2016 -3 swas submitted
12/1/2016- SM Charlottesville, LLC recorded in Deed Book 4846, page 182; Wintergreen Farm
Phase II, LLC recorded in Deed Book 4846, page 186; Wiintergreen Farm Phase III, LLC recorded in
Deed Book 4846, page 190.
Division:
Page:2 of 2 County of Albemarle Printed On:September 21, 2017
COLLINS - WO GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902
�/ 434.293.3719 PH 434.293.2813 FX
www.collins-engineering.corn
March 30,2016
John Anderson, P.E.
Department of Community Development
401 McIntire Road
Charlottesville,VA 22902
RE: Wintergreen Farm VSMP Plan(WPO 201500098)
Thank you for your'conditional approval' letter dated March 29,2016 on the above-referenced project. The
plans were tweaked to address your conditional items described below:
A. Stormwater Pollution Prevention Plan
1. Erosion and sediment control plan sheets 8 and 10-13 were updated to include the note in the vicinity of the
SWM facilities that reads, "proposed juniper plantings required for slopes greater than 3:1." Please note,
County Engineering provided follow-up comments on March 29,2016.To address this follow-up
correspondence a note was added to the cover sheet reading, "1,600LF of 10'wide paved path will be shown
on(future)amended road plans for Wintergreen Farm Subdivision."Another note was added to sheets 1 and
5 stating, "no canopy or understory trees shall be planted within ten(10)feet of the back of the top of the
retaining wall."As a result,sheets 1 and 5 have also been updated in the SWPPP.
B. Stormwater Management Plan
1. A professionally sealed retaining wall design has been submitted with the plans. Please note,sheet 5 was
updated per the response above to the follow-up SWPPP comment requesting the tree separation from
the wall at SWM facility A.
C. Erosion Control Plan
1. Sheets 8 and 10-13 were revised in the vicinity of the SWM facilities to read, "proposed juniper plantings
required for slopes greater than 3:1."Also note, per the response to the SWPPP comment Al,sheets 1 and 5
were also updated to include the two notes described above.
Should you have any questions, please feel free to contact me at(434) 566-3011.
Sincerely,
Graham Murray, PE
Noe sod
Todd Shifflett
From: John Anderson
Sent: Wednesday, June 22, 2016 8:20 AM
To: Scott Collins; Adam Long;Alan Taylor
Cc: Todd Shifflett; Frank Pohl; Ana Kilmer
Subject: Planning Application Review for WPO201500098 Wintergreen Farm -VSMP.
The Review for the following application has been completed:
Application Number=WPO201500098
Reviewer=John Anderson
Review Status =Approved
Completed Date =06/22/2016
Thanks for your patience.
CV Engineering review comments:
"Engineering review comments addressed with this or prior submittal.
Wintergreen Farm Retaining Wall Plans (Dominion Engineering Associates, H. M. Moore, PE, dated 3.28.16)
are legible.
-Deed/covenant restrictions (8.71 Ac.) -Applicant acknowledges deed will be provided with Final Plat."
New tel. #: 434.872-4501 —x3069
1
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Project:
Project File Number:
Plan preparer:
Owner or rep.
Owner:
Plan received date:
(Rev. 1)
(Rev. 2)
(Rev. 3)
(Rev. 4)
Date of comments:
(Rev. 1)
(Rev. 2)
(Rev. 3)
(Rev. 4)
Reviewer:
VSMP Permit plan review
Wintergreen Farm VSMP Plan WP0201500098
WP0201500098
Scott Collins; Collins Engineering [200 Garrett St., Suite K, Charlottesville, VA
22902, scott@collins-en ing eering com, adam@collins-en ing eering com ]
Alan Taylor, Riverbend Development [455 2nd Street, Charlottesville, VA 22902 —
alanAriverbenddev. com]
Wintergreen Farm Land Trust, 600 Peter Jefferson Parkway #130
Charlottesville, VA 22911
24 Nov 2015
17 Feb 2016 (Dropbox; .PDF e plan)
18 Feb 2016 (.PDF e plan)
11 Mar 2016 (.PDF e plan)
15 Mar 2016
7 Jan 2016
18 Feb 2016 (e -review)
10 Mar 2016 (e -review)
12 Mar 2016 (e -review)
29 Mar 2016 —Conditional Approval
Justin Deal (initial); John Anderson (revisions)
Caution: Planning Division comments (30 -Dec) have potential to affect design —this may have a ripple effect.
Please avoid reference to Engineering (WPO plan) review status in discussion with Planning, or VDOT.
VDOT /Planning ROAD Plan comments must be addressed —nothing diminishes their comments.
If layout changes in response to PlanningNDOT affect SWM design, WPO may need to be re -reviewed.
Prior comments available in CV document system (removed for simplicity). Prior comments not listed have
been addressed (Sec. A, B, C, D).
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1)
a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Update ESC Plan sheets 8, 10, 12: Show landscaping vegetation hardier than grass; ref. ROAD Plan sheet 6
—show/label juniper plantings required for slopes steeper than 3:1, SWM Area `A'. Also: ESC Plan, Sec. C.
2. Revise/update. Submit (2) print copies; one will be distributed to contractor at pre -construction.
B. VSMP: SWPPP: Stormwater Management Plan (WP0201500098)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is
conditionally approved.
1. Retaining Wall /SWM Area "A": Since this wall is integral to SWM facility design, we require PE -sealed
geotechnical RW design prior to WPO Approval [J. Anderson email: Mar -11, 2016, 12:40 PM]. Applicant
response [FGM E-mail, March 11, 2016 3:18 PM]: "A structural retaining wall design ... will have to
follow." Acknowledged.
2. If 8.71 Ac. of forest/protected open space are protected from future development via the plat, please be
Engineering Review Comments
Page 2 of 2
advised Deeded easement must be reviewed and approved by the County Assistant Attorney's office [ref.
February 18, 2016 3:15 AM email to Collins Engineering]. —Addressed. Discussed 11 -Mar (JA/FGM).
Deed will be provided with Final Plat.
C. VSMP: SWPPP: Erosion Control Plan (WP0201500098)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is approved
pending single revision. The erosion control plan content requirements can be found in County Code section 17-402.
1. Sheets 8, 10, 12: Show landscaping vegetation hardier than grass. Ref. ROAD Plan sheet 6 —show/label
juniper plantings required for slopes steeper than 3:1, SWM Area W. Also: Update SWPPP.
D. Mitigation Plan (WP0201500098)
The mitigation plan content requirements can be found in County Code section 17-406. Addressed.
Engineering review staff are available 2-4 PM on Thursdays, should wish to discuss project, comments, or design. Plan review
staff is available at 434.296-5832 -x3069, should you have questions.
Process:
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request
form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and
check parcel and easement information based on the approved plans. The County's Management Analyst will
prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash,
certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County
Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The
County's Management Analyst or other staff will prepare the forms and check for ownership and signature
information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ database
for state application processing. DEQ will review the application information based on local VSMP authority
approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest
processing, this is done electronically with the emails provided on the application. DEQ should notify applicants
with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter.
This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants
will need to request a pre -construction conference by completing a form, and pay the remainder of the application
fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be
checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County
inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
httt)://www.albemarle.org/dei)tforms.asi)?deDartment--cdenawt)o
Thank you
434.296-5832 —x3069
WP0201500098 Wintergreen Farm 032916rev4_Approv_conditional
John Anderson
From:
Sent:
To:
Subject:
John Anderson
Tuesday, March 15, 2016 8:10 AM
'Graham Murray'; 'Adam Long'
RE: Planning Application Review for WPO201500098 Wintergreen Farm - VSMP.
Graham,
slight edit —basin `A', MWSE —thanks
Adam, Graham,
Thanks for coordinated revisions, for emails and .PDFs.
At this point, please make last corrections and rather than send .PDFs, work with one another.
Ensure plans are accurate.
Please submit one (1) VSMP print copy for final review. I will respond within 5 business days.
I feel certain we'll be there —unable to review .PDF Attachments for this project beyond this.
Thanks, again
434.296-5832 —0069
MMIRETEWMNWUPOR
{WALE 1 —5n -�1-
Mam
fironowil
SHOA
715
ASM GRl4LM00 WALL HCPrr iIq.!� � F
P, rffCVDMD
- sirnx+x y _i
PER -Affi HT -
Op
,mss
IDOM
raieruY srt o ` L� _
PCOLem
From: Graham Murray [mailto:graham@collins-engineering.com]
Sent: Monday, March 14, 2016 10:00 AM
To: John Anderson <janderson2@albemarle.org>
1
S
W Wn5E EA
CAN&D &tHFJ
ALCM NCUO WMWM
LONUffLOP"L SLOPE a r
CNC5s!WE
J
#} CL111004AMLk7
f
i
Cc: Adam Long <adam@collins-engineering.com>; Scott Collins <scott@collins-engineering.com>
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Good morning John,
Thanks for your e-mail. I believe Adam has already sent you the other sheets addressing your comments, however if I am mistaken
we can provide you with these. The mitigation sheet was not included in Adam's Friday e-mail, but this will be forthcoming.
Also, in efforts to address your comments from Saturday I have attached two revised PDF sheets. One is an updated cover sheet
adding back the retaining wall note and a bold boxed note stating the requested utility contractor information. The other PDF sheet
is sheet 5. This sheet revised basin A's MWSE and now labels the floor elevations on the profiles.
If you need anything else (besides a retaining wall design & the mitigation sheet) for a WPO approval please let us know. Adam will
be happy to resend the other PDF sheets and the SWPPP.
Thanks,
Graham
From: John Anderson [mailto:janderson2@albemarle.org]
Sent: Saturday, March 12, 2016 12:05 PM
To: Graham Murray
Cc: Adam Long; Scott Collins; aIan@riverbenddev.com
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Graham,
Are you planning to send Title sheet, additional sheets, and SWPPP?
Since there is a retaining wall, title sheet RW note is appropriate.
I would rather not issue review comments until all items addressed — ref red text, below + sheet 16/Mitigation Plan
Also:
Please label SWM floor Elev. (Facilities A, B, D) as w/ past projects —aids review/construction—forebay /basins.
(IMAGE, below). Please revise MWSE SWM Area "A"
I think that w/ red text revisions below (SWPPP /other sheets), Floor Elev. labels, and Retaining Wall design, we'll be
there.
Caution/WARNING: Planning Division comments (30 -Dec) have potential to affect design —this may have a ripple effect.
Please avoid reference to Engineering (WPO plan) review status in discussion with Planning, or VDOT.
VDOT /Planning ROAD Plan comments must be addressed —nothing diminishes their comments.
If layout changes in response to Planning/VDOT affect SWM design, WPO must be re -reviewed.
Thanks, Graham
From: Graham Murray [mailto:graham@collins-engineering.com]
Sent: Friday, March 11, 2016 3:18 PM
To: John Anderson <janderson2@albemarle.org>
Cc: Adam Long <adam@collins-engineering.com>
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Good afternoon John,
Adam and I revised the Wintergreen plans and he sent you PDFs earlier this afternoon. These PDFs addressed your initial comments
(hopefully). However after sending you these PDFs I noticed your follow up e-mail.
As a result, I updated the attached sheet 4 (though the older one has more highlighted info. in red to assist you). I have also
included a revised sheet 5 showing you the TW, BW and wall length. A structural retaining wall design is not something I can
complete unfortunately and this will have to follow.
3
CAADE 465
r75CAI�1,
460 ra iaP 460
5W WFtW POOPMED &M-0 WFC
1NUKENCF 5PUWAY €MT ELFY.-4U- g,
MNTR URR SHf1.L STALL _
- riY ! iGC
giLLYMY ASE MOPES SKOJI K4:5 OR
FLATFIATOPKVM+R5MOPEHYErPCOW
veucWmow ALONG IWAC= bOM r TO
t/ VE IDL%pq
4 5 ,av�trEwPaAa�wFr3 THESE K.MS. 4
PF9TJ1T7TK KA.1 LRfD}WUW,%Y
160 460
FCW&AV &NLLWAVCR 5? _
�ifY.µgd+ S7o'Q+A,
F-Oir POMAA kT
M ELE POOL
TOF9FWl1AELEM,-}+,Y F'Ei4kiMifNFJFx74LdEP'FFF4?
----
'
4 — — — — — — T — — L � 450
455 } 455
OEEP FORM:: Y
G
445 cam 1 445
any
450 450
Pp4Fk}SED�6'iii(eElpiTAhlf]F�fxyff�fShRAICIC O'J1b!'bsEb�ao'�A•L•L■
A�1:1 SE7M'E AS Tl� A15Ea STfWE 1� RM RCP WAPoiL r4T P,4� Pt+Y
Ya5
ELEV.�S��aVAH�M LOMfPLCIkURIRCEMIYERTkl �ry,y��y,�p�,y��
� '
fLEY_� T4 PAEYEHCFLQTk71067 iFE ¢CSFB Ei4yEAii7 PROPOSED YW F n 4LUltl1i JYOa141S
MRFIEiL{OWNECTI4H SNALL U FM4NO ED dP
.. .
Wf*Ak lirri-nC1� e's+ri rre F L1NbxYmW,1 fw,Y IS Ou7kFT FR jCTpM *i LLE 1'Rg�,�I�
I� �5
YELCAi'GAOLIFI4. FAR0�6.M UMERUMEW i'RbFSM Sr y
y 64451
C
,3
p1tl6"AFiD$41R1FG
49
p
T3 W
d3
4 Mr L
14
W) T
MY 14
Gi'!0 1+00 1+50 2+00 2+}50 3+00 3+25
D+W 0.70
BASIN A- SECTION AND OUTFALL I
I BASIN - SPILLWA
I think that w/ red text revisions below (SWPPP /other sheets), Floor Elev. labels, and Retaining Wall design, we'll be
there.
Caution/WARNING: Planning Division comments (30 -Dec) have potential to affect design —this may have a ripple effect.
Please avoid reference to Engineering (WPO plan) review status in discussion with Planning, or VDOT.
VDOT /Planning ROAD Plan comments must be addressed —nothing diminishes their comments.
If layout changes in response to Planning/VDOT affect SWM design, WPO must be re -reviewed.
Thanks, Graham
From: Graham Murray [mailto:graham@collins-engineering.com]
Sent: Friday, March 11, 2016 3:18 PM
To: John Anderson <janderson2@albemarle.org>
Cc: Adam Long <adam@collins-engineering.com>
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Good afternoon John,
Adam and I revised the Wintergreen plans and he sent you PDFs earlier this afternoon. These PDFs addressed your initial comments
(hopefully). However after sending you these PDFs I noticed your follow up e-mail.
As a result, I updated the attached sheet 4 (though the older one has more highlighted info. in red to assist you). I have also
included a revised sheet 5 showing you the TW, BW and wall length. A structural retaining wall design is not something I can
complete unfortunately and this will have to follow.
3
Thanks John for working with us towards an approval. As always, if there is anything I can do to assist you with your approval, please
let me know.
Thanks,
Graham
From: John Anderson[ma iIto: janderson20)albemarle.org]
Sent: Friday, March 11, 2016 12:40 PM
To: Graham Murray
Cc: Scott Collins; Adam Long
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Graham,
Thanks for your phone message.
We spoke a few minutes ago. Thanks for accepting request for landscape planting details/plant schedule (species/count)
to guide Mitigation Plan bond, installation, inspection —Sheet 16.
Also: I left voicemail re. Retaining Wall /SWM Area "A" (RW). Since this wall is integral to SWM facility design, we
require PE -sealed geotechnical RW design prior to WPO approval.
RW will be bonded with WPO since BMP cannot be built without it.
WP0201500098 sheet 4: Please add label: RETAINfNG WALL.
Sheet 5: Please provide additional TW/BW Elevations /overall RW Length.
I failed to mention requests relating to wall when we spoke, and apologize.
Thanks for your patient efforts, Graham.
434.296-5832 —x3069
From: John Anderson
Sent: Thursday, March 10, 2016 5:24 PM
To: Adam Long <adam@collins-engineering.com>; 'Graham Murray' <graham@collins-engineering.com>
Cc: Scott Collins <scott@collins-engineering.com>
Subject: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
The Review for the following application has been completed:
Application Number = WP0201500098
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 03/10/2016
Thanks for your patience.
CV comments:
"SWPPP - ? /please submit
1. General VPDES Permit Registration Statement Estimated Area to be disturbed, 51.55 Ac., does not match plan,
47.4 Ac. (.PDF Attached to FGM email: 2/18/2016 9:07 AM). Please reconcile.
2. Nature of Activity project description Area of Disturbance does not match Registration Statement. Please
reconcile.
3. Provide concrete washout draining to trapping device for site entrances on Sunset Ave. Ext. and Ambrose
Commons.
4. Sign/date Sec. 9
5. Title Sheet —Delete Retaining Walls note. Addressed; please disregard comment.
6. Revise Title sheet critical slopes Note. There are proposed impacts to critical and preserved steep slopes. -?
/please submit
7. Sheet 10 shows utility impacts to critical slopes on Lots 17, 24-27, and preserved steep slopes on Lots 27 and
28. Label preserved steep and critical slopes on sheets 3, 4, 8, 10, 12, especially in areas or on Lots with utility
impacts. Sheets 4, 5 received 11 -Mar /submit remaining sheets.
8. Remove utility (easement) lines in floodplain/stream buffer, sheet 3, since not pre-existing. —
Addressed. Discussed 11 -Mar; comment withdrawn.
9. Show development area/rural area line on sheets 3 and 4. Addressed.
10. Turn on Lot # and street name labels, sheet 4. Addressed.
11. Sheet 2 —slopes labeled existing managed steep west of floodplain are existing critical slopes; revise label. -?
/please submit
12. Important: Include Notes that specifically direct ACSA/ACSA utility contractor to limit clearing, excavation,
trenching to minimum necessary to install 8" sanitary transmission line across critical or steep slopes. Provide notes that
assure impacts will be limited as much as possible. -? /please submit Not addressed —please direct reviewer to Note.
13. If 8.71 Ac. of forest/protected open space are protected from future development via the plat, please be advised
Deeded easement must be reviewed and approved by the County Assistant Attorney's office [ref. February 18, 2016 3:15
AM email to Collins Engineering]. —Addressed. Discussed 11 -Mar. Deed will be provided with Final Plat.
Also: ref. email to Applicant/
February 18, 2016 3:15 AM
Thu 3/10/2016 5:18 PM
434.296-5832 —0069
John Anderson
From: John Anderson
Sent: Saturday, March 12, 2016 12:05 PM
To: 'Graham Murray'
Cc: Adam Long; 'Scott Collins'; 'alan@riverbenddev.com'
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Graham,
Are you planning to send Title sheet, additional sheets, and SWPPP?
Since there is a retaining wall, title sheet RW note is appropriate.
I would rather not issue review comments until all items addressed — ref red text, below + sheet 16/Mitigation Plan
Also:
Please label SWM floor Elev. (Facilities A, B, D) as w/ past projects —aids review/construction—forebay /basins.
(IMAGE, below). Please revise MWSE SWM Area "A"
.134f]
4vG
;�-- - —,r
w'Rib€6UPW UNED
FOR AY 3FILLWAVCREST
�v�,.f t v I FMEW
W41 ELE':,-45Y
PFO PMEMV .—
PEEP FOR AY
. • n,E oL53G1 �
THEM oLANS.'
aFiF'PSEE>rT4�nE. ixt'irT►,r1 -
-
PrEAMANEWF POOL bEPThw*} —
i
PROFILE SCALES]
J# MME MWDSED GRASS LW
FJJMEHCY5KLwkY CK5TELEY.M"-yf.
9hLLWAv SM MCM SFn4L K 4:1 OR
FLATTER TO FRVM A MWHOM V>EWOFJ TI
Tm eW)ON ALONG THL ACCi#s m Ub m M
M4TECTTIRGRJS$LK WPUWAY
460 4r2
ti
4;
450 455
. al
450 I-- r� I
445 p 445
YI 4'F M1
ia7 4 7 Ln
-e4Yl
C+W 0+715
BASIN Ak- SPILLWA
I think that w/ red text revisions below (SWPPP /other sheets), Floor Elev. labels, and Retaining Wall design, we'll be
there.
Caution/WARNING: Planning Division comments (30 -Dec) have potential to affect design —this may have a ripple effect.
445
I 445
PFOPOSF.ftV CL. F ACP STAMPIPE kW TRASHE�dF85EC} 9u' Yt CL r
SSE5Fx'EfS—AI$F,RFnKK kK-Rg� -A RCR L/tTp4�fl+�
ELEY.-4S.7.V+WAMOE`LOW FLOW(AFKE KeM AT �ry.�6� 61YOtJr+y;bmq
T1EY. -T4 vFrrrrwTxnoe,lTYTE¢LSEmd4�EI1i}rnpoSEOYLMracum AOGmom
HECTIQN 514wL11 E FlRMtiV Eit9EpGEd
WTLTBJRIIlYOM
YfT#+4fl fB'THKX€pY ETA LM�1�7iaFI fIMTI$TFAQ AQIpLtsro. TPI
44 [7
Er0T Na 40
6Y6,AHDBIIRIFGWEIOMIGA4UMQ FARM LxoETJMXXt_v.0-o-Y, w-
CM
v
0+5D 1T0 I+50 2+00 ;2 .N 310 3+25
BASIN - SECTION AND OUTFALL
450 I-- r� I
445 p 445
YI 4'F M1
ia7 4 7 Ln
-e4Yl
C+W 0+715
BASIN Ak- SPILLWA
I think that w/ red text revisions below (SWPPP /other sheets), Floor Elev. labels, and Retaining Wall design, we'll be
there.
Caution/WARNING: Planning Division comments (30 -Dec) have potential to affect design —this may have a ripple effect.
Please avoid reference to Engineering (WPO plan) review status in discussion with Planning, or VDOT.
VDOT /Planning ROAD Plan comments must be addressed —nothing diminishes their comments.
If layout changes in response to Planning/VDOT affect SWM design, WPO must be re -reviewed.
Thanks, Graham
From: Graham Murray [mailto:graham@collins-engineering.com]
Sent: Friday, March 11, 2016 3:18 PM
To: John Anderson <janderson2@albemarle.org>
Cc: Adam Long <adam@collins-engineering.com>
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Good afternoon John,
Adam and I revised the Wintergreen plans and he sent you PDFs earlier this afternoon. These PDFs addressed your initial comments
(hopefully). However after sending you these PDFs I noticed your follow up e-mail.
As a result, I updated the attached sheet 4 (though the older one has more highlighted info. in red to assist you). I have also
included a revised sheet 5 showing you the TW, BW and wall length. A structural retaining wall design is not something I can
complete unfortunately and this will have to follow.
Thanks John for working with us towards an approval. As always, if there is anything I can do to assist you with your approval, please
let me know.
Thanks,
Graham
From: John Anderson [ma iIto: janderson2@albemarle.org]
Sent: Friday, March 11, 2016 12:40 PM
To: Graham Murray
Cc: Scott Collins; Adam Long
Subject: RE: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
Graham,
Thanks for your phone message.
We spoke a few minutes ago. Thanks for accepting request for landscape planting details/plant schedule (species/count)
to guide Mitigation Plan bond, installation, inspection —Sheet 16.
Also: I left voicemail re. Retaining Wall /SWM Area "A" (RW). Since this wall is integral to SWM facility design, we
require PE -sealed geotechnical RW design prior to WPO approval.
RW will be bonded with WPO since BMP cannot be built without it.
WPO201500098 sheet 4: Please add label: RETAINfNG WALL.
Sheet 5: Please provide additional TW/BW Elevations /overall RW Length.
I failed to mention requests relating to wall when we spoke, and apologize.
Thanks for your patient efforts, Graham.
434.296-5832 —x3069
From: John Anderson
Sent: Thursday, March 10, 2016 5:24 PM
To: Adam Long <adam@collins-engineering.com>; 'Graham Murray' <graham@collins-engineering.com>
Cc: Scott Collins <scott@collins-engineering.com>
Subject: Planning Application Review for WP0201500098 Wintergreen Farm - VSMP.
The Review for the following application has been completed:
Application Number = WP0201500098
Reviewer = John Anderson
Review Status = Requested Changes
Completed Date = 03/10/2016
Thanks for your patience.
CV comments:
"SWPPP - ? /please submit
1. General VPDES Permit Registration Statement Estimated Area to be disturbed, 51.55 Ac., does not match plan,
47.4 Ac. (.PDF Attached to FGM email: 2/18/2016 9:07 AM). Please reconcile.
2. Nature of Activity project description Area of Disturbance does not match Registration Statement. Please
reconcile.
3. Provide concrete washout draining to trapping device for site entrances on Sunset Ave. Ext. and Ambrose
Commons.
4. Sign/date Sec. 9
5. Title Sheet —Delete Retaining Walls note. Addressed; please disrcQard comment.
6. Revise Title sheet critical slopes Note. There are proposed impacts to critical and preserved steep slopes. -?
/please submit
7. Sheet 10 shows utility impacts to critical slopes on Lots 17, 24-27, and preserved steep slopes on Lots 27 and
28. Label preserved steep and critical slopes on sheets 3, 4, 8, 10, 12, especially in areas or on Lots with utility
impacts. Sheets 4, 5 received 11 -Mar /submit remaining sheets.
8. Remove utility (easement) lines in floodplain/stream buffer, sheet 3, since not pre-existing. —
Addressed. Discussed 11 -Mar; comment withdrawn.
9. Show development area/rural area line on sheets 3 and 4. Addressed.
10. Turn on Lot # and street name labels, sheet 4. Addressed.
11. Sheet 2 —slopes labeled existing managed steep west of floodplain are existing critical slopes; revise label. -?
/please submit
12. Important: Include Notes that specifically direct ACSA/ACSA utility contractor to limit clearing, excavation,
trenching to minimum necessary to install 8" sanitary transmission line across critical or steep slopes. Provide notes that
assure impacts will be limited as much as possible. -? /please submit Not addressed —please direct reviewer to Note.
13. If 8.71 Ac. of forest/protected open space are protected from future development via the plat, please be advised
Deeded easement must be reviewed and approved by the County Assistant Attorney's office [ref. February 18, 2016 3:15
AM email to Collins Engineering]. —Addressed. Discussed 11 -Mar. Deed will be provided with Final Plat.
Also: ref. email to Applicant/
February 18, 2016 3:15 AM
Thu 3/10/2016 5:18 PM
434.296-5832 —x3069
John Anderson
From:
John Anderson
Sent:
Thursday, February 18, 2016 3:14 AM
To:
'Adam Long'
Cc:
'Graham Murray'; 'Scott Collins'
Subject:
WP0201500098 -Wintergreen Farm
Attachments:
WP0201500098 Review Comments WPO VSMP 2016 -01 -07 -Wintergreen
Farm_JusDeel.pdf
Adam,
Thanks for Dropbox link
—I've had a chance to review revised WPO.
Please:
• Accept preview comments, below.
• Email rev. SWPPP, VRRM worksheet (.XLS).
• Print one (1) full-size copy of plans —bring to SRC, if possible.
• Anticipate comments on print plans by 22 -Feb. —difficult to review on pc/laptop.
• Remind if do not receive (print plan) WPO plan review comments by 22 -Feb.
• Reference recent ROAD Plan review comment #18 (10 -Feb) relative to steep/critical slopes:
18, Slm - sha& preserved +,ieepycritical slopes on T rnswiie Driue,clwwhew Label �ts�prcri��ca1 slapr�_
(Rev. 1) Farllrally Addrossed. Mse 11 critical slops mi,;6ib6cJ nnroagedcjifowl slopts (temi not fow
toC,A Flew. Also, build slIcs 410"Id Rol contain erttrol $10110
�pccibr2lly LP15 21. 8l, 82 (Also. Cots 73-95. gemora Reif Di %,. comment 410 t M -D} - 21) 15
• ROAD Plan steep/critical slopes comment (#18) remains; applies to VSMP Plan as well.
Thanks for your help and patience.
Ref. Attached 7 -Jan comments:
SWMP
1. Addressed.
2. Please use New Development worksheet (reversal/discussed with Graham).
3. Please email VRRM New Development worksheet (.XLS).
4. Addressed, discussed with Graham.
5. Addressed, discussed with Graham.
6. Partially Addressed. As follow-up: 120' VEPCO Easement will not be cleared/bush-hogged not more than 4 X
year —qualifies as forest/open space. Balance of 8.71 Ac. listed as VRRM forest/open space requires
documentation to ensure area will remain in a natural, vegetated state. Assistant County Attorney Greg Kamptner
has spent considerable time on this issue, can provide guidance. Advise contact County Attorney's Office —TEL.
434.972-4067.
7. Although Limits of Disturbance (Typ.) are shown (image below) please provide labels that identify Area of
disturbance (Ac.).
8. Addressed. [ May include WP0201500098 in plan title -reversal/optional ]
ESCP
1. Need print copy —3rd bullet above.
2. Relocate S132 to avoid stream buffer to extent practical (50' to stream). If SB2 occupies area proposed for SWM
facility, it may remain.
ISec. 17-603.B.]
Sec. 17-603'ryp,es of structures, improvtmeaIs and activities aaIhurized in a stresm buffer.
Cf oiherwlse authnri7ed by the applicable regulations of the Zoning (Mirmnee. the types of
structurc5, control mcasur" and activities AV be allowed in a stream buffer, provided that the
requirements ofthis section are satisfied:
A. Pre-errslrng buildings or•sfr•uclurps-_ Any building or structure which existed an February 11, 1998
may continue in its location on that date. However, nothing in this section authorizes the
continuance, repair, replacement, expansion or enlargement of any such building or structure
except as provided in sections 18-6 and 18-30.3,
B. Temporar), erosion and sedonew control measures. Temporary erasion and sediment corarol
measures, provided that to the extent practical. as determWd by the administrator, the control
mca wcr shall be local -d outside of the strearn buffer and diqurhance impaclsare minimized.
ff i8' BERM F
{r SHALL BE
r / FIRST STEF
ItAITS OF DISTURBANCE {TY17 1
I'.l'
SF TS
E 1.14 T,. QP �
DESIGN INFORMATION PRQPIRSED EC M
�. RfOUlRED FOR S
t " GREATERTNANy
f S8PROPOSED SAFE
I NSTALL SIGNS 0
'
SEE: HE 0UICK SAND, xE
} � �,
FOR DESIGN PS
11111FORFRM 4T OSI
No
- TP
3. Comment withdrawn.
4. Please provide Narrative response to review comment/question —would like to check against print plan set:
4. Please ela6fy what's being proposed at sediment trap S in Phase 111. Is i1 real stic expecI that only
half of the cul-de-sac will be complcted, then removing the trap to finish'
Thanks, Adam
Thanks, Graham
7 -Jan 2016 WPO plan review comments Attached.
434.296-5832 —0069
From: Adam via Dropbox [ma iIto: no-reply@dropbox.com]
Sent: Wednesday, February 17, 2016 3:26 PM
To: John Anderson <janderson2@albemarle.org>
Subject: Adam Long sent you "160216 Wintergreen Farms VSMP.pdf"
4
Ltj
Adam shared a file with you on Dropbox
160216 Wintergreen Farms VSMP.pdf
Justin Deel
From: Justin Deel
Sent: Thursday, January 07, 2016 1:16 PM
To: 'Scott Collins'; 'alan@riverbenddev.com'
Subject: Planning Application Review for WPO201500098 Wintergreen Farm -VSMP.
Attachments: WPO201500098 Wintergreen Farm VSMP Review.pdf
The Review for the following application has been completed:
Application Number=WPO201500098
Reviewer=Justin Deel
Review Status = Requested Changes
Completed Date =01/07/2016
1
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP Permit plan review
Project title: Wintergreen Farm
Project file number: WP0201500098
Plan preparer: Collins Engineering [scott@collins-engineering.com]
Owner or rep.: Wintergreen Farm, LLC
c/o River Bend Development [alan@riverbenddev.com]
Plan received date: 24 November 2015
Date of comments: 7 January 2016
Reviewer: Justin Deel
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please check date on cover.
2. Please update plans in SWPPP to reflect the below requested changes.
3. Please complete sections 8, 9, and 10.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. No comment.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. Piping drainage across the WPO buffer to SWM B is not approvable. This facility should be
located on side of the stream that the drainage originates. Please adjust.
2. This plan attempts to show compliance using the new development VRRM spreadsheet; however,
the site has largely been cleared, contains at least one residence, multiple building structures,
roads, and a tennis court. "Prior developed lands" means land that has been previously utilized for
residential, commercial, industrial, institutional recreation, transportation or utility facilities or
structures, and that will have the impervious areas associated with those uses altered during a land -
disturbing activity (9VAC25-870-10). Please reanalyze and demonstrate compliance using the
Engineering Review Comments
Page 2 of 3
redevelopment VRRM spreadsheet.
3. Please correct facility labels to correspond to the BMPs used in the VRRM spreadsheet. All 3
facilities are labeled as level II.
4. The proposed level I extended detention pond does not meet the minimum length to width ratio of
2:1, please adjust.
5. Sediment forebays cannot be included in facility capacities. Forebays fill with sediment, negating
the capacity. Please adjust.
6. Please clearly show all forest/open space areas used in your VRRM (8.71 acres). DEQ requires
that all areas that will be considered forest/open space for stormwater purposes must have
documentation that prescribes that the area will remain in a natural, vegetated state. Also, it
appears that some of your forest/open space is within the 120' VEPCO easement, which, as you
state, has been cleared and is to remain cleared. These areas cannot be used as forest/open space
in the VRRM spreadsheet as they are not in a natural vegetated state.
7. Please show and quantify limits of disturbance on plans.
8. Please change plan set and sheet titles to VSMP Plan, not WPO.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. Please make the window layout of the E&SC plans a little more reader friendly for the reviewers
and contractors. This layout is very difficult to follow, particularly when dealing with 3 phases.
2. Placing sediment basin 2 within the WPO buffer does not appear to be necessary, please adjust to
outside of the buffer.
3. Please move sediment basin 3 to the east side of the stream. The WPO does not allow for piping
sediment through and across the WPO buffer to an E&SC facility on the other side of the stream.
See also SWM comment 1. This will also eliminate the need for the proposed access road winding
through the WPO buffer.
4. Please clarify what's being proposed at sediment trap 5 in Phase III. Is it realistic expect that only
half of the cul-de-sac will be completed, then removing the trap to finish?
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
Engineering Review Comments
Page 3 of 3
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
hLtp://www.albemarle.org/deptfonns.asp?department--cdengWpo