The final site plan for Lidl - Pantops has been reviewed by Engineering. The following comments will
need to be addressed before approval:
1. WPO Plan must be approved before final site plan can be approved. Rev. 1: Comment
not addressed.
2. Road Plan must be submitted and approved before final site plan can be approved. Rev. 1:
Comment not addressed.
3. VDOT approval is required. Rev. 1: Comment not addressed.
4. Please remove sheets that do not apply to the site plan (E&S, SWM).Rev. 1: Please
remove road profile sheets. They are part of the road plan (SUB 201700138). Refer
to County Code Section 32.6.2, CONTENTS OF A FINAL SITE PLAN.
5. Cannot create open channel outfall in the preserved slopes. Can pipe stormwater through
preserved slopes to get to the existing channel, but cannot create an open channel in the
preserved slopes. Rev 1: Please pipe stormwater to where it meets the 1% rule. See
WPO Plan, WP0201600073, for more details.
6. Grading along Route 20 in the preserved slopes seems excessive. Was this due to sight
distance issues? Rev. 1: Comment addressed.
7. Provide signed and sealed design for retaining walls to ensure they are structurally
adequate. Rev. 1: Design must be provided for walls adjacent to the roadway.
8. Show the location of the geogrid/grading/disturbance that will be necessary to install the
retaining walls. Ensure this is contained on site or within the easement. Rev. 1:
Disturbance for walls not shown.
9. The left sight distance profile for the entrance on Route 20 appears to have an obstruction
with the existing grade. Rev. 1: Comment addressed.
10. Provide better detail of the dumpster pad foundation. Rev. 1: Comment addressed.
11. Rev 1: Please ensure proposed contours are tying in to the existing contour
conditions.
12. Rev. 1: Ensure all comments from the road plan and WPO plan are incorporated
into the site plan.