VSMP Permit plan review
Project title: UVA Foundation Golf Facility
Project file number: WP0201700031
Plan preparer: Dewberry Engineers [dkeeler@dewberry.com]
Owner or rep.: University of Virginia Real Estate Foundation [cds7c@virginia.edu]
Plan received date:
April 3, 2017
Sept 15, 2017
Oct 19, 2017
Date of comments:
(Rev. 1)
May 9, 2017
(Rev. 2)
Oct 16, 2017
(Rev. 3)
Nov 7, 2017
Reviewer:
David James (ext. 3273)
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are satisfactorily
addressed. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. (Rev.1) Registration Statement - Provide correct 8 -digit HUC;
Provide copy of General Permit coverage when obtained;
Nature of activity — Provide the updated/correct plan date;
PPP — Provide a reduced size site plan showing potential sources of pollution generating
activities (see Sect. 6C) that can be updated by the RLD;
List/name the impaired waters with TMDL — reports can be found
httn://www.deg.vir2inia.2ov/fs2014/Choose.asi)x
2. (Rev.2) Registration Statement— Change HUC from JR14 to JR15; Sign & date. Provide reports
for only Morey Creek & Moore's Creek.
(Rev. 3) Registration Statement - Change the disturbed acres to 4.26 ac to match area stated
on sheet C6.01 of the plans.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. (Rev.2) Show a list of potential pollutant sources on the PPP and/or location of potential
pollutant sources. Show the appropriate scale for the 11x17 sheet.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved, and the reasons are provided in the comments below. The stormwater
management plan content requirements can be found in County Code section 17-403.
1. (Rev.1) Submit VSMP plan that contains only the E&SC & SWM plan sheets. Change the
title to VSMP Plan, and include WPO number.
2. (Rev.1) Provide ditch computations for any created ditches.
3. (Rev.1) Provide computations that your stormwater management design meets Part II(B)
requirements. Show that Energy Balance, or channel/flood protection to the limits of
analysis is met for both biofilter outfalls (STM S7 & S9).
4. (Rev.1) Provide routing for bioretention #2 (including forebay weir width, stage storage,
outlet protection design, etc.).
5. (Rev.1) Bioretention - Provide dimensions, and cross-sections for bioretentions. Show floor
and top embankment elevations. Show underdrain, and cleanouts. Show that 12" gravel
sump is met for entire footprint (Lvl 2).
6. (Rev.1) Provide stage storage table for detention pipe. Provide all pages of routing calcs.
7. (Rev.1) C5.04 - Correct weir elevation shown on SWM outlet control weir detail. Provide
8. (Rev.1) Verify 8' weir length is correct (see C6.06). Should this be 4 feet (see weir detail
C5.04)? Provide dimensions on manhole section.
9. (Rev.1) C6.02 - May need to correct Tc... for slopes over 15% sheet flow will become erosive in
75' or less without E&S controls (VADEQ ESC guide/manual).
(Rev.2) Not addressed. The slope and length for sheet flow as shown is incorrect.
10. (Rev.1) Show pre -/post- development drainage maps (show drainage divide, Tc calcs, point of
analysis).
(Rev.2) Not addressed. Show pre /post- development drainage area & divides. Show total
drainage area & acres. Show routed, detained, and/or undetained offsite DAs and where
runoff is going to downstream.
11. (Rev.1) Show inlet drainage map (show DA and sub -areas, C -values, Tc, destination
structures).
12. (Rev.1) Provide water quantity volume calcs for proposed underground detention. Provide
additional cover for pipe. Where does 8' long weir from routing calcs fit in 48" pipe?
13. (Rev.1) C6.05 - Show correct drawing scale. Clarify DA to each bioretention.
14. (Rev.1) Standard Inlet Shaping (IS -1) shall be required for any structure with a 4' or
greater drop.
15. (Rev.1) Provide maintenance requirements for all SWM facilities on drawings.
16. (Rev.2) Provide your analysis/determination of runoff, including calculated values.
17. (Rev.2) The DA going to S6 is 0.87ac according to sizing calcs on sheet C6.05, but according to
the routing analysis on sheet C6.06 the DA going to the detention is 2.22ac. Please correct, or
provide reasoning for difference.
(Rev. 3) Sheet C6.05 - Is the pipe going to be 42" or 48"? You use 42" for the design, but
48" shown.
18. (Rev.2) Provide information about what SWF will discharge into. State how you intend to meet
water quantity and quality requirements in SWM narrative.
(Rev. 3) Sheet C6.01- Provide/show RV calculation. Should mention that the area not
detained will sheet flow in a well -vegetated area to an existing channel.
19. (Rev.2) Provide proposed land use tabulation of the % of surface area to be adapted to
various uses, including but not limited to planned locations of utilities, roads, and
easements.
20. (Rev.2) Bioretention facility (Lvl.2) - Include detail of figure 9.4b. Provide forebay (cell) volume
is at least 15% of total treatment volume (sect. 6.4). Show underdrain, observation wells, and
cleanout locations (sect. 6.7). Provide a specific planting plan (not shown on sheet L1.03).
Provide certification that selected plants will survive ponding depths over 6" (sect. 6.8). There
are slopes >15% leading to bioretention area and this requires a two cell design (sect. 7.3). Add
notes & graphic details on plan specifying that (1) the maximum excavation depth at the
construction stage must be at least F above the post -construction installation, and (2) the facility
must contain an underdrain (sect. 8.1). What is S8 to S9 intended use? As shown, it looks like it
directs runoff offsite bypassing biofilter. Show S8 (DI -1) in the bioretention design details.
Provide S8 to S9 profile information.
(Rev. 3) Provide Planting Plan for Level 2 Bioretention.
21. (Rev. 3) Cover sheet - Show `VSMP Plan' & `WP020170003I' in the title.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. (Rev.1) A portion of the runoff will be detained at the south side ST. Where is
stormwater runoff being detained on north side of side at construction entrance?
Revise plan to include remaining area.
2. (Rev.1) Show callouts for proposed structures & E&S controls to a details sheet.
Use leaders/extend arrows/shading for clarity where needed.
3. (Rev.1) Provide storm & sanitary structure schedules.
4. (Rev.1) Label end section (ES -1) for all pipe outlets.
5. (Rev.1) Provide OP for all pipe outlets, and OP sizing calcs.
(Rev.2) Partially addressed. Show OP computations for all outlets; dims and stone sizes.
Show callout symbols for S12 & S13.
6. (Rev.1) 2.02 - Show location, footprint, grading for ST.
7. (Rev.1) C3.06 -- Show area to be protected fenced off from construction activities.
Adjust grading around tree in TP.
8. (Rev.1) C0.05 - Show Limits of Disturbance (turn on?).
9. (Rev.1) Show CE for E&S phase 11.
10. (Rev.1) Use this detail for CE (Design Manual, Sect. 6):
(Rev.2) Not addressed. Show location of sediment trapping device.
11. (Rev.1) Revise E&SC sequence... not all ph. I controls are removed.
12. (Rev.1) Remove Bioretention from E&SC plans. Should be on SWM plans. ESC
plans should only show implementation of temp. controls.
13. (Rev.1) Show staging area & stockpile locations.
14. (Rev.2) Show existing drainage divides. Show sediment trap's drainage area.
15. (Rev.2) Include sheets... soils map C0.04, overview C0.05 in set.
16. (Rev.2) Sheet C2.02/C3.06 - How will runoff be contained on the right half of site once
grading takes place?
Acknowledged. See #18 above.
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this
review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.orj4/deptfonns.asp?department—cdengw2o
A
November 7, 2017
David James
County of Albemarle
Department of Community Development
401 McIntire Road, Room 227
Charlottesville,VA 22902
RE: UVA Foundation Golf Facility (WPo2o1700030
Dear Mr. James,
In response to your VSMP comments via email dated November 7, 2017 we offer the
following responses:
A. Stormwater Pollution Prevention Plan
/. Registration Statement— Change the disturbed acres to 4.26 to match area
stated on sheet C6.oi of the plans.
Response: Area has been updated and coordinated on the plan set as well as the
Registration Statement.
B. Stormwater Management Plan (SWMP)
/1. C6.o5—Is the pipe going to be 42"or 48"? You use 42"for the design, but 48"
shown.
Response: The pipe has been update in the plan set to be a 48" pipe as the
design shows.
6Sheet C6.o1 —Provide/show RV calculation. Should mention that the area
not detained will sheet flow in a well-vegetated area to an existing channel.
Response: Rv calculations shown on sheet C6.o6. Note added on sheet
C6.o1 that any sheet flow offsite will be to a well-vegetated existing channel.
J3. Provide Planting Plan for Level 2 Bioretention.
Response: Planting Plan for Level 2 Bioretention has been added to the
Landscape sheets.
J 4. Cover sheet—Show VSMP Plan'& `WP02o1700031'in the title.
Response: VSMP Plan &WP02o1700031 have been added to the cover
sheet.
Mr.David James
WA Foundation Golf Facility
WPo2o1700031
November 7,2017
Page 2 of 2
Thank you for your attention in this matter. Please contact me with any questions or
concerns at (804) 205-3321 or email dkeeler@dewberry.com
Sincerely,
Devin Keeler, P.E.
Dewberry
Dewberry
4
October 17, 2017
David James
County of Albemarle
Department of Community Development
401 McIntire Road, Room 227
Charlottesville,VA 22902
RE: UVA Foundation Golf Facility (WPo2o1700031)
Dear Mr. James,
In response to your VSMP comments via email dated October 16, 2017 we offer the
following responses:
A. Stormwater Pollution Prevention Plan
1. Registration Statement— change HUC from JR14 to JR15; Sign&date. Provide
reports for only Morey Creek&Moore's Creek.
Response: Will change HUC from JR14 to JR15, sign, and date.
B. Pollution Prevention Plan (PPP)
1. Show a list of potential pollutant sources on the PPP and/or location of
potential pollutant sources. Show the appropriate scale for the 11x17 sheet.
Response: PPP Exhibit is attached with appropriate scale.
C. Stormwater Management Plan (SWMP)
1. C6.o2 —May need to correct Tc...for slopes over 15%sheet flow will become
erosive in 75'or less without E&S controls (VADEQ ESC guide/manual)
Response: Time of concentration has been adjusted per our conversation.
Additional offsite Tc has been shown for further clarity on drainage/runoff
calculations.
2. Show pre-/post- development drainage maps (show drainage divide, Tc
calcs,point of analysis).
Response: As discussed, a pre-drainage map for this site will not clarify
anything as there are no existing structures and all the drainage goes to the
existing roadside swale. To help clarify the offsite drainage around the site,
areas have been delineated to show the runoff to the proposed swales to help
clarify the numbers used in the calculations found on sheet C6.o5. The
delineated areas for all runoff can be found on sheet C6.o5.
' Mr.David James
UVA Foundation Golf Facility
WPo2o1700031
October 17,2017
Page 2 of 3
3. Provide your analysis/determination of runoff, including calculated values.
Response: As previously stated, all runoff areas have been delineated and
calculated for clarity on sheet C6.o5. Tc numbers for the offsite drainage to
the swale can be found on sheet C6.o2.
4. The DA going to S6 is 0.87 ac according to sizing talcs on sheet C6.05, but
according to the routing analysis on sheet C6.o6 the DA going to the
detention is 2.22 ac. Please correct, or provide reasoning for difference.
Response: Computations have been corrected on sheet C6.o6.
5. Provide information about what SWF will discharge into. State how you
intend to meet water quantity and quality requirements in SWM narrative.
Response: SWM Narrative has been updated to clarify discharge
information. On sheet C6.oi the energy balance has been updated and shown
for clarity.
6. Provide proposed land use tabulation of the % of surface area to be adapted
to various uses, including but not limited to planned locations of utilities,
road, and easements.
Response: As discussed this has been satisfied.
7. Bioretention facility(Lv1.2) —Include detail of figure 9.4b. Provide forebay
(cell) volume is at least 15% of total treatment volume (sect. 6.4). Show
underdrain, observatio • a • . •• • • :e a e • • . - . Provi e
sped M• e tin. •lan not shown on sheet L1.o3) 'rove.e cer i `ca on t at
selected plants will survive pone mg •ep s o • .' sect. •.8 . There arc
s • .•-i►se "-410 . :---_. a esign/
7.3).Add notes&graphic details on plan specifying that(1) the
maximum excavation depth at the construction stage must be at least 1'
above the post-construction installation, and( - : : • •-. -- . . ' ;
What is S8 to S9 intended use?As shown, it looks like
it directs runoff offsite bypassing biofilter. Show S8 (DI-1) in the bioretention Oil,
design details. Provide S8 to S9 profile information.
14 ,, 0
Response: Forebay calculations have been added to s et 4.03 per our t''
conversation are an adequate treatment method for the vel 2. derdrains ` ,
with observation wells/cleanouts have been added to theplan. The planting 1
plan on Li.o3 combined with the planting schedule also on shee .Li.o3 should
provide all the detail needed. The plan and schedule identify the location,
materials, and quantities of seed to be planted in the bioretention area. The 0.
1�0
I
Dewberry
' ' ' Mr.David James
UVA Foundation Golf Facility
WPo2or70003i rr /�// II__
October 17,2017 T,(;44:0„/ d �5 i k --6
Page 3 of 3
seed mix is the "rain • . • • °" mix, which has been designed by a leading
conservation seed-: e .•- and is intended for use in wet rain gardens. A note
has been added to clarify mucking of sediment trap is necessary before the
installation of the bioretention facility. As disccuss S8 to S9 is the
bioretentions overflow structure and it does not direct runoff offsite bypassing
the biofilter. The profile sheet that shows this, sheet C4.o3, has been added to
the VSMP submission to clarify this.
D. Erosion and Sediment Control Plan (ESCP)
1. Provide OP for all pipe outlets, and OP sizing talcs.
Response: Outlet protection and sizing has been added to all pipe outlets,.
see sheet C3.o6.
2. Use this detail for CE(Design Manual, Sect. 6), show location of sediment
trapping device.
Response: Detail has been added for possible future need on site.
3. Show existing drainage divides. Show sediment trap's drainage area.
Response: Drainage area for the sediment trap has been added to sheet
C2.o2.
4. Include sheets...soils map Co.o4, overview Co.o5 in set. V
C
Response: Soils map Co.o4 and overview Co.o5 have been added to the set.
5. Sheet C2.o2/C3.o6 —How will runoff be contained on the right hald of site . /
once grading takes place. V
Response: Per our conversation, a diversion has been added to divert clean
offsite water around the site.
Thank you for your attention in this matter. Please contact me with any questions or
concerns at (804) 205-3321 or email dkeeler@dewberry.com
Sincerely,
Devin Keeler, P.E.
Dewberry
9 Dewberry°
Phone (434) 296-5832
OF Alga.
VIRGSry�P
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
VSMP Permit plan review
Fax (434) 972-4126
Project title: UVA Foundation Golf Facility
Project file number: WP0201700031
Plan preparer: Dewberry Engineers [dkeeler@dewberry.com]
Owner or rep.: University of Virginia Real Estate Foundation [cds7c@virginia.edu]
Plan received date:
(Rev. 1)
(Rev. 2)
Date of comments:
(Rev. 1)
(Rev. 2)
Reviewer:
April 3, 2017
Sept 15, 2017
May 9, 2017
Oct 16, 2017
David James (ext. 3273)
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are satisfactorily
addressed. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESOP, (3) a SWMP, and (4) any TMDL measures necessary.
1. (Rev.1) Registration Statement - Provide correct 8 -digit HUC;
Provide copy of General Permit coverage when obtained;
Nature of activity — Provide the updated/correct plan date;
PPP — Provide a reduced size site plan showing potential sources of pollution generating
activities (see Sect. 6C) that can be updated by the RLD;
List/name the impaired waters with TMDL — reports can be found
http://www.deci.virginia.gov/fs2014/Choose.aspx
2. (Rev.2) Registration Statement — Change HUC from JR14 to JR15; Sign & date. Provide
reports for only Morey Creek & Moore's Creek.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. (Rev.2) Show a list of potential pollutant sources on the PPP and/or location of potential
pollutant sources. Show the appropriate scale for the 11x17 sheet.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved, and the reasons are provided in the comments below. The stormwater
management plan content requirements can be found in County Code section 17-403.
1. (Rev.1) Submit VSMP plan that contains only the E&SC & SWM plan sheets. Change the
title to VSMP Plan, and include WPO number.
2. (Rev.1) Provide ditch computations for any created ditches.
3. (Rev.1) Provide computations that your stormwater management design meets Part II(B)
requirements. Show that Energy Balance, or channel/flood protection to the limits of
analysis is met for both biofilter outfalls (STM S7 & S9).
4. (Rev.1) Provide routing for bioretention #2 (including forebay weir width, stage storage,
outlet protection design, etc.).
5. (Rev.1) Bioretention - Provide dimensions, and cross-sections for bioretentions. Show floor
and top embankment elevations. Show underdrain, and cleanouts. Show that 12" gravel
sump is met for entire footprint (Lvl 2).
6. (Rev.1) Provide stage storage table for detention pipe. Provide all pages of routing calcs.
7. (Rev.1) C5.04 - Correct weir elevation shown on SWM outlet control weir detail. Provide
8. (Rev.1) Verify 8' weir length is correct (see C6.06). Should this be 4 feet (see weir detail
C5.04)? Provide dimensions on manhole section.
9. (Rev. l) C6.02 - May need to correct Tc... for slopes over 15% sheet flow will become erosive in
75' or less without E&S controls (VADEQ ESC guide/manual).
(Rev.2) Not addressed. The slope and length for sheet flow as shown is incorrect.
10. (Rev.1) Show pre -/post- development drainage maps (show drainage divide, Tc calcs, point of
analysis).
(Rev.2) Not addressed. Show pre /post- development drainage area & divides. Show total
drainage area & acres. Show routed, detained, and/or undetained offsite DAs and where
runoff is going to downstream.
11. (Rev.1) Show inlet drainage map (show DA and sub -areas, C -values, Tc, destination
structures).
12. (Rev.1) Provide water quantity volume calcs for proposed underground detention. Provide
additional cover for pipe. Where does 8' long weir from routing calcs fit in 48" pipe?
13. (Rev.1) C6.05 - Show correct drawing scale. Clarify DA to each bioretention.
14. (Rev.1) Standard Inlet Shaping (IS -1) shall be required for any structure with a 4' or
greater drop.
15. (Rev.1) Provide maintenance requirements for all SWM facilities on drawings.
16. (Rev.2) Provide your analysis/determination of runoff, including calculated values.
17. (Rev.2) The DA going to S6 is 0.87ac according to sizing calcs on sheet C6.05, but according
to the routing analysis on sheet C6.06 the DA going to the detention is 2.22ac. Please
correct, or provide reasoning for difference.
18. (Rev.2) Provide information about what SWF will discharge into. State how you intend to
meet water quantity and quality requirements in SWM narrative.
19. (Rev.2) Provide proposed land use tabulation of the % of surface area to be adapted to
various uses, including but not limited to planned locations of utilities, roads, and
easements.
20. (Rev.2) Bioretention facility (Lvl.2) - Include detail of figure 9.4b. Provide forebay (cell)
volume is at least 15% of total treatment volume (sect. 6.4). Show underdrain, observation
wells, and cleanout locations (sect. 6.7). Provide a specific planting plan (not shown on
sheet L1.03). Provide certification that selected plants will survive ponding depths over 6"
(sect. 6.8). There are slopes >15% leading to bioretention area and this requires a two cell
design (sect. 7.3). Add notes & graphic details on plan specifying that (1) the maximum
excavation depth at the construction stage must be at least 1' above the post -construction
installation, and (2) the facility must contain an underdrain (sect. 8.1). What is S8 to S9
intended use? As shown, it looks like it directs runoff offsite bypassing biofilter. Show S8 (DI -
1) in the bioretention design details. Provide S8 to S9 profile information.
A Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. (Rev.1) A portion of the runoff will be detained at the south side ST. Where is
stormwater runoff being detained on north side of side at construction entrance?
Revise plan to include remaining area.
2. (Rev.1) Show callouts for proposed structures & E&S controls to a details sheet.
Use leaders/extend arrows/shading for clarity where needed.
3. (Rev.1) Provide storm & sanitary structure schedules.
4. (Rev.1) Label end section (ES -1) for all pipe outlets.
5. (Rev.1) Provide OP for all pipe outlets, and OP sizing calcs.
(Rev.2) Partially addressed. Show OP computations for all outlets; dims and stone sizes.
Show callout symbols for S12 & S13.
6. (Rev.1) 2.02 - Show location, footprint, grading for ST.
7. (Rev.1) C3.06 -- Show area to be protected fenced off from construction activities.
Adjust grading around tree in TP.
8. (Rev.1) C0.05 - Show Limits of Disturbance (turn on?).
9. (Rev.1) Show CE for E&S phase II.
10. (Rev.1) Use this detail for CE (Design Manual, Sect. 6):
STONE 30 MIN.
CONSTRUCTION
ACCESSS' SM -2A ASPHALT TOA
COURSE EXISTING
2R 2R PAVEMENT
6 ':N. 21A ACOREGATE BASE
PROFILE
STONE _"'"IN
CONSTRUCTION ASPHALT PAVED
ACCESS -\ r-'® rWA RRATC
PAVFW `:I
l+-PDSIT
'MUST E]ITENU NLL Wf�F A I 70 SEDIMENT
NE DRAINAGE
OF INGRESS AND EGRESS 4 TRAPPING DEVICE
OPERATION
ELAS
12MiNPODRAINAGE TC, SEDIMENT
TRAPPING PENCE
T': ER CL9TH
SECTION A -A
_1 UWMII D waltt fay of 1 tlldl nmol Ue mafa0ed wilh a mhlnmuu 1 inch ba0cack
shutoff Mahe suyphuts a wash hose with a dianteler 01`1 uwhes fot adecpulfe
cO1vtM1(pmq.91We- WOEII Nater Until be carried away fl on) the nlhance to an
7I>(xoced setttillg aea to ranace sed�nalt. ell saluuaTt shall be prm mted from
atlaitte MIDI (haw, ditches 01wata[o1H'ses.
PAVED WASH RACK
NO SCALE
(Rev.2) Not addressed. Show location of sediment trapping device.
11. (Rev.1) Revise E&SC sequence... not all ph. I controls are removed.
12. (Rev.1) Remove Bioretention from E&SC plans. Should be on SWM plans. ESC
plans should only show implementation of temp. controls.
13. (Rev.1) Show staging area & stockpile locations.
14. (Rev.2) Show existing drainage divides. Show sediment trap's drainage area.
15. (Rev.2) Include sheets... soils map C0.04, overview C0.05 in set.
16. (Rev.2) Sheet C2.02/C3.06 - How will runoff be contained on the right half of site
once grading takes place?
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this
review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
htt2://www.albemarle.org/deptforms.asl2?department--cdengMMo
Phone (434) 296-5832
OF AI g�
VIRGSry�P
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
VSMP Permit plan review
Fax (434) 972-4126
Project title: UVA Foundation Golf Facility
Project file number: WP0201700031
Plan preparer: Dewberry Engineers [dkeeler@dewberry.com]
Owner or rep.: University of Virginia Real Estate Foundation [cds7c@virginia.edu]
Plan received date:
(Rev. 1)
Date of comments:
(Rev. 1)
Reviewer:
April 3, 2017
May 9, 2017
David James (ext. 3273)
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are satisfactorily
addressed. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Registration Statement - Provide correct 8 -digit HUC;
Provide copy of General Permit coverage when obtained;
Nature of activity — Provide the updated/correct plan date;
PPP — Provide a reduced size site plan showing potential sources of pollution generating
activities (see Sect. 6C) that can be updated by the RLD;
List/name the impaired waters with TMDL — reports can be found
http://www.deq.virginia.gov/fs2014/Choose.aspx
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved, and the reasons are provided in the comments below. The stormwater
management plan content requirements can be found in County Code section 17-403.
1. Submit VSMP plan that contains only the E&SC & SWM plan sheets. Change the title to
VSMP Plan, and include WPO number.
2. Provide ditch computations for any created ditches.
3. Provide computations that your stormwater management design meets Part II(B)
requirements. Show that Energy Balance, or channel/flood protection to the limits of
analysis is met for both biofllter outfalls (STM S7 & S9).
4. Provide routing for bioretention #2 (including forebay weir width, stage storage, outlet
protection design, etc.).
5. Bioretention - Provide dimensions, and cross-sections for bioretentions. Show floor and top
embankment elevations. Show underdrain, and cleanouts. Show that 12" gravel sump is
met for entire footprint (Lvl 2).
6. Provide stage storage table for detention pipe. Provide all pages of routing calcs.
7. C5.04 - Correct weir elevation shown on SWM outlet control weir detail. Provide
8. Verify 8' weir length is correct (see C6.06). Should this be 4 feet (see weir detail C5.04)?
Provide dimensions on manhole section.
9. C6.02 - May need to correct Tc... for slopes over 15% sheet flow will become erosive in 75'
or less without E&S controls (VADEQ ESC guide/manual).
10. Show pre -/post- development drainage maps (show drainage divide, Tc calcs, point of
analysis).
11. Show inlet drainage map (show DA and sub -areas, C -values, Tc, destination structures).
12. Provide water quantity volume calcs for proposed underground detention. Provide
additional cover for pipe. Where does 8' long weir from routing calcs fit in 48" pipe?
13. C6.05 - Show correct drawing scale. Clarify DA to each bioretention.
14. Standard Inlet Shaping (IS -1) shall be required for any structure with a 4' or greater drop.
15. Provide maintenance requirements for all SWM facilities on drawings.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. A portion of the runoff will be detained at the south side ST. Where is stormwater
runoff being detained on north side of side at construction entrance? Revise plan
to include remaining area.
2. Show callouts for proposed structures & E&S controls to a details sheet. Use
leaders/extend arrows/shading for clarity where needed.
3. Provide storm & sanitary structure schedules.
4. Label end section (ES -1) for all pipe outlets.
5. Provide OP for all pipe outlets, and OP sizing calcs.
6. 2.02 - Show location, footprint, grading for ST.
7. C3.06 -- Show area to be protected fenced off from construction activities. Adjust
grading around tree in TP.
8. C0.05 - Show Limits of Disturbance (turn on?).
9. Show CE for E&S phase II.
10. Use this detail for CE (Design Manual, Sect. 6):
STFINE 70' MIN.
CONSTRUCTION
ACCESSS" SM -7.A ASPNALT TCP
COURSE
2$ 211 F..
6' MIN, 21A AGGREGATE BASE
PROFILE
STONE
CONSTR CI'ICN
ACCESS -
PAVEWIVI
�+—PC3IT- )-II
NTRONS
-MUST EXTEND FJL_ ESS TO SECIMENT A I
OF IAND EGRESS 4
OPERATION TRAPPING OEVCE
FM
—12' MINTWE DRAINAGE
SEDIMENT 2S TO SE01HEN7
TRAPpIryG G`�"!
FlLTER Civ?H
SECTION A—A
A muwntn wales tap of 1 filen nw t be ulsta0ed with a minhmutt 1 filch baOcocA
shutoffvWt stlpphiug n wash hOSC w4111 fl d1a111Cter Of 1.? hlches fOr ade(pl ate
constatlt pressure- wash water In1ri'1 be ealried away from the entrance to an
Ittnxoved settling area to relnoce sedt1nc11F. All swlunad.+-hA be prel-ented from
entok-_ stmnl ch aul�, ditches or watuI,olu'ses.
PAVED WASH RACK
NO SCALE
11. Revise E&SC sequence... not all ph. I controls are removed.
12. Remove Bioretention from E&SC plans. Should be on SWM plans. ESC plans
should only show implementation of temp. controls.
13. Show staging area & stockpile locations.
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this
review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.