February 12, 2015
Mr. Glenn Brooks, P.E.
County Engineer
Albemarle County Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902
RE: Cascadia—Blocks 4-7(WPO 2013-00032)— VSMP Amendment
Dear Glenn,
Enclosed please find two (2) sets of VSMP Amendment that have been prepared to address a STOP WORK
order on the referenced project. When the contractor was clearing to install the sediment basin adjacent to
Route 20, it was discovered that the ditch that runs parallel to the road meandered on to the site in the
approximate location of the proposed dam embankment. Our proposal is to divert this ditch to downstream toe
of the embankment slope,thereby adhering to the intent of the approved plans. The attached amendment
includes design computations that indicate the ditch is to be a ditch meeting the EC-2 design specifications.
We have discussed the amendment with Max Greene and have shown a sediment trap along Route 20 to
control sediment laden runoff until the new ditch is stabilized.
We also met with Vinny Pero of the Army Corps of Engineers onsite on Monday, February 9, 2015. Vinny has
determined the ditch in question is a stormwater ditch and no further remediation is necessary. I have included
the email trail to this submission.
We trust the above adequately addresses your comments. Please let me know if you have any questions or
require additional information. Also, if you are in approval, can you please notify Jeremy Glode and myself as
soon as possible so that we can alert the construction crews to get back to work?
Very truly yours,
M iael Myers, P.E., C.F.M.
Attachments
Cc: Jeremy Glode
Guy Wright
Charlie Armstrong
Charlie Hurt
Page 1 of 1
Mike Myers
From: Charlie Armstrong [carmstrong@southern-development.com]
Sent: Monday, February09, 2015 10:49 AM
To: Keith Lancaster; Mike Myers
Subject: FW: Cascadia Stop Work Fix(UNCLASSIFIED)
Original Message
From: Pero, Vincent D NAO [mailto:Vincent.D.Pero@usace.army.mil]
Sent: Monday, February 09, 2015 10:44 AM
To: Charlie Armstrong
Subject: FW: Cascadia Stop Work Fix (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Here you go Charlie
Thanks
Original Message
From: Pero, Vincent D NAO
Sent: Monday, February 09, 2015 10:33 AM
To: 'Max Greene'; 'Glenn Brooks'
Cc: Pero, Vincent D NAO; 'Millard, Eric (DEQ) '
Subject: RE: Cascadia Stop Work Fix (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Max
I just got back from a site visit at Cascadia. I have determined the channel is not a water
of the United States, but an outlet from the stormwater basin from the Fontana development
above the Cascadia project and is not under the jurisdiction of the Corps of Engineers.
The Corps does not regulate storm water facilities. I informed the consultant and someone
from Southern development that they should always get a letter from the Corps if there is any
water or possible wetlands on site. May be a good idea for you guys to inquire of the
developers if they have talked to the Corps. Just a thought.
Thanks and let me know if I can be of further help
Vinny
Original Message
From: Max Greene [mailto:MGreene@albemarle.org]
Sent: Friday, February 06, 2015 10:32 AM
To: Pero, Vincent D NAO
Subject: [EXTERNAL] FW: Cascadia Stop Work Fix
Pic's of Cascadia stream are location in a link in e-mail from Mike Myers.
a
1
Thanks,
Max
From: Jeremy Glode
Sent: Wednesday, February 04, 2015 9:16 AM
To: Michelle Roberge; Glenn Brooks
Cc: Max Greene
Subject: FW: Cascadia Stop Work Fix
FYI - here's the stream fix proposed by Dominion.
Jeremy Glode
Engineering Inspector
Albemarle County
jglode@albemarle.org
(c) 434-989-1534
From: Mike Myers [mailto:mmyers@dominioneng.com]
Sent: Monday, February 02, 2015 2:59 PM
To: Max Greene; Jeremy Glode
Cc: Keith Lancaster; Charlie Armstrong; Barbara Wright; Charlie A. Hurt
Subject: Cascadia Stop Work Fix
Max, We met this morning with Jeremy Glode, Linco and Hanley Excavating to discuss a
resolution to a stop work order issued last week. Currently, the Route 20 roadside ditch is
flowing within the construction limits of the dam as can be seen on the attached plan and on
the photos in my dropbox link below. It appears that the actual topo is slightly off with
the aerial topo survey. The solution appears to be a fairly straightforward one - redirect
the ditch to the downstream side of the dam. Please see attached plan sheet with a typical
cross-section showing a 4'-wide V-ditch with EC-2 lining. As discussed in the field, we have
indicated the final 30 feet of ditch to be rip-rap lined. Our thought was to include this
plan in the SWPPP and allow the contractor to proceed based on this. Please review and call
me to discuss if you have any questions. If this looks good, can you please let Jeremy know,
thanks! Mike
Drop box Link to site photos:
2
1 ,
' ..https1//www.dropbox.com/sh/08i93hzo4em9utn/AACju5BLva1PUjPaPPGrjla1a?d1=0
Michael F. Myers, P.E., C.F.M.
Director of Engineering
Dominion Engineering and Design, LLC
172 South Pantops Drive
Charlottesville, VA 22911
434.979.8121 ext. 2 (office)
434.906.3161 (mobile)
Please visit our website at: www.dominioneng.com
domeng
Classification: UNCLASSIFIED
Caveats: NONE
Classification: UNCLASSIFIED
Caveats: NONE
3
1 , •
•
Glenn Brooks
From: Glenn Brooks
Sent: Friday, July 31, 2015 2:32 PM
To: 'Mike Myers'
Cc: Kenny Thacker; Jeremy Glode
Subject: WPO201500043 Cascadia interim plan amendment
Mike,
This plan is approved. I will give the two copies you submitted to our inspectors. Please ensure the contractor has
adequate copies,and they are include in the SWPPP documents on-site.
Thank you,
Glenn Brooks, P.E.
County Engineer
VSMP Administrator
Albemarle County
1