HomeMy WebLinkAboutSDP201800003 Review Comments Final Site Plan and Comps. 2018-02-07County of Albemarle
Department of Community Development
Memorandum
To: Patricia Saternye
From: Emily Cox
Date: 07 Feb 2018
Subject: Hansen Road Church — Final Site Development Plan (SDP201800003)
The final site development plan for Hansen Road Church has been reviewed by Engineering. The
following comments will need to be addressed before approval:
1. WPO Plan must be submitted and approved before final site plan can be approved.
2. Please ensure the professional seal is signed and dated.
3. Provide details for the proposed retaining walls.
4. Provide drainage easements for all pipes carrying water offsite. Easements will need to be recorded
before plan can be approved.
5. Parallel parking spaces should be 9'x20', not 8'x20'. (County Code Chapter 18- 4.12.16)
6. Show pavement markings required throughout the site (stop bars, one-way at the drop-off area,
etc.)
7. Provide a road section detail. Pavement sections were provided, but not road sections.
8. Ensure proposed tree protection locations are shown on the demolition sheet.
9. 2:1 Slopes should be avoided wherever possible. The landscape plan does properly specify the
required ground cover, but please ensure the WPO Plan also specifies this.
10. Please show the acreage and c-factors for each drainage area on sheet C-11.
11. Where is Ex. DI-7? The note on Sheet C-I I says concrete flume to Ex. DI-7, but it is not labeled.
12. Velocity in storm drains should be kept below 10 ft/s if possible.( Per the VDOT drainage manual,
section 9.4.8.7, velocities in excess of 10ft/s should be avoided)