HomeMy WebLinkAboutWPO201700024 Review Comments WPO VSMP 2018-01-25Short Review Comments Report for:
WPO201700024
SubApplication Type:
Chesterfield Landing II
Stormwater Management/BMP Plan
Erosion and Sediment Control Plan
Date Completed:03/29/2017
Reviewer:Bobby Jocz CDD Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:05/26/2017
Reviewer:Bobby Jocz CDD Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:12/13/2017
Reviewer:Bobby Jocz CDD Engineering
Review Status:Pending
Reviews Comments:Approved conditional on record of Deed of Dedication and Easement Plat for SWM forest and Open
Space
Division:
Date Completed:12/20/2017
Reviewer:Bobby Jocz CDD Engineering
Review Status:See Recommendations
Reviews Comments:
Division:
Date Completed:01/25/2018
Reviewer:Jennifer Pritchett CDD Engineering
Review Status:Approved
Reviews Comments:SWM RECORDED WITH THE COUNTY CLERK'S OFFICE 01/25/2018 - DEED BOOK 5008,
PAGES 93-101
Division:
Page:1 of 1 County of Albemarle Printed On:February 13, 2018
SHIM PROJA
CIVIL ECT ME NGINEERINGNAGEMENT
LAND PLANNING
t. I 14 k
May 5, 2017
Bobby Jocz
Albemarle County
Department of Community Development
Regarding: WPO 2017 00024—Chesterfield Landing II—VSMP
Dear Mr. Jocz,
I have attached 2 copies of the Site Development Plans addressing your comments dated March 30, 2017. The
specific changes are outlined below.
A. Stormwater Pollution Prevention Plan (SWPPP)
1. [General] Parcel boundaries do not match that available in County records. Referenced deed book
and page for parcel PLAT does not match existing records. Please update, or provide confirmation
regarding parcel boundaries.
/4.3111 (2„44.sbbd„7 5k/ Soap- bo drj.
A proposed boundary line adjustment is shown. It is now labeled on sheet C2.
2. [General] All topography should be field verified by the designer within the last year. Please
provide information on the date of field verification.
Justin Shimp recently visited the site to verify topography. This date has been added to the plans. O/'
3. [General] Disturbed and total project acreage is inconsistent between WPO submittal, registration
statement, and other documentation. Please correct.
The project acreage and disturbed area have been updated throughout the plans and forms.
4. [General] Easement or other form of agreement for working on lots/area outside of property
boundary will be needed.
Grading has been altered so that it no longer encroaches upon Lot 16 of Phase One of this development.
The sanitary lateral installation will take place within the sanitary sewer easement, and there is a grading
easement already covering the storm installation down to the level spreader.
5. [General] A mitigation plan will need to be provided for buffer impacts related to construction of
the level spreader.
A mitigation plan is now included on sheet C14. 0/(-
6.
/6. [SWPPP] Signatures must be provided on Registration statement prior to final VSMP approval.
Signatures are now provided on the Registration Statement. 0 I
7. [SWPPP] Signatures must be provided on Certification and Delegation of authority forms prior to
land disturbance permit issuance.
Signatures are now provided on the Certification and Delegation of Authority forms. e.„
8. [Cover sheet] Provide the WPO number, WP0201700024, for the project on the cover sheet and
SWPPP booklet.
The WPO number is now on the cover sheet and SWPPP booklet.-*X - k✓AS �vkTiv
�
9. [General] label limits of WPO stream buffer, line is provided but not labeled. Ensure all hatching
is included in the key or explicitly labeled, such as shading for Preserved/managed/critical slopes.
Some symbols are not identified (The brick hatching pattern on sheet C3, the L shaped hatching
adjacent to the managed slopes on C2/C3).
The floodplain label has been edited to indicate that it is also the stream buffer. Labels have been added to
the hatching on sheets C2 and C3. -084(6- Ctfrtlno hist f/adf/Nr OW k*I.br/d
10. [SWPPP] Phosphorous reduction results are not consistent between project narrative and VRRM
spreadsheet. The narrative states that phosphorous reduction requirements will be exceeded by 0.3
lbs/year, while the VRRM spreadsheet states it will be exceeded by 1.16 lbs/year. Please clarify.
The VRRM is correct; however,the project narrative had not been updated. This has been fixed.
11. [Sheets C4 &C5] Scaling is incorrect, indicated as 1"=30', when scale is actually 1"=20'. Ensure
scales are correct throughout.
The scales have been updated on these two sheets.O1
B. Pollution Prevention Plan (PPP)
1. No Objection OK/
C. Stormwater Management Plan (SWMP)
1. [General] Provide legible pre and post-construction drainage areas. Drainage areas should relate to
those used on VRRM spreadsheet. Provide on plan sheets, not on separate documents.
The drainage area maps have been updated to be printed on 18x24 sheets, which doubles the size. They
should now be shown legibly.
2. [General] Inlet/stormsewer sections provided in calculations packet (Structures Bl-B11) are not
identified on the plans. Please indicate their location.
The Phase 1 storm inlets are now identified on the overview sheet of the plan set and on the storm sewer
drainage map.
3. [General] Adequate channel must be provided/identified for water discharging from outlet Dl.
After a site visit, the location of discharge appeared to be best suited for a level spreader. The existing
vegetation to remain below the level spreader consists of thick fescue and will be adequate to dissipate
stormwater runoff into sheet flow.
4. [Sheet C14] The SWM plan should include an exhibit identifying the indicated 8.14 acres of
conserved as Forest and Open space. The size (in acres) of conserved spaces should also be
provided and match that identified on the VRRM spreadsheet. Conserved Forest and Open Space
should be identified in a separate PLAT with deed and SWM agreement.
The conserved open space areas have been labeled on sheet C3. They are indicated with a diagonally
striped hatch.
5. [Sheet C14] Please include maintenance guidelines for Forest and Open Space on SWM plan.
Should be formatted in a manner similar to that provided for the level spreader.
Maintenance for conserved open space has been described in the same section as the level spreader
maintenance. Ok
6. [Sheet C14] VRRM spreadsheet summary should be provided on the SWM plan sheet.
The VRRM Summary is now included on sheet C14.
7. [Sheet C14] Provide sizing and detail of riprap outlet channel conveying stormwater towards level
spreader.
Dimensions for the channel have been provided, and it is now included in the profile on sheet C14.
8. [All] Identify all current and proposed easements, including deed book and page. Include easement
type and widths.
Labels have been added to the proposed 20' public drainage easement. The sidewalk/landscaping
easement label has been updated to include the width.
9. [General] Volumes do not appear to match. Volume of runoff from impervious surfaces treated by
level spreader(s) does not match that designated in VRRM spreadsheet, or is not clearly indicated
within drainage maps provided. If runoff is treated by separate level spreader, provide
documentation proving it is designed to handle additional capacity.
A note regarding the history of the project has been added to the stormwater management computation
packet, along with the Phase 1 computations documenting capacity for a portion of the Phase 2
development.
D. Erosion and Sediment Control Plan (ESCP)
1. [Narrative] Existing site conditions section references the wrong parcel and parcel owner. Please
correct.
Parcel number and parcel owner have been updated. 91,
2. [Narrative] Soils section contains typos. Please correct.
The mislabeled soil `37C3'was changed to `37D3.'
3. [Narrative] Adjacent property section does not contain accurate information. Please revise.
The adjacent property information has now been updated. Off/
4. [General] Existing grade lines are incorrect. Grading for existing cul-de-sac should be presented as
existing grade.
The proposed cul-de-sac grading from phase one has been shown in a grayed layer. Proposed grading is
shown tying into the phase one grading. Iv
5. [Sheet C16] Areas receiving temporary seeding and dust control should be identified.
Areas with temporary seeding and dust control have now been identified on sheet C16. 'J't-
6. [Sheet C16] Provide drainage area acreages to each sediment trap.O�
These areas are provided in the table titled "Sediment Trap Design Data."
7. [Sheet C16] Clarify function of structure (appears to be diversion dike) placed along LOD to the
north of the property between sediment traps 1&2.
I believe it is the fill diversion you are referring to. This item was not included in the legend before, but it
has been added.Oi
8. [C16, C17 & C18] No soil divides are provided, or labeled. (31._
Soil divides have now been added to sheets C16 & C17, along with labels for each section of soil.
9. [Sheet C17] Ensure all symbols are identified in key.
The temporary fill diversion has been added to the erosion and sediment control legend. 21L
10. [All] a ROW diversion should be provided across the construction entrance.
A right-of-way diversion is now specified across the construction entrance. 9!L_
11. [All] Provide contour elevations.
Contour elevations are now shown on the plan.°`1---
If you have any questions please do not hesitate to contact me at your earliest opportunity at lauren@shimp-
engineering.com or Justin Shimp, P.E. may be reached at:justin@shimp-engineering.com or by phone at 434-953-
6116.
Best Regards,
\,
, ,
, . ,
aur n Gilroy
Shimp Engineering, P.C.
&A
tell!,-iiii
6414.
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road,Room 227
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
VSMP Permit plan review
Project title: Chesterfield Landing II
Project file number: WPO201700024
Plan preparer: Justin Shimp [Justin@shimp-engineering.com]
Keane Rucker,E.I.T[keane@shimp-engineering.com]
Owner or rep.: SM Charlottesville[swinkjw@stanleymartin.com]
Plan received date: Rev 1 —3rd Mar. 2017
Rev 2- 10tMay 2017
Rev 3—20"'November 2017
Date of comments: Rev 1 —30th Mar. 2017
Rev 3— 11th December 2017
Reviewers: 1 —Bobby Jo,
Rev 2—Bobby Jocz
Rev 3—Bobby Jocz
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is Denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
Note: The resubmittal may result in additional comments due to incompleteness of current
submittal.
A. Stormwater Pollution Prevention Plan(SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain(1)a PPP,(2)an ESCP,(3)a SWMP, and(4)any TMDL measures necessary.
1. [General] l rcel boundaries do not match that available in County records. Referenced deed book
and page f parcel PLAT does not match existing records. Please update, or provide confirmation
regarding parcel boundaries.
Rev 2—Acknowledged, however the boundary line to the southwest portion of the property
is still in question. Please provide copy of"Unrecorded" Boundary line plat by Roger Ray
Rev 3—Adequately Addressed.
2. [General] 1 aph; ,c field verified by the designer within the last year. Please
provide information on the date of field verification.
Rev 2—Addressed,field verified by Shimp Engineering May 3".
3. [General] Disturbed and total project acreage is inconsistent between WPO submittal, registration
statement, and other documentation. Please correct.
Rev 2—Incomplete. Disturbed area must be updated on Registration statement to reflect
Engineering Review Comments
Page 2 of 6
increased disturbed acreage in Phase II (it seems the exact same registration statement,with
updated signature,was submitted from Chesterfield landing Phase I). In addition,disturbed
,c'cs,'i "vi in 1'cR , lc'
Rev 3—Partially addressed.Disturbed area is not correct on cover sheet. It indicates
disturbed area as 17.71 acres whereas the registration statement and other documentation
state a disturbance of 7.17 acres.
4. [General] Easement or other form of agreement for working on lots/area outside of property
• boundary will be needed.
Rev 2—Addressed.
5. [General] A mitigation plan will need to be provided for buffer impacts related to construction of
the level spreader.
Rev 2—Addressed
6. [SWPPP] Signatures must be provided on Registration statement prior to final VSMP approval.
Rev 2—Addressed
7. [SWPPP] Signatures must be provided on Certification and Delegation of authority forms prior to
land disturbance permit issuance.
Rev 2—Addressed
8. [Cover sheet]Provide the WPO number, WPO201700024, for the project on the cover sheet and
SWPPP booklet.
Rev 2—Not provided on the SWPPP booklet. Please provide new cover sheet including
,..rs
Rev 3 -Addressed
9. - ., „„. .[s of WPO stream buffer, line is provided but not labeled. Ensure all hatching
is included in the key or explicitly labeled, such as shading for Preserved/managed/critical slopes.
Some symbols are not identified(The brick hatching pattern on sheet C3, the L shaped hatching
adjacent to the managed slopes on C2/C3).
MRY
Rev 3-,-.Putty addressed. Brick hatching still included on E&S control phase II plan
Sheet C17 and the level spreader detail on sheet C18 without callout.
10. [SWPPP] Iiorous reduction results are not consistent between project narrative and VRRM
spreadsheet. The narrative states that phosphorous reduction requirements will be exceeded by 0.3 •
lbs/year,while the VRRM spreadsheet states it will be exceeded by 1.16 lbs/year. Please clarify.
Rev 2—Addressed.
11. [Sheets C4 &C5] Scaling is incorrect, indicated as 1"=30', when scale is actually 1"=20'. Ensure
scales are correct throughout.
Rev 2—Addressed.
Additional Rev 2 Comments:
12. Slopes assessed at<25% cannot be waved unless field survey is performed. Arial survey is
not acceptable as means to re-assess slopes of critical areas. Grading within Critical slope
areas is not permitted.
Rev 3 - Proms k grivi t'✓ Pt"M (sell /MS 5v4,75 *If- Airs /OW” ettliad
CG r"
Additional Rev 3 Comments:
13. Sheet title blocks must be updated to reflect VSMP plan. Currently identify sheets as part of
"Final Construction Plans" and indicate revisions associated with Site plan submittal. Please
correct for final submittal.
14.
I
I
Engineering Review Comments
Page 3 of 6
B. Pollution Prevention Plan(PPP)
The PPP content requirements can be found in County Code section 17-404.
1. No Objection.
C. Stormwater Management Plan(SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is Denied,and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. [General] Provide legible pre and post-construction drainage areas. Drainage areas should relate to
those used on VRRM spreadsheet. Provide on plan sheets,not on separate documents.
Rev 2—Partially addressed. Although overall drainage between the Phase 1 and phase II
projects are presented, not enough information is provided to make a determination of the
adequacy bf water quality computations.It appears that water quality assessment for level
spreader 14,includes areas already accounted for during water quality analysis for level
spreader Please provide assessment of pre and post development drainage areas to level
spreader . Make assessment of effects due to removal of areas used in the assessment of the
water qua ity requirements for Chesterfield landing Phase I and ensure compliance is still
achieved f r phase I following the development of Phase II due to the overlapping of
drainage reas. Ensure drainage areas can be compared to that utilized in the VRRM
spreadshe t for both phases.
Rev 3 -Addressed
2. [General] let/stormsewer sections provided in calculations packet(Structures Bl-B11)are not
identified i the plans.Please indicate their location. •
Rev 2—A dressed.
3. [General] dequate channel must be provided/identified for water discharging from outlet Dl.
Rev 2—A dressed, discharge to level spreader.
4. [Sheet C14 The SWM plan should include an exhibit identifying the indicated 8.14 acres of
conserved s Forest and Open space. The size(in acres)of conserved spaces should also be
provided ai d match that identified on the VRRM spreadsheet. Conserved Forest and Open Space
should be i entified in a separate PLAT with deed and SWM agreement.
Rev 2—Pa tially addressed. Please provide and show Conserved Forest and Open Space
contained n conservation easement. These areas will need to be dedicated within a
stormwate management easement. A stormwater management maintenance agreement,
plat identifying these areas,and deed of dedication will need to be completed prior to VSMP
approval.
Rev 3—Not addressed.Acreages and locations of SWM Forest and Open space Easements
are not included and must be identified on VSMP plan. Subtracting Phase 1 Forest and
open space area from number presented as preserved in the total project(VRRM phase II)
leaves 8.12 acres which does not match the 8.039 acres shown as protected in the
subdivision/easement PLAT. Please explain inconsistencies.
5. [Sheet Cl4]Please include maintenance guidelines for Forest and Open.Space on SWM plan.
Should be formatted in a manner similar to that provided for the level spreader.
Rev 2—Addressed.
6. [Sheet C14] VRRM spreadsheet summary should he provided on the SWM plan sheet.
Rev 2—Addressed.
7. [Sheet C14] Provide sizing and detail of riprap outlet channel conveying stormwater towards level
spreader.
Engineering Review Comments
Page 4 of 6
Rev 2—Addressed.
8. [All] Identify all current and proposed easements, including deed book and page. Include easement
type and widths.
4 Rev 2—Partially Addressed.Level spreader D will need to he inclnded within a SWM
r., eavement.
hRev 3—Partially addressed.Deed book and page references for existing easements not
cs T provided.
.,n
M
[General] Volumes do not appear to match. Volume of runoff from impervious surfaces treated by
level spreader(s)does not match that designated in VRRM spreadsheet, or is not clearly indicated
.V. within drainage maps provided. If runoff is treated by separate level spreader, provide
documentation proving it is designed to handle additional capacity.
Rev 2—Cannot he assessed. See comment Cl above.
Rev 3—Phase 1 and Phase 2 areas in drainage maps and VRRM spreadsheet still contain
inconsistencies.
Additional Rev 2 Comments
10. Computations for level spreader B are missing from calculations packet. Please provide so
that it can be determined if design is sufficient to handle additional volume from Phase II.
Rev 3 -Addressed
Provide detail for level spreader discharging flow from D1. Provide dimensions for level
11. p g g
,ength and width, and provide computations proving adequacy.
Rev 3—Addressed
Additional Rev 3 Comments:
12. In the Stormwater Management section of the E&S narrative [Sheet C151,the amount of
additional SWM credit is incorrectly identified as 1.16 lbs.
13. Easement Plats, Deed of dedication and easement, and SWM agreement must be recorded
[Acknowledged by Engineer,under review].
14.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is Denied, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. [Narrative] Existing site conditions section references the wrong parcel and parcel owner.Please
correct.
Rev 2—Addressed.
2. [Narrative] Soils section contains typos. Please correct
Rev 2—Addressed.
3. [Narrative] Adjacent property section does not contain accurate information. Please revise.
Rev 2—Addressed.
4. [General] Existing grade lines are incorrect. Grading for existing cul-de-sac should be presented as
existing grade.
Rev 2—Addressed.
5. [Sheet C16] Areas receiving temporary seeding and dust control should be identified.
Rev 2—Addressed.
6. [Sheet C16] Provide drainage area acreages to each sediment trap.
Engineering Review Comments
Page 6 of 6
VSMP authority approval. At this time,the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing,this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application,they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued,via the coverage letter,the County can hold a pre-construction conference.
Applicants will need to complete the request for a pre-construction conference form,and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber,and the fee
remaining to be paid. This will be checked by county staff,and upon approval,a pre-construction
conference will be scheduled with the County inspector. At the pre-construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
Bobby Jocz, EIT
Civil Engineer 1
(434)296-5832 ext: 3283
County of Albemarle
Department of Community Development •
401 McIntire Rd.
Charlottesville,VA 22902
Engineering Review Comments
Page 5 of 6
Rev 2 —Addressed.
7. [Sheet C16] Clarify function of structure(appears to be diversion dike)placed along LOD to the
north of the property between sediment traps 1&2.
Rev 2—Addressed.
8. [C16, C17 & C18] No soil divides are provided, or labeled.
Rev 2—Addressed.
9. [Sheet C17] Ensure all symbols are identified in key.
Rev 2—Addressed.
10. [All] a ROW diversion should be provided across the construction entrance.
Rev 2—Addressed.
11. [All] Provide contour elevations.
Rev 2—Addressed.
Additional Rev 2 Comments
h, 12. Temporary grading and construction easements will need to be established for construction
activities occurring on adjacent parcels.
Rev 3—Addressed.
13. Label ROW diversion which crosses existing portion of Oxbow drive.
Rev 3—Addressed.
Additional Rev 3 Comments
14. Review drainage divide presented in phase 1 E&S plan [Sheet C16].It does not appear to
accurately define drainage areas according to presented contours.
15. ( K..S ftr 4rsi 471 OCcpv e ;f 115 bjon,vL 1+ (oeshfre"rJ o,. tat 31 03
etc. d.i$",-g^', .— /br
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re-submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval,plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms,which will need to be completed by the owner
and submitted along with cash,certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP Permit plan review
Project title: Chesterfield Landing II
Project file number: WP0201700024
Plan preparer:
Justin Shimp [Justin@shimp-engineering.com]
Keane Rucker, E.I.T[keane@shimp-engineering.com]
Owner or rep.:
SM Charlottesville [swinkjw@stanleymartin.com]
Plan received date:
Rev 1 — 3rd Mar. 2017
Rev 2 —10' May 2017
Rev 3 — 20' November 2017
Date of comments:
Rev 1 — 301' Mar. 2017
Rev 2 — 5" June 2017
Rev 3 —11" December 2017
Reviewers:
Rev 1 — Bobby Jocz
Rev 2 — Bobby Jocz
Rev 3 — Bobby Jocz
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is approved
conditional on record of Deed of Dedication and Easement Plat for SWM forest and Open
Space. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. [General] Parcel boundaries do not match that available in County records. Referenced deed book
and page for parcel PLAT does not match existing records. Please update, or provide confirmation
regarding parcel boundaries.
Rev 2 — Acknowledged, however the boundary line to the southwest portion of the property
is still in question. Please provide copy of "Unrecorded" Boundary line plat by Roger Ray
and Associates dated July 18', 1996.
Rev 3 — Adequately Addressed.
2. [General] All topography should be field verified by the designer within the last year. Please
provide information on the date of field verification.
Rev 2 — Addressed, field verified by Shimp Engineering May 3rd
3. [General] Disturbed and total project acreage is inconsistent between WPO submittal, registration
statement, and other documentation. Please correct.
Rev 2 — Incomplete. Disturbed area must be updated on Registration statement to reflect
increased disturbed acreage in Phase II (it seems the exact same registration statement, with
updated signature, was submitted from Chesterfield landing Phase 1). In addition, disturbed
acreage still incorrect as presented in E&S narrative [Sheet 15].
Rev 3 — Partially addressed. Disturbed area is not correct on cover sheet. It indicates
Engineering Review Comments
Page 2 of 6
disturbed area as 17.71 acres whereas the registration statement and other documentation
state a disturbance of 7.17 acres.
Rev 3 - Addressed
4. [General] Easement or other form of agreement for working on lots/area outside of property
boundary will be needed.
Rev 2 — Addressed.
5. [General] A mitigation plan will need to be provided for buffer impacts related to construction of
the level spreader.
Rev 2 — Addressed
6. [SWPPP] Signatures must be provided on Registration statement prior to final VSMP approval.
Rev 2 — Addressed
7. [SWPPP] Signatures must be provided on Certification and Delegation of authority forms prior to
land disturbance permit issuance.
Rev 2 — Addressed
8. [Cover sheet] Provide the WPO number, WP0201700024, for the project on the cover sheet and
SWPPP booklet.
Rev 2 — Not provided on the SWPPP booklet. Please provide new cover sheet including
WPO number.
Rev 3 - Addressed
9. [General] label limits of WPO stream buffer, line is provided but not labeled. Ensure all hatching
is included in the key or explicitly labeled, such as shading for Preserved/managed/critical slopes.
Some symbols are not identified (The brick hatching pattern on sheet C3, the L shaped hatching
adjacent to the managed slopes on C2/C3).
Rev 2 — Partially Addressed. Buffer limits outside floodplain are not labeled.
Rev 3 — Partially addressed. Brick hatching still included on E&S control phase II plan
Sheet C17 and the level spreader detail on sheet C18 without callout.
Rev 3 - Addressed
10. [SWPPP] Phosphorous reduction results are not consistent between project narrative and VRRM
spreadsheet. The narrative states that phosphorous reduction requirements will be exceeded by 0.3
lbs/year, while the VRRM spreadsheet states it will be exceeded by 1.16 lbs/year. Please clarify.
Rev 2 — Addressed.
11. [Sheets C4 & C5] Scaling is incorrect, indicated as 1"=30', when scale is actually 1"=20'. Ensure
scales are correct throughout.
Rev 2 — Addressed.
Additional Rev 2 Comments:
12. Slopes assessed at <25% cannot be waved unless field survey is performed. Arial survey is
not acceptable as means to re -assess slopes of critical areas. Grading within Critical slope
areas is not permitted.
Rev 3 - Providing certification/verification for slope
Additional Rev 3 Comments:
13. Sheet title blocks must be updated to reflect VSMP plan. Currently identify sheets as part of
"Final Construction Plans" and indicate revisions associated with Site plan submittal. Please
correct for final submittal.
Addressed
Engineering Review Comments
Page 3 of 6
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
No Objection.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is approved conditional on record of SWM agreement, Deed of Dedication
and Easement Plat for SWM forest and Open Space. The stormwater management plan content
requirements can be found in County Code section 17-403.
[General] Provide legible pre and post -construction drainage areas. Drainage areas should relate to
those used on VRRM spreadsheet. Provide on plan sheets, not on separate documents.
Rev 2 — Partially addressed. Although overall drainage between the Phase 1 and phase II
projects are presented, not enough information is provided to make a determination of the
adequacy of water quality computations. It appears that water quality assessment for level
spreader E includes areas already accounted for during water quality analysis for level
spreader B. Please provide assessment of pre and post development drainage areas to level
spreader B. Make assessment of effects due to removal of areas used in the assessment of the
water quality requirements for Chesterfield landing Phase I and ensure compliance is still
achieved for phase I following the development of Phase II due to the overlapping of
drainage areas. Ensure drainage areas can be compared to that utilized in the VRRM
spreadsheet for both phases.
Rev 3 - Addressed
[General] Inlet/stormsewer sections provided in calculations packet (Structures B 1-B 11) are not
identified on the plans. Please indicate their location.
Rev 2 — Addressed.
[General] Adequate channel must be provided/identified for water discharging from outlet D1.
Rev 2 — Addressed, discharge to level spreader.
[Sheet C14] The SWM plan should include an exhibit identifying the indicated 8.14 acres of
conserved as Forest and Open space. The size (in acres) of conserved spaces should also be
provided and match that identified on the VRRM spreadsheet. Conserved Forest and Open Space
should be identified in a separate PLAT with deed and SWM agreement.
Rev 2 — Partially addressed. Please provide and show Conserved Forest and Open Space
contained in conservation easement. These areas will need to be dedicated within a
stormwater management easement. A stormwater management maintenance agreement,
plat identifying these areas, and deed of dedication will need to be completed prior to VSMP
approval.
Rev 3 — Not addressed. Acreages and locations of SWM Forest and Open space Easements
are not included and must be identified on VSMP plan. Subtracting Phase 1 Forest and
open space area from number presented as preserved in the total project (VRRM phase 11)
leaves 8.12 acres which does not match the 8.039 acres shown as protected in the
subdivision/easement PLAT. Please address.
Addressed
[Sheet C14] Please include maintenance guidelines for Forest and Open Space on SWM plan.
Should be formatted in a manner similar to that provided for the level spreader.
Rev 2 — Addressed.
6. [Sheet C14] VRRM spreadsheet summary should be provided on the SWM plan sheet.
Rev 2 — Addressed.
Engineering Review Comments
Page 4 of 6
7. [Sheet C 14] Provide sizing and detail of riprap outlet channel conveying stormwater towards level
spreader.
Rev 2 — Addressed.
8. [All] Identify all current and proposed easements, including deed book and page. Include easement
type and widths.
Rev 2 — Partially Addressed. Level spreader D will need to be included within a SWM
easement.
Rev 3 — Partially addressed. Deed book and page references for existing easements not
provided.
Addressed
9. [General] Volumes do not appear to match. Volume of runoff from impervious surfaces treated by
level spreader(s) does not match that designated in VRRM spreadsheet, or is not clearly indicated
within drainage maps provided. If runoff is treated by separate level spreader, provide
documentation proving it is designed to handle additional capacity.
Rev 2 — Cannot be assessed. See comment C1 above.
Rev 3 — Phase 1 and Phase 2 areas in drainage maps and VRRM spreadsheet still contain
inconsistencies, as discussed.
Addressed
Additional Rev 2 Comments
10. Computations for level spreader B are missing from calculations packet. Please provide so
that it can be determined if design is sufficient to handle additional volume from Phase II.
Rev 3 - Addressed
11. Provide detail for level spreader discharging flow from D1. Provide dimensions for level
spreader such as Length and width, and provide computations proving adequacy.
Rev 3 — Addressed
Additional Rev 3 Comments:
12. In the Stormwater Management section of the E&S narrative [Sheet C15], the amount of
additional SWM credit is incorrectly identified as 1.16 lbs.
Addressed
13. Easement Plats, Deed of dedication and easement, and SWM agreement must be recorded
[Acknowledged by Engineer, under review].
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. [Narrative] Existing site conditions section references the wrong parcel and parcel owner. Please
correct.
Rev 2 — Addressed.
2. [Narrative] Soils section contains typos. Please correct
Rev 2 — Addressed.
3. [Narrative] Adjacent property section does not contain accurate information. Please revise.
Rev 2 — Addressed.
Engineering Review Comments
Page 5 of 6
[General] Existing grade lines are incorrect. Grading for existing cul-de-sac should be presented as
existing grade.
Rev 2 — Addressed.
[Sheet C 16] Areas receiving temporary seeding and dust control should be identified.
Rev 2 — Addressed.
[Sheet C16] Provide drainage area acreages to each sediment trap.
Rev 2 — Addressed.
7. [Sheet C16] Clarify function of structure (appears to be diversion dike) placed along LOD to the
north of the property between sediment traps 1&2.
Rev 2 — Addressed.
8. [C16, C17 & C18] No soil divides are provided, or labeled.
Rev 2 — Addressed.
9. [Sheet C17] Ensure all symbols are identified in key.
Rev 2 — Addressed.
10. [All] a ROW diversion should be provided across the construction entrance.
Rev 2 — Addressed.
11. [All] Provide contour elevations.
Rev 2 — Addressed.
Additional Rev 2 Comments
12. Temporary grading and construction easements will need to be established for construction
activities occurring on adjacent parcels.
Rev 3 — Addressed.
13. Label ROW diversion which crosses existing portion of Oxbow drive.
Rev 3 — Addressed.
Additional Rev 3 Comments
14. Review drainage divide presented in phase 1 E&S plan [Sheet C16]. It does not appear to
accurately define drainage areas according to presented contours.
Addressed
15. Evaluate locations of traps STI and ST2 as discussed.
Addressed
Please provide 3 copies of the plan sheets and updated inserts for the SWPPP.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
Engineering Review Comments
Page 6 of 6
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
Bobby Jocz, EIT
Civil Engineer 1
(434) 296-5832 ext: 3283
County of Albemarle
Department of Community Development
401 McIntire Rd.
Charlottesville, VA 22902
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP Permit plan review
Project title:
Chesterfield Landing II
Project file number:
WP0201700024
Plan preparer:
Justin Shimp [Justin@shimp-engineering.com]
Owner or rep.:
Lucky Creek LLC. [N/A]
Plan received date:
3rd Mar. 2017
Date of comments:
301 Mar. 2017
Reviewers:
Bobby Jocz
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is Disapproved.
The rationale is given in the comments below. The application may be resubmitted for approval if
all of the items below are satisfactorily addressed. The VSMP application content requirements
can be found in County Code section 17-401.
Note: The resubmittal may result in additional comments due to incompleteness of current
submittal.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. [General] Parcel boundaries do not match that available in County records. Referenced deed book
and page for parcel PLAT does not match existing records. Please update, or provide confirmation
regarding parcel boundaries.
2. [General] All topography should be field verified by the designer within the last year. Please
provide information on the date of field verification.
3. [General] Disturbed and total project acreage is inconsistent between WPO submittal, registration
statement, and other documentation. Please correct.
4. [General] Easement or other form of agreement for working on lots/area outside of property
boundary will be needed.
5. [General] A mitigation plan will need to be provided for buffer impacts related to construction of
the level spreader.
6. [SWPPP] Signatures must be provided on Registration statement prior to final VSMP approval.
7. [SWPPP] Signatures must be provided on Certification and Delegation of authority forms prior to
land disturbance permit issuance.
8. [Cover sheet] Provide the WPO number, WP0201700024, for the project on the cover sheet and
SWPPP booklet.
9. [General] label limits of WPO stream buffer, line is provided but not labeled. Ensure all hatching
is included in the key or explicitly labeled, such as shading for Preserved/managed/critical slopes.
Some symbols are not identified (The brick hatching pattern on sheet C3, the L shaped hatching
adjacent to the managed slopes on C2/C3).
Engineering Review Comments
Page 2 of 3
10. [SWPPP] Phosphorous reduction results are not consistent between project narrative and VRRM
spreadsheet. The narrative states that phosphorous reduction requirements will be exceeded by 0.3
lbs/year, while the VRRM spreadsheet states it will be exceeded by 1.16 lbs/year. Please clarify.
11. [Sheets C4 & C5] Scaling is incorrect, indicated as 1"=30', when scale is actually 1"=20'. Ensure
scales are correct throughout.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. No Objection
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is Disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. [General] Provide legible pre and post -construction drainage areas. Drainage areas should relate to
those used on VRRM spreadsheet. Provide on plan sheets, not on separate documents.
2. [General] Inlet/stormsewer sections provided in calculations packet (Structures B 1-B 11) are not
identified on the plans. Please indicate their location.
3. [General] Adequate channel must be provided/identified for water discharging from outlet D 1.
4. [Sheet C14] The SWM plan should include an exhibit identifying the indicated 8.14 acres of
conserved as Forest and Open space. The size (in acres) of conserved spaces should also be
provided and match that identified on the VRRM spreadsheet. Conserved Forest and Open Space
should be identified in a separate PLAT with deed and SWM agreement.
5. [Sheet C14] Please include maintenance guidelines for Forest and Open Space on SWM plan.
Should be formatted in a manner similar to that provided for the level spreader.
6. [Sheet C14] VRRM spreadsheet summary should be provided on the SWM plan sheet.
7. [Sheet C14] Provide sizing and detail of riprap outlet channel conveying stormwater towards level
spreader.
8. [All] Identify all current and proposed easements, including deed book and page. Include easement
type and widths.
9. [General] Volumes do not appear to match. Volume of runoff from impervious surfaces treated by
level spreader(s) does not match that designated in VRRM spreadsheet, or is not clearly indicated
within drainage maps provided. If runoff is treated by separate level spreader, provide
documentation proving it is designed to handle additional capacity.
D. Erosion and Sediment Control Plan (ESOP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is Disapproved, and the reasons are provided in the comments below. The erosion
control plan content requirements can be found in County Code section 17-402.
1. [Narrative] Existing site conditions section references the wrong parcel and parcel owner. Please
correct.
2. [Narrative] Soils section contains typos. Please correct
3. [Narrative] Adjacent property section does not contain accurate information. Please revise.
4. [General] Existing grade lines are incorrect. Grading for existing cul-de-sac should be presented as
existing grade.
5. [Sheet C16] Areas receiving temporary seeding and dust control should be identified.
6. [Sheet C16] Provide drainage area acreages to each sediment trap.
Engineering Review Comments
Page 3 of 3
7. [Sheet C16] Clarify function of structure (appears to be diversion dike) placed along LOD to the
north of the property between sediment traps 1 &2.
8. [C 16, C 17 & C 18] No soil divides are provided, or labeled.
9. [Sheet C17] Ensure all symbols are identified in key.
10. [All] a ROW diversion should be provided across the construction entrance.
11. [All] Provide contour elevations.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
Bobby Jocz, EIT