HomeMy WebLinkAboutWPO201600064 Review Comments WPO VSMP 2017-02-24 Williams``literprises Incorporated
Land Development Design
TO: Albemarle County
Department of Community Development
amis.
FROM: Robert Williams
SUBJECT: Response to Comments
SDP-2016-00064
Canaan Christian Church
DATE: February 24, 2017
Plat Changes:
1.6dd a SWM definition: SWM = Stormwater Management
V Response: The definition was added as note#15 on sheet 1
2.Add the following note: "The SWM Forest and Open Space Easement is subject
to the guidance set forth by DEQ in the Virginia Stormwater Management
Program. The areas will remain undisturbed in a natural, vegetated state,
except for activities as approved by the local program authority, such as forest
management, control of invasive species, replanting and revegetating, passive
recreation (e.g., trails), and limited bush hogging to maintain desired vegetative
�mmunity (but no more than four times a year)."
esponse: The note was added as note#14 on sheet 1.
3.Hatch the SWM forest & open space easement area. Remove note that says
"hereby dedicated to Albemarle County"
,Response: The SWM Forest& Open Space Easement area was hatched
t/ and "hereby dedicated to Albemarle County" was removed from the
easement label. See sheet 2.
4.Show a SWM facility easement around the two SWM facilities. Remove the
SWM access easement.
Response: The SWM Access Easement was removed and its description
V-removed from the Owner's Consent. A SWM easement was added around
the two SWM facilities and its description added to the Owner's Consent.
See sheets 1 and 2.
P.O. Box 67 Ruby, Virginia 22545 (540)226-1203
we . inc (a� live . corn
SDP-2016-00064 '`4400.
Canaan Christian Church
February 24, 2017
Page 2 of 2
Plan Changes:
1.Add the following note: "The SWM Forest and Open Space Easement is subject
to the guidance set forth by DEQ in the Virginia Stormwater Management
Program. The areas will remain undisturbed in a natural, vegetated state,
except for activities as approved by the local program authority, such as forest
management, control of invasive species, replanting and revegetating, passive
recreation (e.g., trails), and limited bush hogging to maintain desired vegetative
pommunity (but no more than four times a year)."
V Response: The note was added as note#7 on sheet 4.
2.SFjow & hatch the SWM forest & open space easement.
,/Response: The SWM Forest& Open Space Easement area was hatched
and labeled on sheet 4.
3.Show a SWM facility easement around the two SWM facilities. Remove the
SWM access easement.
/Response: The SWM Access Easement was removed and a SWM
easement was added around the two SWM facilities. See sheet 4.
4.Provide 4 copies of the plan.
`/Response: 4 copies of the VSMP plans and the plat have been provided.
P.O. Box 67 Ruby, Virginia 22545 (540)226-1203
we . incRlive . corn
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
VSMP Permit plan review
Project title: Canaan Christian Center
Project file number: WP0201600064
Plan preparer:
Williams Enterprises, Inc.
Owner or rep.:
Canaan Christian Church
Plan received date:
18 Oct 2016
Rev. 1 received date:
22 Dec 2016
Date of comments:
15 Nov 2016
Rev. 1 comments: 01 Feb 2017
Reviewers: Emily Cox
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please provide a signed copy of the certification (Section 9). Rev. 1. Comment addressed.
2. Please note that the notice of general permit coverage (Section 2) and the general permit copy
(Section 11) must be inserted. Rev. 1. Comment addressed.
3. Update any plans sheets which are revised in the next submission. Rev. 1 Comment addressed.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Approved, but update plan sheet with any E&S revisions. Rev. 1 Comment addressed.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. Please combine the SWMP & ESCP into one plan set. It should be called VSMP Submittal and
have the WPO number (201600064) on it. Rev. 1 Comment addressed.
2. Provide calculations for the sizing of the 8" roof drain as well as permanent outlet protection to
prevent erosion. Rev. 1 Comment Addressed.
3. The forest/open space used for VRRM calculations will need to be platted before this plan can be
Engineering Review Comments
Page 2 of 3
approved. Please note that the County Attorney is currently working on a template for a deed to go
with this plat. Rev. 1 Required deed and agreement are provided with this letter. The forest
and open space should be labeled as "SWM forest & open space easement".
4. Please clarify the total areas and types of cover within the drainage divides. The charts on sheets 6,
7 and 9 all have different numbers. Rev. 1 Comment Addressed.
5. There are sheet flow labels on Sheet 8 that don't appear to be pointing towards any Tc path.
Please remove or clarify. Also, there are no Tc paths shown for Drainage Area A. Please provide.
Rev. 1 Comment Addressed.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. The diversion dike on the western end of the site may be changed to silt fence. All diversion dikes
need to be directed to sediment traps or basins. There is not much drainage on this end of the site
and in this case a trap or basin is not necessary. Silt fence will be sufficient. This silt fence should
be included in Phases I and II.
2. Please show silt fence on the eastern end of the site adjacent to the staging and stockpile areas.
This silt fence should be included in Phases I and II.
3. Please show silt fence as well as tree protection on the southern perimeter of the site in Phase II.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
Engineering Review Comments
Page 3 of 3
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle. org/deptforms.asp?department=cdengwno
1/441101 **440,
,z�III4
8F"�®G
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road,Room 227
Charlottesville,Virginia 22902-4596
Phone(434)296-5832 Fax(434)972-4126
VSMP Permit plan review
Project title: Canaan Christian Center
Project file number: WPO201600064
Plan preparer: Williams Enterprises,Inc.
Owner or rep.: Canaan Christian Church
Plan received date: 18 Oct 2016
Date of comments: 15 Nov 2016
Reviewers: Emily Cox
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to
act on any VSMP permit by issuing a project approval or denial. This project is denied. The
rationale is given in the comments below. The application may be resubmitted for approval if all
of the items below are satisfactorily addressed. The VSMP application content requirements can
be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain(1)a PPP, (2)an ESCP, (3)a SWMP, and(4)any TMDL measures necessary.
1. Please provide a signed copy of the certification(Section 9).
2. Please note that the notice of general permit coverage(Section 2)and the general permit copy
(Section 11)must be inserted.
3. Update any plans sheets which are revised in the next submission.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Approved, but update plan sheet with any E&S revisions.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a
SWMP. This plan is disapproved, and the reasons are provided in the comments below. The
stormwater management plan content requirements can be found in County Code section 17-403.
1. Please combine the SWMP&ESCP into one plan set. It should be called VSMP Submittal and
have the WPO number(201600064)on it.
2. Provide calculations for the sizing of the 8"roof drain as well as permanent outlet protection to
prevent erosion.
3. The forest/open space used for VRRM calculations will need to be platted before this plan can be
approved. Please note that the County Attorney is currently working on a template for a deed to go
with this plat.
Engineering Review Comments
Page 2 of 3
4. Please clarify the total areas and types of cover within the drainage divides. The charts on sheets 6,
7 and 9 all have different numbers.
5. There are sheet flow labels on Sheet 8 that don't appear to be pointing towards any Tc path.
Please remove or clarify. Also, there are no Tc paths shown for Drainage Area A. Please provide.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. The diversion dike on the western end of the site may be changed to silt fence. All diversion dikes
need to be directed to sediment traps or basins. There is not much drainage on this end of the site
and in this case a trap or basin is not necessary. Silt fence will be sufficient. This silt fence should
be included in Phases I and II.
2. Please show silt fence on the eastern end of the site adjacent to the staging and stockpile areas.
This silt fence should be included in Phases I and II.
3. Please show silt fence as well as tree protection on the southern perimeter of the site in Phase II.
The VSMP permit application and all plans may be resubmitted for approval when all comments have
been satisfactorily addressed. For re-submittals please provide 2 copies of the complete permit package
with a completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval,plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms,which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing,this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application,they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued,via the coverage letter,the County can hold a pre-construction conference.
Applicants will need to complete the request for a pre-construction conference form, and pay the remainder
Sod
Engineering Review Comments
Page 3 of 3
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre-construction
conference will be scheduled with the County inspector. At the pre-construction conference, should
everything proceed satisfactorily,a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.org/deptforms.asp?department=cdengwpo
Williams terprises Incorporated
Land Development Design
TO: Albemarle County
Department of Community Development
Engineering
Attn: Emily Cox
FROM: Robert Williams
SUBJECT: Response to Comments
SDP-2016-00064
Canaan Christian Church
DATE: December 12, 2016
Requirements:
A.Stormwater Pollution Prevention Plan(SWPPP)
The SWPPP content requirements can be found in County Code section 17-405.A SWPPP must
contain(1)a PPP,(2)an ESCP,(3)a SWMP,and(4)any TMDL measures necessary.
1.Please provide a signed copy of the certification(Section 9).
VResponse: A signed copy of the certification has been added to the
SWPPP. See section 9.
2.Please note that the notice of general permit coverage(Section 2)and the general permit copy
(Section 11)must be inserted.
/Response: The County's notice of general permit was added to the
V SWPPP. See section 2. A copy of the approved general permit issued for
the site will be inserted once received. See section 11.
3.0 to any plans sheets which are revised in the next submission.
esponse: Any revised plan sheets will be updated in the SWPPP.
B.Pollution Prevention Plan(PPP)
The PP content requirements can be found in County Code section 17-404.
.Approved,but update plan sheet with any E&S revisions.
Response: The PPP has been updated with the E&S revisions.
C.Stormwater Management Plan(SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved,and the reasons are provided in the comments below.The stormwater
management plan content requirements can be found in County Code section 17-403.
1.Please combine the SWMP&ESCP into one plan set.It should be called VSMP Submittal and
have the WPO number(201600064)on it.
Rsponse: The two plan sets were combined to create the VSMP
mittal plan set. The plan number WPO-2016-00064 was added to
sheet 1.
P.O. Box 67 Ruby, Virginia 22545 (540)226-1203
we inclive . corn
SDP-2016-00064 *41001sold
• Canaan Christian Church
December 12, 2016
Page 2 of 3
2.Provide calculations for the sizing of the 8"roof drain as well as permanent outlet protection to
prevent erosion.
. response: Pipe capacity computations for the roof drain have been
V provided on sheet 6. Outlet protection was added for the roof drain with
the computations provided on sheet 4.
3.The forest/open space used for VRRM calculations will need to be platted before this plan can be
approved.Please note that the County Attorney is currently working on a template for a deed to
go with this plat.
Response: A plat was prepared to delineate the forest/open space used
0 for the VRRM calculations. The plat is included with the plan sets. A
preliminary copy of the deed document has been completed and provided
with the plat.
4.Please clarify the total areas and types of cover within the drainage divides. The charts on sheets
6, 7 and 9 all have different numbers. / Co.Ce 7 Sl{e al-P--et-
Response:
. -&Response: The VRRM spreadsheet on sheet 7 evaluates the water quality
requirements for the site. Therefore, only the on-site areas are included.
The proposed drainage divides tabulation on sheet 9 lists the proposed
drainage areas which include drainage from Hacktown Road that flows
y/ on-site. Therefore, the drainage from the off-site areas is included for
/ water quantity evaluation purposes. The tabulation on sheet 6 lists the
��V subareas within the overall drainage in order to evaluate each segment of
L the drainage path. The roof drainage area is shown to evaluate the roof
drain, the upstream area of the driveway culvert is shown to evaluate it
and the total area to each level spreader is shown on sheet 6. The
computations use the rational method and profiles/sections are shown on
sheet 5. Please note that the area breakdown and total for each level
spreader(LS#1 and LS#2) on sheet 6 is the same as DA B1 and DA B2 on
sheet 9.
5.There are sheet flow labels on Sheet 8 that don't appear to be pointing towards any Tc path.
Please remove or clarify. Also,there are no Tc paths shown for Drainage Area A.Please
provide.
Response: The erroneous text was deleted. The Tc for Drainage Area 'A'
/ in both the pre and post condition was determined to be sheet flow with
IL less than the minimum of 0.1 hr or 6 min. Therefore, the Tc path was not
shown. The Tc is listed in the Drainage Area tabulation for both the
existing and proposed drainage divides. See sheets 8 and 9.
P.O. Box 67 Ruby, Virginia 22545 (540)226-1203
weinc (a� live . com
SDP-2016-00064 `0 '‘..0/
' Canaan Christian Church
December 12, 2016
Page 3 of 3
D.Erosion and Sediment Control Plan(ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This
plan is disapproved,and the reasons are provided in the comments below. The erosion control plan
content requirements can be found in County Code section 17-402.
I.The diversion dike on the western end of the site may be changed to silt fence.All diversion dikes
need to be directed to sediment traps or basins. There is not much drainage on this end of the
site and in this case a trap or basin is not necessary. Silt fence will be sufficient.This silt fence
should be included in Phases I and II.
Response: The diversion dike was replaced with silt fence and the silt
trap was deleted. The silt trap computation was deleted. The silt fence is
shown in both Phase I and Phase II. References to the diversion dike and
silt trap were deleted from the Erosion and Sediment Control Legend for
Phase I and Phase II. See sheets 16 and 17. The silt trap and diversion
dike details were deleted from the Erosion and Sediment Control Details.
0 See sheet 19. Reference of the diversion dike and silt trap were deleted
from the list of structural practices on the Erosion and Sediment Control
Notes. The Erosion and Sediment Control Escrow estimate was updated
to include the additional silt fence, tree protection, outlet protection and
delete the diversion dike and silt trap. See sheet 18.
2.Please show silt fence on the eastern end of the site adjacent to the staging and stockpile areas.
This silt fence should be included in Phases I and H.
Response: Silt fence was added along the eastern portion of the
development area adjacent to the staging area and stockpile in both
Phase I and Phase II. See sheets 16 and 17.
3.Please show silt fence as well as tree protection on the southern perimeter of the site in Phase H.
V Response: Silt fence and tree protection are shown along the southern
perimeter of the development area in both Phase I and Phase II. See
sheets 16 and 17.
r
P.O. Box 67 Ruby, Virginia 22545 (540)226-1203