HomeMy WebLinkAboutARB201700032 Review Comments Architectural Review Board Approval 2018-03-28 (4)Margaret Maliszewski
From: Margaret Maliszewski
Sent: Tuesday, December 12, 2017 3:36 PM
To: Tayth Hasan'
Subject: RE: Dominion Engineerin - SpringHill/TP - ARB Comment -Response
Layth,
`hanks for sending this along. A few things:
1. Why are 3 poles necessary?
2. You've noted that smaller trees would need to be planted under the power lines, but the poles you've shown
are directly over three trees, so what would the actual planting plan look like for this area?
3. It looks like some other (un-requested) landscape changes have been made. When you make your next
resubmittal, would you please include a list of changes made since the 7/12/17 plan (which corresponds to my
7/28/17 comments)? Also, please include revisions dates on the plans.
Thanks.
Margaret
From: Layth Hasan [mailto:lhasan@dominioneng.com]
Sent: Friday, December 08, 2017 9:27 AM
To: Margaret Maliszewski <MMaliszewski@albemarle.org>
Cc: Mike Myers <mmyers@dominioneng.com>
Subject: RE: Dominion Engineerin - SpringHill/TP - ARB Comment -Response
Margaret,
Good morning,
After a meeting with DOMINION ENERGY yesterday to discuss re locating the existing OH power line, we would like to
make the change ( shown in PDF attached ) to the OH lines, I want to make sure that you are OK with how this change is
going to effect the landscaping at that area, we would have to put DOM POWER approved trees under the line, the
electrical poles showing in PDF are -+40' high.
Please hold off on reviewing the old PDFs sent, we would be making our official 211 submission to the county on Dec 11
anyway.
Thank you and i appreciate your effort and help.
Best,
Layth Hasan
Project Engineer
Dominion Engineering and Design, LLC
172 South Pantops Drive, Charlottesville, VA 22911
434.979.8121 ext.112
From: Layth Hasan
Sent: Thursday, December 07, 2017 10:53 AM
To: 'Margaret Maliszewski'
Cc: Mike Myers
Subject: RE: Dominion Engineerin - 5pringHill/TP - ARB Comment -Response