HomeMy WebLinkAboutWPO201700076 Review Comments WPO VSMP 2018-03-29Phone(434)296-5832
Project title:
Project file
number:
Plan preparer:
Owner or rep.:
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
VSMP Permit plan review
UVAF Temporary Golf Course Connector Road
WP0201700076
Dewberry Engineers
University of Virginia Real Estate
Foundation
Plan received date: Nov 21, 2017
Feb 5, 2018
March 15, 2018
Date of comments: Dec 27, 2017 (Rev. 1)
March 9, 2018 (Rev. 2)
March 29, 2018 (Rev. 3)
Reviewer: David James
Fax(434)972-4126
[dkeeler@dewberry.com]
[cds7c@virginia.edu@virginia.edu]
[dj ames@albemarle. org]
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is approved. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are satisfactorily
addressed. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please add WPO number (WP0201700076) to SWPPP cover sheet.
(Rev.2) Provide copy for review.
(Rev.3) Addressed.
2. Insert copy of General Permit coverage when obtained.
(Rev.2) Acknowledged.
3. (Rev.2) Provide (2) copies of the SWPPP. Please have engineer seal, sign and date each.
(Rev.3) Provide hardcopies for approval. (4) Plans / (2) SWPPPs.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Show proposed construction entrance, staging, stockpile, borrow, fueling, waste disposal,
concrete washout areas on the PPP.
(Rev.2) Please submit for review. Insert PPP `exhibit sheet' into SWPPP book.
(Rev.3) Addressed.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is approved. The stormwater management plan content requirements can be found in County
Code section 17-403.
1. Cover sheet -
a. Add WPO number WPO201700076 to cover sheet title.
(Rev.2) Addressed.
b. Remove signature block from cover sheet.
(Rev.2) Addressed.
2. Provide design details on the `Detention Basin'. Should be sized to handle the design storms.
(Rev.2) Addressed.
3. Provide a level spreader or gravel diaphragm design at end of basin outfall I-4, or extend
the outfall channel protection to the natural channel outfall downstream.
(Rev.2) Addressed.
4. C9.03 Bioretention facility (VADEQ SW Design Spec. 9) -
a. Provide testing of underlying soils - 1 per 1000sf of filter surface (Sect. 6.2).
(Rev.2) Acknowledged; comment still valid.
b. Show filter fabric only on the sides of BMP. Use a layer of coarse washed choker
stone on bottom instead.
(Rev.2) Addressed.
c. Provide a planting plan or template to be used. Specify sources of plant species,
planting sequence including post -nursery care and initial maintenance requirements
(Sect. 6.8).
(Rev.2) Addressed.
d. Include notes on installation. Fig. 9.16 (Sect. 8.2).
(Rev.2) Addressed.
5. C9.04 - Show Tc flow paths with lengths, Tt of each.
(Rev.2) Addressed.
6. Provide profiles of all proposed utilities.
(Rev.2) Acknowledged.
7. Show SWM facility & access easement over all facilities, and associated structures to outfall
{Design Manual, Sect. 5).
(Rev.2) Addressed.
8. Submit an Easement Plat, and Deed of Dedication and Easement for the SWM facilities &
access.
(Rev.2) This must be submitted, reviewed, approved & recorded prior to VSMP plan
approval.
(Rev.3) Addressed.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is approved. The erosion control plan content requirements can be found in County Code
section 17-402.
Please show the steep slopes. Show all existing easements with deed book references, locations &
dims.
(Rev.2) Not Addressed. Show steep slopes along Golf Course Dr.
(Rev.3) Addressed.
2. Provide E&SC details sheet (Paved CE, CD, IP, OP, etc).
(Rev.2) Mostly addressed; Include paved wash rack detail below:
(Rev.3) Addressed.
3. Provide OP shape & stone size calcs (see VADEQ ESC HB Spec. 3.18).
(Rev.2) Addressed.
4. C7.02 — For I-3 use an outlet structure that withdraws water from the surface when
discharging from basins.
(Rev.2) Addressed.
5. Provide low maintenance ground cover where grades are steeper than 3:1.
(Rev.2) Addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this
review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.org/deptforms.asp?department--cdengMo
Phone(434)296-5832
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
VSMP Permit plan review
Project title: UVAF Temporary Golf Course Connector Road
Project file WP0201700076
number:
Plan preparer: Dewberry Engineers
Owner or rep.: University of Virginia Real Estate
Foundation
Plan received date: Nov 21, 2017
Feb 5, 2018
Date of comments: Dec 27, 2017 (Rev. 1)
March 9, 2018 (Rev. 2)
Reviewer: David James (ext. 3273)
Fax(434)972-4126
[dkeeler@dewberry.com]
[cds7c@virginia.edu@virginia.edu]
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are satisfactorily
addressed. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please add WPO number (WP0201700076) to SWPPP cover sheet.
(Rev.2) Provide copy for review.
2. Insert copy of General Permit coverage when obtained.
(Rev.2) Acknowledged.
3. (Rev.2) Provide (2) copies of the SWPPP. Please have engineer seal, sign and date each.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Show proposed construction entrance, staging, stockpile, borrow, fueling, waste disposal,
concrete washout areas on the PPP.
(Rev.2) Please submit for review. Insert PPP `exhibit sheet' into SWPPP book
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved, and the reasons are provided in the comments below. The stormwater
management plan content requirements can be found in County Code section 17-403.
1. Cover sheet -
a. Add WPO number WPO201700076 to cover sheet title.
(Rev.2) Addressed.
b. Remove signature block from cover sheet.
(Rev.2) Addressed.
2. Provide design details on the `Detention Basin'. Should be sized to handle the design storms.
(Rev.2) Addressed.
3. Provide a level spreader or gravel diaphragm design at end of basin outfall I-4, or extend
the outfall channel protection to the natural channel outfall downstream.
(Rev.2) Addressed.
4. C9.03 Bioretention facility (VADEQ SW Design Spec. 9) -
a. Provide testing of underlying soils — 1 per 1000sf of filter surface (Sect. 6.2).
(Rev.2) Acknowledged; comment still valid.
b. Show filter fabric only on the sides of BMP. Use a layer of coarse washed choker
stone on bottom instead.
(Rev.2) Addressed.
c. Provide a planting plan or template to be used. Specify sources of plant species,
planting sequence including post -nursery care and initial maintenance requirements
(Sect. 6.8).
(Rev.2) Addressed.
d. Include notes on installation. Fig. 9.16 (Sect. 8.2).
(Rev.2) Addressed.
5. C9.04 — Show Tc now paths with lengths, Tt of each.
(Rev.2) Addressed.
6. Provide profiles of all proposed utilities.
(Rev.2) Acknowledged.
7. Show SWM facility & access easement over all facilities, and associated structures to outfall
{Design Manual, Sect. 5).
(Rev.2) Addressed.
8. Submit an Easement Plat, and Deed of Dedication and Easement for the SWM facilities &
access.
(Rev.2) This must be submitted, reviewed, approved & recorded prior to VSMP plan
approval.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
Please show the steep slopes. Show all existing easements with deed book references, locations &
dims.
(Rev.2) Not Addressed. Show steep slopes along Golf Course Dr.
2. Provide E&SC details sheet (Paved CE, CD, IP, OP, etc).
(Rev.2) Mostly addressed; Include paved wash rack detail below:
STONE 70' MIN.
CONSTRUCTION
ACCESS -Y SM -2A ASPHALT TOP
/ COURSE EXISTING
27. 27 PAVEMENT
STONE
CONSTRUCTION
ACCESS --\
5" IAN 2'4 BASE
PROFILE
10' MIN.
ASPHALT PAVED
F WASH RACK
2% 1 1 29
2% 12' M?N." +-
'"MUST EXTEND FULL WIDTH POSITIVE DRAINAGE
OF INGRESS AND EGRESS TO SEDIMENT l
OPERATION TRAPPING DEVICE
FILTER CLOTH
EXISTING 1
PAVEMENT)
12' MIN.POSTIVE DRAINAGE
' 2i -ITO SEDIMENT
TRAPPING DEVICE
SECTION A—A
A ntinuntun water tap of 1 inch must be iu tailed with a minimtun 1 inch ballco&
shutoff valve .11pp4ijl, a wash hose w7th a diameter of 1.5 inches for adequate
constant pressure. Wash water crust be car ied away fi-oru the enhance to au
approved settling, area to remove sednnent. dill ,eclitimit shall be prevented h-oui
errternt, storur ch-auis. ditclie., or watercourses.
PAVED WASH RACK
NO SCALE
3. Provide OP shape & stone size cales (see VADEQ ESC HB Spec. 3.18).
(Rev.2) Addressed.
4. C7.02 — For I-3 use an outlet structure that withdraws water from the surface when
discharging from basins.
(Rev.2) Addressed.
5. Provide low maintenance ground cover where grades are steeper than 3:1.
(Rev.2) Addressed.
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this
review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.orgjdeptforms.asp?department--cdengMo
Phone(434)296-5832
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
VSMP Permit plan review
Project title: UVAF Temporary Golf Course Connector Road
Project file WP0201700076
number:
Plan preparer: Dewberry Engineers
Owner or rep.: University of Virginia Real Estate
Foundation
Plan received date: Nov 21, 2017
Date of comments: Dec 27, 2017
Reviewer: David James (ext. 3273)
Fax(434)972-4126
[dkeeler@dewberry.com]
[cds7c@virginia.edu@virginia.edu]
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are satisfactorily
addressed. The VSMP application content requirements can be found in County Code section 17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must
contain (1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Please add WPO number (WP0201700076) to SWPPP cover sheet.
2. Insert copy of General Permit coverage when obtained.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17-404.
1. Show proposed construction entrance, staging, stockpile, borrow, fueling, waste disposal,
concrete washout areas on the PPP.
C. Stormwater Management Plan (SWMP)
VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP.
This plan is disapproved, and the reasons are provided in the comments below. The stormwater
management plan content requirements can be found in County Code section 17-403.
1. Cover sheet -
a. Add WPO number WPO201700076 to cover sheet title.
b. Remove signature block from cover sheet.
2. Provide design details on the `Detention Basin'. Should be sized to handle the design storms.
3. Provide a level spreader or gravel diaphragm design at end of basin outfall I-4, or extend
the outfall channel protection to the natural channel outfall downstream.
4. C9.03 Bioretention facility (VADEQ SW Design Spec. 9) -
a. Provide testing of underlying soils —1 per 1000sf of filter surface (Sect. 6.2).
b. Show filter fabric only on the sides of BMP. Use a layer of coarse washed choker
stone on bottom instead.
c. Provide a planting plan or template to be used. Specify sources of plant species,
planting sequence including post -nursery care and initial maintenance requirements
(Sect. 6.8).
d. Include notes on installation. Fig. 9.16 (Sect. 8.2).
5. C9.04 — Show Tc flow paths with lengths, Tt of each.
6. Provide profiles of all proposed utilities.
7. Show SWM facility & access easement over all facilities, and associated structures to outfall
{Design Manual, Sect. 5).
8. Submit an Easement Plat, and Deed of Dedication and Easement for the SWM facilities &
access.
D. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP.
This plan is disapproved, and the reasons are provided in the comments below. The erosion control
plan content requirements can be found in County Code section 17-402.
1. Please show the steep slopes. Show all existing easements with deed book references,
locations & dims.
2. Provide E&SC details sheet (Paved CE, CD, IP, OP, etc).
3. Provide OP shape & stone size calcs (see VADEQ ESC HB Spec. 3.18).
4. C7.02 — For I-3 use an outlet structure that withdraws water from the surface when
discharging from basins.
5. Provide low maintenance ground cover where grades are steeper than 3:1.
The VSMP permit application and all plans may be resubmitted for approval when all comments have been
satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a
completed application form.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this
review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond
estimate request form and fee to the Department of Community Development. One of the plan reviewers
will prepare estimates and check parcel and easement information based on the approved plans. The
County's Management Analyst will prepare bond agreement forms, which will need to be completed by
the owner and submitted along with cash, certificates or sureties for the amounts specified. The
agreements will need to be approved and signed by the County Attorney and County Engineer. This may
take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the
remainder of the application fee. The form identifies the contractor and responsible land disturber, and
the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
http://www.albemarle.orp,/deptforms.asp?departrnent--cdengMo