HomeMy WebLinkAboutWPO201800023 Review Comments Appeal to BOS 2018-04-27COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, Room 227 Charlottesville, Virginia 22902-4596 Phone (434) 296-5832 Fax (434) 972-4126 VSMP Permit Plan Review Project title: Keswick Hall Energy Plant Demolition and Renovation Project file number: WP0201800023 Plan preparer: Timmons Group, Craig Kotarski, P.E. craig.kotarski@timmons.com Owner or rep.: Historic Hotels of Albemarle, LLC, John Trevenen jtrevenen@keswick.com Plan received date: 27 March 2018 Date of comments: 27 April 2018 Reviewer: WW Associates, Inc. County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the comments below. The VSMP application content requirements can be found in County Code section 17-401. A. Stormwater Pollution Prevention Plan (SWPPP) The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain (1) a PPP, (2) an ESOP, (3) a SWMP, and (4) any TMDL measures necessary. 1. SWPPP Section 1 — Please have the owner execute the Registration Statement Certification (Item 12) and resubmit. Delete instructions for filling out the Registration Statement. 2. SWPPP Section 2 — Please provide a copy of the DEQ coverage when obtained. 3. SWPPP Section 7 — Please add the verbiage from subparagraphs (b) and (c) of 9VAC25-880-70 Part I(B)(4). 4. SWPPP Section 9 — Complete and sign the certification. 5. SWPPP Section 10 — Per 9VAC25-880-70 Part K, provide the person with the authority to sign inspection reports or to modify the stormwater pollution prevention plan. B. Pollution Prevention Plan (PPP) The PPP content requirements can be found in County Code section 17-404. 1. SWPPP Section 6 PPP meets Albemarle County Code Section 17-404 requirements. C. Stormwater Management Plan (SWMP) VSMP Regulation 9VAC25-870-108 requires the VSMP authority to approve or disapprove a SWMP. This plan is disapproved, and the reasons are provided in the comments below. The Stormwater management plan content requirements can be found in County Code section 17-403. 1. Please provide pre- and post -development hydrographs for Water Quantity Analysis Points 1, 2, and 3 and place on the plans. 2. Please provide the pre- and post -development flow path and calculations for all pre- and post - developed drainage areas shown on the plans. 3. Please provide VRRM spreadsheets for Water Quality Analysis and place on the plans. Engineering Review Comments Page 2 of 3 4. Please provide routing of the Bioretention Facility No. 1. 5. Please provide the planting plan and schedule for Bioretention Facility No. 1. 6. Pretreatment of runoff entering Biofilter No. 1 is required. Please provide. 7. Please provide ratio of shortest flow path to overall length calculation and graphically show on the plan. 8. Please note that additional comments may be generated based on response to these comments. D. Erosion and Sediment Control Plan (ESCP) Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan is disapproved, and the reasons are provided in the comments below. The erosion control plan content requirements can be found in County Code section 17-402. 1. Please add WPO201800023 to the cover sheet of the plans and SWPPP. 2. The County's Critical Resource Plan indicates critical slopes within the limits of clearing and grading/limits of disturbance. Please add the critical slopes within the limits of clearing and grading/limits of disturbance to the plan and label whether managed or preserved. 3. Please add limits of clearing and grading/limits of disturbance to demolition Sheet Nos. C2.3 and C2.4. 4. Sheet No. C2.3 - Please add removal/demolition X's to the brick walk to the south of the Energy Plant Building and across the drive aisle. Also, there are removal/demolition X's in the referenced drive aisle. Please identify what is to be demolished/removed or delete these X's from the plan. 5. Sheet No. C2.3 - On the north side of building to be removed/demolished, a note indicates "see arch/map plans for building and utility removal." Please note which impervious surfaces in this area are being removed/demolished and label as such on this plan sheet. 6. Sheet No. C3.1- Silt fence along the southeast side of the swimming pool area is proposed to be installed perpendicular to contours in several locations. Silt fence is to be installed on contour, not across contours. Please place silt fence on tangent parallel to contour or provide other measures to contain E&S. 7. Sheet No. C3.1- Silt fence break is noted as a measure to be provided. This control measure is not a Virginia Erosion and Sediment Control -approved device. Please adjust plan accordingly to depict approved control measures or submit a variation request. 8. Please add TP tree protection symbol to the legend on E&SC Phases I and II plan sheets. 9. The CWD (Clean Water Diversion) is to be released through a stabilized outlet or channel. Please provide a stabilized outlet such as rip -rap outlet protection. 10. It is noted that the Phase I (Sheet No. C3.1) Construction Entrance (CE) is not shown on the Phase II E&SC plan Sheet No. C3.3. CE's are to be provided until County E&S Inspector allows removal. Please adjust Phase II E&SC plan to include Phase I CE. 11. Sheet No. C3.3 - Please show the drip line of the existing tree to remain located just south of the SFB symbol. 12. The narrative on Sheet No. C3.0 under offsite areas states that some utility connections will be offsite. These areas are to be shown if ground is to be disturbed to include erosion and control measures. 13. Please show stockpile location on plan. 14. Please verify that cut or fill balances have a deficit of 10,000 C.Y. or less. 15. Please identify contractor staging/laydown area and parking area. 16. A closed conduit storm drain system is shown on the north side of the energy plant. Please provide inlet protection if these structures are inlets. 17. Please provide outlet control calculations for the rip -rap at structure 600. 18. In accord with VE&SCH Standards and Specifications 3.13 Sediment Traps, the maximum height Engineering Review Comments Page 3 of 3 of the sediment embankment shall be 5 feet as measured from the base of the store outlet (see VE&SCH page I11-73 Embankment Cross -Section and page lIl-74 plate 3.13-1). Sediment trap ST-1 embankment height exceeds this requirement by approximately 5 feet. Please provide an erosion and sediment control measure that meets the VE&SCH requirements for this drainage area. 19. No drainage computations for the closed conduit storm drain system were provided. Please provide storm drain inlet and storm drain pipe calculations as well as drainage area map for the closed conduit storm drain system. The VSMP permit application and all plans may be resubmitted for approval when all comments have been satisfactorily addressed. For re -submittals please provide 2 copies of the complete permit package with a completed application form. Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss this review. Process: After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and check parcel and easement information based on the approved plans. The County's Management Analyst will prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms. Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The County's Management Analyst or other staff will prepare the forms and check for ownership and signature information. The completed forms will need to be submitted along with court recording fees. After bonding and agreements are complete, county staff will need to enter project information in a DEQ database for state application processing. DEQ will review the application information based on local VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid directly to the state. For fastest processing, this is done electronically with the emails provided on the application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the application, they will issue a permit coverage letter. This should be copied to the county. After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference. Applicants will need to complete the request for a pre -construction conference form, and pay the remainder of the application fee. The form identifies the contractor and responsible land disturber, and the fee remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction conference will be scheduled with the County inspector. At the pre -construction conference, should everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that work may begin. County forms can be found on the county website forms center under engineering; httD://www.albemarle.orv/deDtforms.aSD?deDartment--cdenewi)o File: WP0201800023 Keswick Hall Energy Plant Demolition and Renovation 04-27-18.doc