Loading...
HomeMy WebLinkAboutSDP201600045 Review Comments Final Site Plan and Comps. 2017-06-13 Christopher Perez From: Christopher Perez Sent: Thursday, June 01, 2017 11:14 AM To: 'Nena H'; 'Scott Collins' Cc: Frank Pohl;Ana Kilmer Subject: SDP2016-45 Briarwood Recreational Area - final site plan Attachments: RE: SDP201600045 Briarwood Recreational Area - final site plan (BONDING OPTION) Nena/Scott, SUB2016-185 -Briarwood Phase 4 (portion) and phase 6 (portion) - final plat, it is not ready for approval yet. Comments on that plat went out on Dec 16, 2016. The revised 1-4-2017 date you referenced has not been submitted nor reviewed. Whenever you are ready please resubmit the plat and a comment response letter and we will conduct a review on it. One of the largest item remaining is the approval and the bonding of the final site plan for the primary rec area (SDP2016-45). Thus what we need to be focus on are the next steps in the process to approve the final site plan. I emailed you a time line back in Jan(email attached and excerpt provided below, red texts are recent status updates and guidance for what Scott Collins needs to do/update the site plan). See below: The primary recreational area can be bonded once the final site plan is signed/approved by the County. Not yet approved nor bonded. Currently there are numerous large items still outstanding prior to final site plan approval. They are: (1) The easement plat into the site across Ray Beard's property is not yet approved/recorded yet this is approva otherwise they don't have access to the recreational area over Ray's propert Col, Meted/approved/recorded. Recordation information of this action needs to be put on the final site .n for the primary rec area. pit'',to.-a � (2) The road plan for phase 4 which includes the portion of St/. Ives fronting the rec area is not approved/bonded yet - is road plan needs to be finish up Pt bc it is needed to provide access to the recreational area. This road plan needs to be bonded. Ana mer will not return from vacation till tomorrow. Not sure where this project is at in her que to fin ' e/post the bowls P,l�eas w rk with her on this item when she comes back. , (3) The subdivision plat for the recreational area(subdividing it off of the rest of the parcel) is not yet approved this matters bc this plat also records required SWM easements required for the final site plan. This plat also dedicated the land to the HOA and divides it so it's it's own parcel. Completed/approved/recorded 6-1-17. Recordation information of this action needs to be put on the final site plan for the primary rec area. Also, assure Scott updates the parcel boundary lines as the version of the final site plan I have incorrectly depicts the stub that Wendell wanted to subdivide into a lot,which was later determined to be previously dedicated R/W and not part of Briarwood. (4) WP02016-50 is t yet approved and requires the two plats mentioned above and bonding prior to it being approved. This W plan for the rec area needs to be bonded. Ana Kilmer will not return from 3()Y �/ ek1 C-a 1 7 '1r vacation till tomorrow. Not sure where this project is at in her que to finalize/post the bonds. Please work with her when she comes back. Christopher P.Perez Senior Planner Department of Community Development !County of Albemarle,Virginia 401 McIntire Road Charlottesville,VA 22902 434.296.5832 ext.3443 Original Message From: Nena H [mailto:ulcwww@embargmail.com] Sent: Thursday,June 01, 2017 9:43 AM To: Christopher Perez<cperez@albemarle.org> Subject: Re: Rec play I believe the only subdivision plat you are reviewing is Briarwood phase 4?? Nena Harrell Sent from my iPhone >On Jun 1, 2017, at 8:55 AM, Christopher Perez<cperez@albemarle.org>wrote: >What subdivision plat are you referring to? > Original Message > From: Nena H [mailto:ulcwww@embargmail.com] >Sent:Thursday,June 01, 2017 8:51 AM >To: Christopher Perez<cperez@albemarle.org> >Subject: Re: Rec play >Ok thanks. I am planning to post bonds tomorrow. Do you need anything else to sign subdivision plat? > Nena Harrell >Sent from my iPhone >>On Jun 1, 2017, at 8:44 AM, Christopher Perez<cperez@albemarle.org>wrote: » It's ready, come by whenever and record both the plat and the legal doc. » Original Message » From: Nena H [mailto:ulcwww@embarqmail.com] >>Sent: Thursday,June 01, 2017 8:34 AM »To: Christopher Perez<cperez@albemarle.org> >>Subject: Rec play »Chris, can you please advise when I can pick up deed & plat? »Thanks, 2 `.- » Nena Harrell >>Sent from my iPhone 3 Christopher Perez From: Christopher Perez Sent: Monday,January 23, 2017 12:24 PM To: 'Nena Harrell'; 'Scott Collins' Cc: Lisa Green;Amelia McCulley; Megan Brown Subject: RE: SDP201600045 Briarwood Recreational Area - final site plan (BONDING OPTION) Attachments: ZMA200500009 Action Letter.pdf; CD2 SDP201600045 Briarwood Recreational Area - Final Site Plan.pdf Nena/Scott, RE: SDP201600045 Briarwood Recreational Area-final site plan (BONDING OPTION) Attached are the proffers for Briarwood, see proffer#4, excerpt provided below, which provides the bonding option for the improvements associated with the Primary Recreational Area Site Plan. IZMA2005-09 Proffer#4J The primary recreational area shall be built or bonded for its construction prior to final plat approval of phase 4. This recreational area shall be built prior to completion of Phase 4... The primary recreational area can be bonded once the final site plan is signed/approved by the County. Attached is the latest comment letter on the final site plan. Currently there are numerous large items still outstanding prior to final site plan approval. I ggest the items be accomplished in the following order: i The easement plat into the site across Ray Beard's property is not yet approved/recorded yet—t this is needed prior to final site plan appr val otherwise they don't have access to the recreational area over Ray's property. evpi, 2)The road plan for phase 4 which includes the portion of St/. Ives fronting the rec area is nota oved/bonded -this road plan needs to �-.( �� be finish p 1st bc it is needed to provide access to the recreational area. E -,14611 .-CIPS-41— e subdivision plat for the recreational area(subdividing it off of the rest of the parcel)is not yet ap ed—this matters bc this plat also records required SWM easements required for the final site plan.This plat also dedicated the land to the HOA and divides it so it's it's own parcel. -____c_4,01. ____74.----d7-3-e..., WPO is not yet approved and requires the two plats mentioned above and bonding prior to it being-€41,se , I also want to make sure you understand that the primary recreational area must be built before the 26nd certificate of occupancy(which is 50%of the units in phase 4 subdivision plat) [requirement based on Sec. 4.16]. Hope this helps. Christopher P.Perez I Senior Planner Department of Community Development 1County of Albemarle,Virginia 401 McIntire Road 1 Charlottesville,VA 22902 434.296.5832 ext.3443 From: Nena Harrell [mailto:ulcwww@embarqmail.com] Sent: Monday,January 23, 2017 11:09 AM To: Christopher Perez<cperez@albemarle.org> Subject: FW: SUB2016-185_Briarwood Phase 4 and 6- Final Sub Plat Chris, 1 0, s lip fif&I County of Albemarle Department of Community Development 401 McIntire Road, Charlottesville,VA,22902 Phone 434-296-5832 Fax 434-972-4126 Memorandum To: Scott Collins C:eD (D---___(D---________ _From: Christopher P.Perez,Senior Planner Division: Planning Date: January 23,2017 Subject: SDP201600045 Briarwood Recreational Area-final site plan The County of Albemarle Planning Division will recommend approval of the plan referenced above once the following comments have been satisfactorily addressed(The following comments are those that have been identified at this time.Additional comments or conditions may be added or eliminated based on further review.): [Each comment is preceded by the plicable reference,which is to the Subdivision/Zoning Ordinances unless otherwise specified.] 1. [32.7. ,32.5.1(c),32.5.2(i),32.5.2(m)] Vehicular access to the site. The access road,access easement,and gr ng outside of the access easement are proposed on TMP 32E-2,which is owned by Ray Beard. Prior to final to plan approval the easements required to construct the road shall be obtained from Mr. Beard and platted. Easement plats shall be reviewed by the County and then recorded in the Clerk's Office. The DB page information of this action shall be provided on the final site plan. Rev 1: Comment not completely addressed, as the easement plat has not been approved/recorded yet.Comments on the easement plat were sent to the applicant on Dec 12,2016,pending a resubmittal. 2. [32.7 .1,4.6.1,ZMA95-20,ZMA79-32]Prior to final site plan approval the road plan(SUB2016-8) for the new s tion of St. Ives Road shall be approved and built/or bonded.Rev 1: Comment not completely addressed,the road plan appears to be nearing an end as most approvals have been received; however,it is suggested that the approval of the road plan be held off till the easement plat across Ray Beard's property be approved (as this is the document which locks down the entrance location as proposed).Comments on the easement plat were sent to the applicant on Dec 12,2016,pending a resubmittal. 3. [32.7. . ] Vehicular access to site. The entrance onto the public street shall be designed and constructed as re fired by the standards of the Virginia Department of Transportation.VDOT approval of the entrance to the rte shall be required prior to final site plan approval. Rev 1: The road plan for phase 4 which includes the portion of St/.Ives fronting the rec area is not approved/bonded yet-this road plan needs to be finished up be it is needed to provide access to the recreational area.Notably VDOT has provided an approval letter for the entrance as currently designed. 4. [Co ment] The WPO application must be approved prior to final site plan approval. Rev 1: comment still evant.Per conversations with Engineering the plan's approval awaits the easement plats being approved and recorded and then bonding of the WPO plan.For complete list of required WPO plan changes see WPO plan comments from Engineering. we0 ax,is"54) 5. [ZMA2005-09 Proffer#4] The primary recreational area shall be built or bonded for its construction prior to final plat approval of phase 4. This recreational area shall be built prior to completion of Phase 4...71: comment still relevant.The primary recreational area can be bonded once the final site plan is signed/approved by the County.Currently there are numerous large items still outstanding(see below) prior to final site plan approval. 1 The easement •lat into the site across Ra Beard's •ro•e is not et a• •roved/recorded et—this is 1 • t if 7 r v-o-- COMMONWEALTH of VIRGINIA DEPARTMENT OF TRANSPORTATION 1601 Orange Road Culpeper Virgin+a 2270% Charles A. Kilpatrick, P.E. Commissioner November 8, 2016 County of Albemarle Department of Community Development 401 McIntire Road Charlottesville, VA 22902 Attn: Christopher Perez Re: Briarwood Recreational Area— Final Site Plan SDP-2016-00045 Review#3 Dear Mr. Perez: The Department of Transportation, Charlottesville Residency Transportation and Land Use Section, has reviewed the above referenced plan as submitted by Collins Engineering, most recently revised 6 October 2016, and find it to be generally acceptable. This office will sign the plans upon review of the appropriate signed and sealed approval copies. Please allow for this office to obtain two signature copies. A VDOT Land Use Permit will be required prior to any work within the right-of-way. The owner/developer must contact the Charlottesville Residency Transportation and Land Use Section at (434) 422-9399 for information pertaining to this process. If further information is desired please contact Justin Deel at (434)422-9894. Sincerely, (1444K4 tA.A Adam J. Moore, P.E. Area Land Use Engineer Charlottesville Residency VirginiaDOT.org WE KEEP VIRGINIA MOVING Review Comments for JP201600045 , Project Name: Briarwood Recreation Area - Final Date Completed: Tuesday, November 01 , 2016 Department/Division/Age eviewer: Matthew Wentland CDD Enaineerina . The VSMP submittal will need to be approved before site plan approval. r It is currently under review and near approval. -�--P j- . , A 2. loodplain Development Permit applicaion will be required [18.30.3.12(A)]. is should contain a floodplain impact plan demonstrating that the grading will have no impact on the elevations or limits of the floodplain [18.30.3.11] and a signed and sealed 'No Rise' certification. These items are currently under review. ;5' COLLINS24GARRETT ST, SUITE K CHARLOTTESVILLE VA 22902 434.293.3719 PH 434.293.2813 FX www.collins-engineering.com October 20,2016 Christopher Perez Senior Planner Department of Community Development 401 McIntire Road Charlottesville,VA 22902 RE: SDP2016-00025—Briarwood Recreation Area Final site plan Thank you for your comments dated September 9,2016 on the above-referenced project. The updated plans reflect changes to address your comments as described below: Planning Co ants: 1. T e location and approval of the access easement through Mr. Beard's property has been resolved. Mr. Beard,the County,and VODT are acceptable with the new location. In addition,we have included the grading on Mr. Beard's property for the tie-in of the roadway to his property. Mr. Beard has accepted this as well. He will be signing an easement document giving United Land the ability to grade across the entire parcel,as necessary. The sight distance easements have been added to the access easement plat. In addition,the label of the access easement has been updated,as requested. 2. Comment addressed. 3. Comment addressed. ymment addressed. knowledged. This portion of St. Ives Road is part of the approval and bonding for Phase 4 road ns. 6 The VDOT entrance to the primary recreation area has been added to the Phase 4 road plans for review and approval. 7. Comment addressed. 8. Commen ddressed. 9. Co ent addressed. 1 he proposed chain link fence stretches along the entire southern area of the site serving as tection from the recreation area to the river. . omment addressed. 1 . The general information has been updated to add in the requested info. ▪ The landscaping plan has been updated as requested. 14. Comment addressed. 15. Comment addressed. 16. Comment addressed. 17. Comment addressed. 18. Co ant addressed. 19. ote has been added to the front sheet about the requirements of the HOA to service these trash re eptacles once a week at minimum. 20. C mment addressed. 1. he pedestrian pathway location has been updated to not continue around the SWM facilty. 22. cknowledged. The WPO has been updated for approval. 23. Comment addressed. *sio's 0cauljvw levA 24. Acknowledged. 25. Project number on title sheet has been updated. Engineering: 1. The VSMP plan has been resubmitted for approval. 2. A floodplain development permit application has been included with the submittal for approval. In addition,a no rise certification has also been included. VDOT 1. The sight distance easement has been added to the access easement plat for recordation. Zoning,Building,ACSA,RWSA,E911,ARB,and Fire/Rescue 1. All comments previously addressed, plan is ready for approval by these agencies. Should you have any questions, please feel free to contact me at 434-293-3719. Sinc ely, S ott Collins Collins Engineering Christopher Perez From: Christopher Perez Sent: Tuesday,January 17, 2017 4:03 PM To: Lisa Green Cc: Megan Brown;Amelia McCulley Subject: Briarwood - Recreational Area (BONDING OPTION) Attachments: ZMA200500009 Action Letter.pdf Lisa, RE: Briarwood-Recreational Area (BONDING OPTION) Nena has been asking around about bonding for the recreational area and I've been meaning to speak to Zoning about it. Attached are the proffers for Briarwood, see proffer#4, excerpt provided below, which provides the bonding option for the improvements associated with the Primary Recreational Area Site Plan. Is bonding of an entire site plan truly feasible? I hope so bc that the option provided for in the proffer and the route Nena wants to go. [ZMA2005-09 Proffer#4] The primary recreational area shall be built or bonded for its construction prior to final plat approval of phase 4. This recreational area shall be built prior to completion of Phase 4... While the recreational area final site plan may appear to be nearing an end, it has a bunch of loose ends which must be completed b4 approval. I'll list a few of the big ticket items: (1) The road plan for phase 4 which includes the portion of St/. Ives fronting the rec area is not approved/bonded yet -this road plan needs to be finished up 1St bc it is needed to provide access to the recreational area. (2) The easement plat into the site across Ray Beard's property is not yet approved/recorded yet—this is needed prior to final site plan approval otherwise they don't have access to the recreational area over Ray's property (3) The subdivision plat for the recreational area(subdividing it off of the rest of the parcel) is not yet approved—this matters bc this plat also records required SWM easements required for the final site plan. This plat also dedicated the land to the HOA and divides it so it's it's own parcel. (4) WPO is not yet approved and requires the two plats mentioned above and bonding prior to it being approved. Hope this helps. Christopher P. Perez Senior Planner Department of Community Development County of Albemarle, Virginia 401 McIntire Road 1 Charlottesville,VA 22902 434.296.5832 ext. 3443 1 COLLINS ! • 200 GARRETT ST,SUITE K CHARLOTTESVILLE VA 22902 434.293.3719 PH 434.293.2813 EX www.collins-engineering.com October 20,2016 Christopher Perez Senior Planner Department of Community Development 401 McIntire Road Charlottesville,VA 22902 RE: SDP2016-00025—Briarwood Recreation Area Final site plan Thank you for your comments dated September 9,2016 on the above-referenced project. The updated plans reflect changes to address your comments as described below: Planning Comments: 1. The location and approval of the access easement through Mr. Beard's property has been resolved. Mr. Beard,the County,and VODT are acceptable with the new location. In addition,we have included the grading on Mr. Beard's property for the tie-in of the roadway to his property. Mr. Beard has accepted this as well. He will be signing an easement document giving United Land the ability to grade across the entire parcel,as necessary. The sight distance easements have been added to the access easement plat. In addition,the label of the access easement has been updated,as requested. 2. Comment addressed. 3. Comment addressed. 4. Comment addressed. 5. Acknowledged. This portion of St. Ives Road is part of the approval and bonding for Phase 4 road plans. 6. The VDOT entrance to the primary recreation area has been added to the Phase 4 road plans for review and approval. 7. Comment addressed. 8. Comment addressed. 9. Comment addressed. 10. The proposed chain link fence stretches along the entire southern area of the site serving as protection from the recreation area to the river. 11. Comment addressed. 12. The general information has been updated to add in the requested info. 13. The landscaping plan has been updated as requested. 14. Comment addressed. 15. Comment addressed. 16. Comment addressed. 17. Comment addressed. 18. Comment addressed. 19. A note has been added to the front sheet about the requirements of the HOA to service these trash receptacles once a week at minimum. 20. Comment addressed. 21. The pedestrian pathway location has been updated to not continue around the SWM facilty. 22. Acknowledged. The WPO has been updated for approval. 23. Comment addressed. 24. Acknowledged. 25. Project number on title sheet has been updated. Engineering: 1. The VSMP plan has been resubmitted for approval. 2. A floodplain development permit application has been included with the submittal for approval. In addition,a no rise certification has also been included. VDOT 1. The sight distance easement has been added to the access easement plat for recordation. Zoning,Building,ACSA,RWSA,E911,ARB,and Fire/Rescue 1. All comments previously addressed,plan is ready for approval by these agencies. Should you have any questions, please feel free to contact me at 434-293-3719. Sinc ely, S ott Collins Collins Engineering