HomeMy WebLinkAboutWPO201600071 Inspection 2018-06-06Q
}:
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-6832 Fax (434) 972-4126
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
Belvedere Phase IIB
ProjectlWPO Number:
WP02016-00071
Project Address:
Belvedere Blvd
DEQ Permit Number (if
applicable):
VAR10K606
Project Operator:
AG Dillard Inc
Operator Telephone #:
434-977-3750
Project Contact:
DJ Banton
Contact Telephone #:
434-293-3719
Contact E-Mail:
djacagdillard.com
Qualified Personnel (QP):
Tom Paquette— RLD02008
Inspector:
p
Jonne Otto
y
Weather (Wet/Dry/Rain)-
>'
T
Disturbed Acreage:
7.66
Inspection Date & Time:
;
Single -Family: ❑ Yes [;INo
Stage of Construction: Pre -Construction Meeting LJ Initial Clearing & Grading LJ
ff Building Construction ❑ Final Grading ❑ Construction of SWM Facilities
❑ Notice of Termination ❑ Other:
Rough Grading
❑ Final Stabilization
Re -Inspection:
❑ Yes LNo
COVERAGE & POSTING REQUIREMENTS
Yes
No
N/A
Reviewed during re- inspection? eyes []No
ConrmentslDescrip6on
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
%
main entrance of the construction activity? (CGP Part I I.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
/
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS
Yes
No
N/A
Reviewed during re -inspection? []Yes Ylo
CommentslDescriptlon
4
The SWPPP is on -site or made available during the inspection? (CGP
/
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A.1.b & c)
Page 1 of 7
The SWPPP includes a narrative description of the nature of the
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
The SWPPP includes a legible site plan identifying all appropriate
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9
The SWPPP contains the name, phone number and qualifications of
"Qualified
Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
f
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.13 ❑ ILC ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.S (a-b))
14
Delegation of Authority is provided and signed in accordance with Part III
d
K? (CGP Part II A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Part
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES Yes
No N/A Reviewed during inspection? ❑YeseNo
Comments/Desci 1ption
Is the SWPPP being amended whenever there is a change in the design,
16
nstruction, operation, or maintenance that has a significant effect on the
ischarge of pollutants to surface waters? (CGP Part II B(1))(9VAC25-870-
G)
Has the SWPPP been amended if inspections or investigations by the
f
17
perator's qualified personnel, or by local, state or federal officials find that
xisting control measures are ineffective in minimizing pollutants in
ischarges? (CGP Part II B(2))(9VAC25-870-54.G)
18
ontractor(s) that will implement and maintain each control measure are
/
identified? (CGP Part II B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
mplementation have occurred, including a record of dates when major
19
grading activities occur, construction activities temporarily or permanently
cease on a portion of the site or stabilization measures are initiated? (CGP
Part II B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
`
(CGP Part II B.4(b))(9VAC25-870-54.G)
2i
Is the SWPPP updated to indicate areas that have reached final
tabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22
egal control of the operator and the dates on which the operator no longer
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
.G)
Does the SWPPP identify the date of any prohibited discharges, the
Volume released, actions taken to minimize the impact of the release
23
and
measures taken to prevent the recurrence of any prohibited discharge?
CGP Part II B.4(e-0) (9VAC25-870-54.G)
24
Amendments, modifications, or updates to the SWPPP are signed in
accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS Yes No N/A I Reviewed during inspection? []Yes 17JNo
Comments/Description
Page 2 of 7
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part it F (2))
(CGP Part II A.5.b.3)
26
Inspection reports are completed and signed in accordance with CGP
Part II F (3-4)? (CGP Part II F (3-4))
Q
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part li G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Yes No N/A Reviewed during inspection?�es []No
Comments/Descrlption
28
Have stream buffers and steep slopes been protected as shown on the
plan?
Sequencing of the project is implemented in accordance with the
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
been stabilized, and have stabilization requirements for impaired waters,
30
approved TMDL(s), pollutants of concern and exceptional waters, when
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part li
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
/
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54. B)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part 11
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
38
Is adequate drainage or other protection provided for water seeps?
(9VAC 25-840-40.9) (CGP Part If A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP If E(1-2)) (9VAC25-870-
/
54.B)
Are stormwater conveyance channels adequately stabilized with channel
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in -stream construction conducted using measures to minimize channel
41
damage? (9VAC 25-840-40.12) (CGP Part 11 A.2(c)) (CGP II E(1-2))
!�
(9VAC25-870-54. B)
Are temporary stream crossings of non -erodible material installed where
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
43
Is necessary restabilization of in -stream construction complete? (9VAC
25-840-40,15) (CGP 11 E(1-2)) (9VAC25-870-54.B)
Page 3 of 7
Are utility trench operations conducted and stabilized in accordance with
44
MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
/
(9VAC25-870-54. B)
Are soil and mud kept off paved or public roads to minimize the transport
45
of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.8)
!
Have all temporary control structures that are no longer needed been
46
removed and disturbed soil resulting from their removal permanently
C k rr aAtf�
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
/
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Yes No N/A Reviewed during inspection? ❑YesANo
Comments/Descriptfon
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
/
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part 11 A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
%
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part 11
A.4.e (2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
/
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
S
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak -proof container or leak -proof
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part 11 A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
56
pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
hspector Signature: 4j'�0.
Date:l,�f
Page 4 of 7
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-6832 Fax (434) 972-4126
VSMPNESCP PERMIT SITE INSPECTION REPORT
Project Name:
Belvedere Phase IIB
ProjectfWPO Number:
WP02016-00071
Project Address:
Belvedere Blvd
DEQ Permit Number (if
applicable):
VAR10K606
Project Operator:
AG Dillard Inc
Operator Telephone #:
434-977-3750
Project Contact:
DJ Banton
Contact Telephone #:
434-293-3719
Contact E-Mail:
dj@agdillard.com
Qualified Personnel (QP):
Tom Paquette — RLD02008
Inspector:
Jonney Otto
Weather (Wet/Dry/Rain):
Disturbed Acreage:
7.66
Inspection Date & Time:
Single -Family: ❑ Yes ZNo
Stag of Construction: Pre -Construction Meeting
Building Construction ❑ Final Grading ❑
❑ Notice of Termination ❑ Other:
Initial Clearing & Grading
Construction of SWM Facilities
Rough Grading
❑ Final Stabilization
Re -Inspection:
❑ Yes ZNo
COVERAGE & POSTING REQUIREMENTS
Yes
No
WA
Reviewed during re -inspection? Yes ❑No
Comments/Descripdon
1
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-870-310)(Alb. Co. Code §17-300, 17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part 11 D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS
Yes
No
N/A
Reviewed during re -inspection? ❑YesONo
Comments/Descrip6on
4
The SWPPP is on -site or made available during the inspection? (CGP
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part 11 A.1.b & c)
Page 1 of 7
The SWPPP includes a narrative description of the nature of the
7
construction activity, including the function of the project? (CGP Part II
A.1.d)
The SWPPP includes a legible site plan identifying all appropriate
/
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9
The SWPPP contains the name, phone number and qualifications of
"Qualified
Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.113 ❑ ILC ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.D)(CGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
13
concern, exceptional waters and the additional controls measures
%
applicable? (9VAC 25-870-54.E)(CGP Part IIA.S (a-b))
14
Delegation of Authority is provided and signed in accordance with Part I II
K? (CGP Part II A.7)
15
The SWPPP is signed and dated in accordance with Part III K? (CGP Parl
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Yes No N/A Reviewed during inspection? []Yes )Vo
Comments/Descripgon
Is the SWPPP being amended whenever there is a change in the design,
16
nstruction, operation, or maintenance that has a significant effect on the
ischarge of pollutants to surface waters? (CGP Part It B(1))(9VAC25-870-
G)
Has the SWPPP been amended if inspections or investigations by the
17
perator's qualified personnel, or by local, state or federal officials find that
S
xisting control measures are ineffective in minimizing pollutants in
ischarges? (CGP Part II B(2))(9VAC25-870-54.G)
18
ontractor(s) that will implement and maintain each control measure are
identified? (CGP Part II B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
mplementation have occurred, including a record of dates when major
18
grading activities occur, construction activities temporarily or permanently
0
cease on a portion of the site or stabilization measures are initiated? (CGP
Part II B.4(a))(9VAC25-870-54.G)
20
Is there documentation in the SWPPP of replaced or modified controls?
CGP Part 11 B.4(b))(9VAC25-870-54.G)
r✓
21
Is the SWPPP updated to indicate areas that have reached final
stabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
22 legal
control of the operator and the dates on which the operator no longer
had legal control over each property? (CGP Part II B.4(d))(9VAC25-870-
G)
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
✓,
measures taken to prevent the recurrence of any prohibited discharge?
(CGP Part II BA(e-f)) (9VAC25-870-54.G)
24
Amendments, modifications, or updates to the SWPPP are signed in
accordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Yes No N/A I Reviewed during inspection? []Yes No
Comments/Descriptiorn
Page 2 of 7
Inspections required by the SWPPP are conducted at the required
25
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part II A.5.b.3)
26
Inspection reports are completed and signed in accordance with CGP
Part II F (3-4)? (CGP Part II F (3-4))
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part li G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Yes No N/A Reviewed during inspection? 01 es []No
Comments/Descrfptfon
28
Have stream buffers and steep slopes been protected as shown on the
plan?
Sequencing of the project is implemented in accordance with the
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
c:,,- cyp t+�r�
been stabilized, and have stabilization requirements for impaired waters,
TMDL(s),
30
approved pollutants of concern and exceptional waters, when
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25
/ ��
880-60) (CGP Part I FA (a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part li
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
C�\^Si-f_tALh�+
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP it E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
/
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
34
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-
54.6)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part 11 A.2.c (9)) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Are finished cut and fill slopes adequately stabilized to prevent or correct
36
excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
/
2)) (9VAC25-870-54.13)
Is concentrated runoff down cut or fill slopes contained in an adequate
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part I I
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
38
(9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-
54.13)
Are stormwater conveyance channels adequately stabilized with channel
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP 11 E(1-2)) (9VAC25-870-54.B)
41
Is in -stream construction conducted using measures to minimize channel
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.8)
Are temporary stream crossings of non -erodible material installed where
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP 11 E(1-2))
(9VAC25-870-54. B)
43
Is necessary restabilization of in -stream construction complete? (9VAC
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.8)
Page 3 of 7
Are utility trench operations conducted and stabilized in accordance with
44 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
Are soil and mud kept off paved or public roads to minimize the transport
45 of sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
Have all temporary control structures that are no longer needed been
46 removed and disturbed soil resulting from their removal permanently
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
Are properties and waterways downstream from development adequately
47 Protected from erosion, sediment and damage in accordance with the
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48 Permanent control measures included in the SWPPP are in place?
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Yes
No
N/A
Reviewed during inspection? VYes []No
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49 and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
50 and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e (2))(9VAC25-870-56)
Practices are in place to prevent the discharge of soaps, solvents,
51 detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52 and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53 Concrete wash water is directed into a leak -proof container or leak -proof
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54 storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part it A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55 petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
56 pollutant -generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
hspector Signature: Zani4_Q� Date: %if i%
Page 4 of 7
rz
COUNTY OF ALBEMARLE
Department of Community Development
VSMP/VESCP PERMIT SITE INSPECTION REPORT
Project Name:
✓z /l `
ProjectlWPO Number:
-00t77/
Project Address:
Reviewed during re-inspection?;31es ❑No
DEQ Permit Number (if
applicable):
VAR (® J
g a
Project Operator:ckc
Operator Telephone #:
_ _�4I • ` �Z
Project Contact:
4
Contact Telephone #:
4 34 L 2�
Contact E -Mail:
Qualified Personnel (QP):
(9VAC25-870-310)(Alb. Co. Code §17-300,17-302)
Inspector:
�C1.1Q LJZ/.e�
Weather(WetlDry/Rain):
Disturbed Acreage:
5r, L`
Inspection Date & Time:
0 0 V6
Single -Family: ❑ Yes No
Stage of Construction: H Pre -Construction Meeting LJ Initial Clearing & Grading LZRough
❑ Building Construction ❑ Final Grading ❑ Construction of SWM Facilities
❑ Notice of Termination ❑ Other:
Grading
❑ Final Stabilization
Re -Inspection:
❑ Yes No
Page 1 of 7
COVERAGE & POSTING REQUIREMENTS
yes
No
N/A
Reviewed during re-inspection?;31es ❑No
Comments/Descdpdon
9
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-870-310)(Alb. Co. Code §17-300,17-302)
2
A copy of the notice of coverage letter is posted conspicuously near the
main entrance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
3
applicable, and information for public access is provided? (9VAC25-870-
54.G)(CGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS
Yes
No
N/A
Reviewed during reinspection? []Yes Rio
Comments/Descripr/on
4
The SWPPP is on-site or made available during the inspection? (CGP
Part II D.1 & 2)(9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part II A.1.a)
6
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A. 1.b & c)
The SWPPP includes a narrative description of the nature of the
7
construction activity, including the function of the project? (CGP Part II
AAA)
Page 1 of 7
Page 2of7
The SWPPP includes a legible site plan identifying all appropriate
!
8
measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9
The SWPPP contains the name, phone number and qualifications of
"Qualified Personnel" conducting inspections? (CGP Part II A.6)
10
The SWPPP contains an approved erosion and sediment control plan?
(9VAC25-870-54.B)(CGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
11
existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria 11.6 ❑ ILC ❑
12
The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.DXCGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
r
13
concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.E)(CGP Part IIA.S (a -b))
Delegation of Authority is provided and signed in accordance with Part III
/
14
K? (CGP Part 11 A.7)
The SWPPP is signed and dated in accordance with Part III K? (CGP Pa
15
11 A.8) i
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Yes No N/A Reviewed during inspection? ❑Yes,;40
Co mm e n ts/Descripfio n
Is the SWPPP being amended whenever there is a change in the design,
16
construction, operation, or maintenance that has a significant effect on the
discharge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
!
54.G)
Has the SWPPP been amended if inspections or investigations by the
!
17
qualified personnel, or by local, state or federal officials find that
.
�perators
xisting control measures are ineffective in minimizing pollutants in
ischarges? (CGP Part 11 B(2)x9VAC25-870-54.G)
!
18
Contractor(s) that will implement and maintain each control measure are
identified? (CGP Part II B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
implementation have occurred, including a record of dates when major
19
grading activities occur, construction activities temporarily or permanently
ase on a portion of the site or stabilization measures are initiated? (CGP
Part 11 13.4(a))(9VAC25-870-54.G)
i
20
Is there documentation in the SWPPP of replaced or modified controls?
CGP Part 11 B.4(b))(9VAC25-870-54.G)
21
Is the SWPPP updated to indicate areas that have reached final
tabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
i
lIs the SWPPP updated to indicate properties that are no longer under the
!
22
egal control of the operator and the dates on which the operator no longer
ad legal control over each property? (CGP Part 11 B.4(d))(9VAC25-870-
i
4.G)
I
Does the SWPPP identify the date of any prohibited discharges, the
23
volume released, actions taken to minimize the impact of the release and
measures taken to prevent the recurrence of any prohibited discharge?
l
CGP Part 11 B.4(e-f)) (9VAC25-870-54.G)
24
Amendments, modifications, or updates to the SWPPP are signed in
III
accordance with Part III K? (CGP Part 11 B(5))(9VAC25-870-54.G)
!
INSPECTIONS AND CORRECTIVE ACTIONS
Yesl No'N/A Reviewed during inspection? []Yes &No
Comments/Description
Inspections required by the SWPPP are conducted at the required
25
I frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part 11 F (2))
(CGP Part 11 A.5.b.3)
Page 2of7
Page 3 of 7
Inspection reports are completed and signed in accordance with CGP
110
.11
26
Part II F (3-4)? (CGP Part II F (3-4))
27
Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Yes
No
Af/A
Reviewed during inspection? [Yes []No
Comments/De=dptfon
28
Have stream buffers and steep slopes been protected as shown on the
plan?
Sequencing of the project is implemented in accordance with the
29
approved erosion and sediment control plan and stormwater management
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
been stabilized, and have stabilization requirements for impaired waters,
30
approved TMDL(s), pollutants of concern and exceptional waters, when
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25
880-60) (CGP Part I F.1 (a)) (CGP Part II A.5.b(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
31
with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.13)
A permanent vegetative cover has been established that is uniform,
32
mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.13)
Have sediment trapping facilities been constructed as the first step in land
33
disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
%
E(1-2)) (9VAC25-870-54.B)
34
Have earthen structures been stabilized immediately after installation?
(9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
/
54.6)
Are sediment traps and basins installed in accordance with MS-6 and the
35
approved plan? (9VAC 25-840-40.6) (CGP Part I I A.2.c (9)) (CGP Part I I
/
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.8)
36
Are finished cut and fill slopes adequately stabilized to prevent or correct
excessive erosion? (9VAC 25,84040.7) (CGP Part 11 A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.B)
Is concentrated runoff down cut or fill slopes contained in an adequate
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.6)
Is adequate drainage or other protection provided for water seeps?
38
(9VAC 25-840-40.9) (CGP Part 11 A.2(c)) (CGP II E(1-2)) (9VAC25-870-
/
54.13)
Do all operational storm sewer inlets have adequate inlet protection?
39
(9VAC 25-84040.10) (CGP Part II A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-
/
54.13)
Are stormwater conveyance channels adequately stabilized with channel
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.B)
Is in-stream construction conducted using measures to minimize channel
�J
41
damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
/
(9VAC25-870-54.B)
Are temporary stream crossings of non-erodible material installed where
42
applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
43
Is necessary restabilization of in-stream construction complete? (9VAC
25-840-40.15) (CGP II E(1-2)) (9VAC25-870-54.B)
Are utility trench operations conducted and stabilized in accordance with
44
MS-167 (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.13)
Are soil and mud kept off paved or public roads to minimize the transport
/
45
of sediment? (9VAC 25-840-40.17) (CGP Part 11 A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.B)
Page 3 of 7
Inspector Signature:
Page 4 of 7
Date:
Have all temporary control structures that are no longer needed been
46
removed and disturbed soil resulting from their removal permanently
stabilized? (9VAC 25-840-40.18) (CGP Part 11 A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.B)
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
I
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48
Permanent control measures included in the SWPPP are in place?
/
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Yes
No
N/A
Reviewed during inspection? ❑YeSIONo
Comments/Description
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
50
Practices are in place to prevent the discharge of spilled and leaked fuels
and chemicals from vehicle fueling and maintenance activities? (CGP Part I I
A.4. e(2))(9VAC25-870-56 )
Practices are in place to prevent the discharge of soaps, solvents,
I
I
51
detergents, and wash water from construction materials, including the
Glean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part 11 A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part 11 A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak-proof container or leak-proof
j
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
54
Practices are in place to minimize the discharge of pollutants from
storage, handling, and disposal of construction products, materials, and
€
,r
i
I
wastes? (CGP Part II A.4.e(6)X9VAC25-870-56)
i
Practices are in place to prevent the discharge of fuels, oils, and other
1
I
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
/
56
pollutant-generating activities not addressed above, when applicable?
(CGP Part II A.4.e(8))(9VAC25-870-56)
Inspector Signature:
Page 4 of 7
Date:
Notes:
CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT
REQUEST FOR CORRECTIVE ACTION
Project Name: Permit Number (if applicable): Date:
' Refers to applicable regulation found In the most recent publication of the State Water Control Law (Va. Code § 62.1.44.2 et seq.), Virginia Eroslon and
Sediment Control Regulations (gVAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Construction Activities (9VAC25-880).
Page 5 of 7
atony
Regulato ry
Occurrence
Observation[Recommended Corrective Action
Checklist #
CRegu
requirement'
Observation:
Recommended CorrectW Actbn
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Acdon:
Observation:
Recommended Corrective Action:
' Refers to applicable regulation found In the most recent publication of the State Water Control Law (Va. Code § 62.1.44.2 et seq.), Virginia Eroslon and
Sediment Control Regulations (gVAC25-840), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Construction Activities (9VAC25-880).
Page 5 of 7
Recommended Corrective Action Deadline:
Tar eted Re -inspection Date:
Comments:
The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently
constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for
ensuring compliance on the above project
Inspector Signature:
Page 6 of 7
Date.-
Page
ate:
COUNTY OF ALBEMARLE
Department of Community Development
VSMPNESCP PERMIT SITE INSPECTION REPORT
Project Name:Fr-eZ_Project/WPO
COVERAGE & POSTING REQUIREMENTS
Yes
Number:
`j 0) .
Project Address:
Cy L
DEQ Permit Number (If
a Ilcable):
VAR i? K gYO
Project Operator:
Comments/Descript hn
9
Operator Telephone #:
Project Contact:
Contact Telephone #:
(9VAC25-870-310xA1b. Co. Code §17-300,17-302)
Contact E -Mail:
Qualified Personnel (QP):
2
Inspector:
(Juc(-�..C..�
Weather (WetfDry/Rain):
Disturbed Acreage:
main entrance of the construction activity? (CGP Part II.C)
6.4 /•der&
Inspection Date & Tlme:
Single -Family: ❑ Yes
FeKo
Notice of the location of the SWPPP is posted near the site's entrance, if
applicable, and Information for public access is provided? (9VAC25-870-
Stage of Construction: LJ
❑ Building Construction
❑ Notice of Termination
Pre -Construction Meeting LJ Initial Clearing & Grading LJ
❑ Final Grading r�Construction of SWM Facilities
❑ Other.
Rough Grading
❑ Final Stabilization
Re -Inspection:
❑ Yes ZNo
54.GXCGP Part II D.2 & 3)
Page 1 of 7
COVERAGE & POSTING REQUIREMENTS
Yes
No
N/A
Reviewed during reinspection? 4 ❑No
Comments/Descript hn
9
Construction site has permit coverage? (Va. Code §52.1- 44.15:34.A)
(9VAC25-870-310xA1b. Co. Code §17-300,17-302)
✓
2
A copy of the notice of coverage letter is posted conspicuously near the
main entrance of the construction activity? (CGP Part II.C)
3
Notice of the location of the SWPPP is posted near the site's entrance, if
applicable, and Information for public access is provided? (9VAC25-870-
54.GXCGP Part II D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS
Yes
No
N/A
Reviewed during re -inspection? pYes�
Comment&Vescrfpdon
4
The SWPPP is on-site or made available during the inspection? (CGP
Part II D.1 & 2X9VAC25-870-54.G)
5
The SWPPP contains a signed copy of the registration statement?
(CGP Part If A.1.a)
5
The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A.1.b & c)
The SWPPP includes a narrative description of the nature of the
7
construction activlty, including the function of the project? (CGP Part II
AAA)
Page 1 of 7
The SWPPP includes a legible site plan identifying all appropriate
8 measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
9 The SWPPP contains the name, phone number and qualifications of
"Qualified Personnel" conducting inspections? (CGP Part 11 A.6)
10 The SWPPP contains an approved erosion and sediment control plan?
(9VAC25-870-54.BXCGP Part II.A.2)
The SWPPP contains an approved stormwater management plan or an
J J existing construction site has a stormwater management plan that
ensures compliance with the water quality and quantity requirements?
(9VAC25-870-54.C)(CGP Part II.A.3) Technical Criteria II.B ❑ ILC ❑
12 The SWPPP contains an adequate pollution prevention plan? (9VAC25-
870-54.DXCGP Part II.A.4)
The SWPPP identifies impaired water(s), approved TMDL, pollutant(s) of
13 concern, exceptional waters and the additional controls measures
applicable? (9VAC 25-870-54.EXCGP Part IIA.5 (a -b))
14 Delegation of Authority is provided and signed in accordance with Part III
K? (CGP Part II A.7)
15 I The SWPPP is signed and dated in accordance with Part III K? (CGP
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Is the SWPPP being amended whenever there is a change in the design,
16 onstruction, operation, or maintenance that has a significant effect on the
ischarge of pollutants to surface waters? (CGP Part II B(1)x9VAC25-870-
Has the SWPPP been amended if inspections or investigations by the
17 perator's qualified personnel, or by local, state or federal officials find that
xisting control measures are ineffective in minimizing pollutants in
ischarges? (CGP Part II B(2))(9VAC25-870-54.0)
18 ontractor(s) that will implement and maintain each control measure are
identified? (CGP Part 11 B(3)x9VAC25-870-54.G)
ave there been updates to the SWPPP when any modifications to its
mplementation have occurred, including a record of dates when major
19 3rading activities occur, construction activities temporarily or permanently
ase on a portion of the site or stabilization measures are initiated? (CGP
NO IN/AI Reviewed during inspection? ❑Yes Ileo
Part 11 B.4(a))(9VAC25-870-54.G)
Is there documentation in the SWPPP of replaced or modified controls?
20
CGP Part II B.4(b))(9VAC25-870-54.G)
is the SWPPP updated to indicate areas that have reached final
21 tabilization? (CGP Part II B.4(c))(9VAC25-870-54.G)
Is the SWPPP updated to indicate properties that are no longer under the
legal control of the operator and the dates on which the operator no longer
22
had legal control over each property? (CGP Part Il B.4(d))(9VAC25-870-
G)
Does the SWPPP identify the date of any prohibited discharges, the
volume released, actions taken to minimize the impact of the release and
23
measures taken to prevent the recurrence of any prohibited discharge?
CGP Part II B.4(e-f)) (9VAC25-870-54.G)
Amendments, modifications, or updates to the SWPPP are signed in
24
ccordance with Part III K? (CGP Part II B(5))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
Yes
No N/A
Reviewed during inspection? ❑Yes 26o
Comments/Descrlpdon
Inspections required by the SWPPP are conducted at the required
frequency, including a modified frequency for impaired water(s), approved
25
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part 11 A.5.b.3)
Page 2 of 7
P Inspection reports are completed and signed in accordance with CGP
26 Part II F (3-4)? (CGP Part 11 F (3-4))
Corrective actions are taken consistent with the requirements of the
27
CGP? (CGP Part II G(1-2))
ESC AND SWM PLAN IMPLEMENTATION
Yes
No
N/A
Reviewed during inspection? []Yes []No
Comments/Desaip8on
28 Have stream buffers and steep slopes been protected as shown on the
plan?
Sequencing of the project Is Implemented In accordance with the
29 approved erosion and sediment control plan and stormwater managemen
plans? (9VAC25-870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
been stabilized, and have stabilization requirements for impaired waters,
/
30 approved TMDL(s), pollutants of concern and exceptional waters, when
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC2
q/
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.15(1)) (CGP Part II A.2.c (8))
(CGP II E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part II
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
33 disturbance activities? (9VAC 25-840-40.4) (CGP Part II A.2(c)) (CGP II
E(1-2)) (9VAC25-870-54.B)
Have earthen structures been stabilized immediately after installation?
34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.13)
Are sediment traps and basins installed in accordance with MS -6 and the
35 approved plan? (9VAC 25-840-40.6) (CGP Part II A.2.c (9)) (CGP Part 11
A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.6)
Are finished cut and fill slopes adequately stabilized to prevent or correct
36 excessive erosion? (9VAC 25-840-40.7) (CGP Part II A.2(c)) (CGP II E(1-
2)) (9VAC25-870-54.6)
Is concentrated runoff down cut or fill slopes contained in an adequate
37 permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP II E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
38 (9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.B)
Do all operational storm sewer inlets have adequate inlet protection?
39 (9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP II E(9-2)) (9VAC25-870-
54.13)
Are stomtwater conveyance channels adequately stabilized with channel
40 lining and/or outlet protection? (9VAC 25-840-40.91) (CGP Part I I A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.8)
Is in -stream construction conducted using measures to minimize channel
41 damage? (9VAC 25-840-40.12) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.8)
Are temporary stream crossings of non -erodible material installed where
42 applicable? (9VAC 25-840-40.13) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54. B)
43 Is necessary restabilization of in -stream construction complete? (9VAC
25-840-40.15) (CGP II E(1-2)) (9VAC25.870-54.B)
Are utility trench operations conducted and stabilized in accordance with
44 MS -16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.B)
Are soil and mud kept off paved or public roads to minimize the transport
Part II A.2(c)) II E(1-2))
45 of sediment? (9VAC 25-840-40.17) (CGP (CGP
(9VAC25-870-54.B)
Page 3 of 7
-
Have all temporary control structures that are no longer needed been
46
removed and disturbed soil resulting from their removal permanently
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.8)
Are properties and waterways downstream from development adequately
47
protected from erosion, sediment and damage in accordance with the
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
Permanent control measures included in the SWPPP are in place? /
tJerK;�►r� ��"'
48
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a)) r!
POLLUTION PREVENTION PLAN IMPLEMENTATION Yes No
N/A Reviewed during inspection? ❑Yes ❑No
CommerrtslDescriptior+
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49
and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part Ill G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and leaked fuels
50
and chemicals from vehicle fueling and maintenance activities? (CGP Part II
A.4.e(2))(9 VAC2 5-870-56 )
Practices are in place to prevent the discharge of soaps, solvents,
51
detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CGP
Part II A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52
and equipment washing, wheel wash water, and other types of washing?
(CGP Part II A.4.e(4))(9VAC25-870-56)
53
Concrete wash water is directed into a leak-proof container or leak-proof
/
+✓
settling basin? (CGP Part II A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54
storage, handling, and disposal of construction products, materials, and
wastes? (CGP Part II A.4.e(6)X9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55
petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
pollutant--generating activities not addressed above,
(CGP Part II A.4.e(8))(9VAC25-870-56)
It � rs
InspectorSignature:4� ��.r;t;' Date:
a
Page 4 of 7
Notes:
CONSTRUCTION GENERAL PERMIT SITE INSPECTION REPORT
REQUEST FOR CORRECTIVE ACTION
Project Name: Permit Number (if applicable): Date:
' Refers to applicable regulation found In the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 at seq.), Virginia Erosion and
Sediment Control Regulations (9VAC2"40), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Constructlon Activities (9VAC25-880).
Page 5 of 7
Regulatory
Occurrence
ObservationlRecornmended Corrective Action
Checklist #
Citation/Legal
requirement'
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Action:
Observation:
Recommended Corrective Acdon_:
Observation:
Recommended Corrective Action:
' Refers to applicable regulation found In the most recent publication of the State Water Control Law (Va. Code § 62.1-44.2 at seq.), Virginia Erosion and
Sediment Control Regulations (9VAC2"40), the Virginia Stormwater Management Program (VSMP) Regulations (9VAC25-870), or the General Permit for
Discharges of Stormwater from Constructlon Activities (9VAC25-880).
Page 5 of 7
Recommended Corrective Action Deadline:
Tarsieted Re -Inspection Date:
Comments:
The recommended corrective action deadline date applies to all conditions noted on this report unless otherwise noted. If listed condition(s) currently
constitute non-compliance and/or corrective actions are not completed by the deadline, other enforcement actions may be issued to the entity responsible for
ensuring compliance on the above project.
Inspector Signature:
Page 6 of 7
Date: