COUNTY OF ALBEMARLE
Dept. of Planning & Community Development
401 McIntire Road
Charlottesville, Virginia 22901-4596
(804) 296-5823
August 7, 1987
Woodbriar Associates
c/o Wendell Wood
P. O. Box 5548
Charlottesville,VA 22905
RE: SP-87-51 Woodbriar Associates
Dear Mr. Wood:
The Albemarle County Board of Supervisors, at its meeting on
August 5, 1987, unanimously approved the above-noted request
to allow installation of a six inch diameter sewer line
under the North Fork of the Rivanna River. Property located
on the west side of Rt. 29N, adjacent to bridge over north
fork of the Rivanna River. Tax Map 32, Parcel 19. Rivanna
Magisterial District. Please note that this approval is
subject to the following conditions:
1. Construction together with all restoration and
stabilization measures to be completed no later than
august 31, 1987; provided that completion date may be
extended not more than thirty (30) days by the County
Engineer in light of the current status of the project
and the weather;
I
2. The Zoning Administrator shall issue a development
permit for this project as required by Section 30.3.3.2
of the Zoning Ordinance. No such permit shall be
issued until all conditions of this special use permit
have been met and the County Engineer shall have
certified that in his opinion, the project can be
expected to be completed prior to termination dated
noted in condition #1;
-
e
3. Approval of appropriate local, state, and federal
agencies and presentation of evidence of such approvals
to the Zoning Administrator;
4. County Engineer approval in accordance with the
requirements of 30.3 Flood Hazard Overlay District with
particular attention to approval of access and river
crossing plans;
5. Only those areas necessary for the conduct of this
project shall be disturbed. Activity shall be
conducted in such a manner so that equipment shall not
travel over, be parked on, or otherwise encroach on
tree root systems outside of approved project limits;
6. All disturbed and denuded areas shall be stabilized as
required by the County Engineer. County engineer
approval of restorative and stabilization measures
prior to issuance of development permit. Such approval
shall among other things specify that all excess
construction material and debris shall be removed from
the floodplain and disposed of properly;
7. Compliance with the Soil Erosion and Sedimentation
Control Ordinance;
8. Posting of warning signs upstream from the site to
advise canoeists and other users of construction
activity and temporary obstructions;
9. Cash bonding as a mechanism by which the Zoning
Administrator may cause immediate compliance with this
special use permit and all other County regulations.
The County Engineer shall make periodic inspections of
the site to insure compliance with conditions imposed
herein. The County Engineer may require such
corrective measures as deemed necessary to insure
compliance with these conditions;
10. Presentation to Zoning Administrator of proof that all
easements necessary for construction and maintenance of
entire length of sewer line have been obtained.
If you should have any questions or comments regarding the
above noted action, please do not hesitate to contact me.
Sincerely,
~~
Ronald S. Keeler
Chief of Planning
RSK/jcw
cc: Charles Burgess, Zoning Administrator
Mike Armm, County Engineer