HomeMy WebLinkAboutWPO201700079 Plan - Stormwater WPO VSMP 2017-12-05STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar SINGLE FAMILY RESIDENCE COMMON PLAN of DEVELOPMENT or SALE STORMWATER POLLUTION PREVENTION PLAN(SWPPP) For Construction Activities At: Wilson Residence Lot 9 Blandemar Farms-Blandemar Drive Charlottesville,VA,22903 Latitude:38.0011 N(decimal degrees) Longitude:-78.3702 W(decimal degrees) Construction Activity Operator: Ben Wilson 19607 White Oak Road Sutherland,VA 23885 804)732-6551 wilsonaruact rcn.corrt 24-hour Emergency Contact;Ben Wilson-(804)731-4924 SWPPP Preparation Date: December 7,2017 CERTIFICATION I certify under penalty of law that I have read and understand this document and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system,or those persons directly responsible for gathering the Information,the information submitted is,to the best of my knowledge and belief,true,accurate,and complete. I am aware that there are significant penalties for submitting false information,Including the possibility of fine gn imprisonment for knowing violations." Operator Name: / 1& 4111 it//,f0 p,) Title: d arvet Signature: Date: a - s--, 7 07/2014, Rev. 1 Single Family Residence, CPoD,SWPPP STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar 1.0 SWPPP Documents Located Onsite&Available for Review SWPPP Document Type Located Onsite&Available for Review? Registration Statement Yes NA Notice of Coverage Letter Yes NA Construction General Permit Yes NA Site Plan Yes NA Erosion&Sediment Control Plan(or agreement in lieu of)Yes NA Stormwater Management Plan(or agreement in lieu of) Yes NA 2.0 Authorized Non-Stormwater Discharges Type of Authorized Non-Stormwater Discharge Likely Present at Your Project Site? External buildings wash down Yes No Uncontaminated foundation or footing drains Yes No Uncontaminated excavation dewatering El Yes No Landscape irrigation Yes No Others[describe] Yes No 3.0 Pollution Prevention Awareness Employees will be given a "walk through" of the site identifying areas of possible pollution and will be shown Erosion and Sediment Controls and Pollution Prevention Practices(identified in Sections 4.0 and 5.0 of this SWPPP)that are applicable to their assigned job duties. A refresher meeting and "walk through" will be conducted on an as needed basis. 4.0 Erosion&Sediment Controls Select all Estimated Estimated Responsible that apply Erosion&Sediment Control Installation Removal PartyDateDate Construction Entrance Std. &Spec. 3.02) 04/01/2018 12/01/2018 Silt Fence 04/01/2018 12/01/2018Std. &Spec. 3.05) Culvert Inlet Protection Std. &Spec. 3.08) 05/01/2018 12/01/2018 Outlet Protection 05/01/2018 NAStd. &Spec. 3.18) Rip Rap 05/01/2018 NA Construction ActivityStd. &Spec. 3.19) Operator(See Cover Rock Check Dam 05/01/2018 12/01/2018 Page of this SWPPP) Std. &Spec. 3.20) Level Spreader 05/01/2018 NAStd. &Spec. 3.21) Temporary Seeding As required NAStd. &Spec. 3.31) by 3.31 Permanent Seeding 10/01/2018 NAStd. &Spec. 3.32) 07/2014, Rev. 1 Single Family Residence, CPoD, SWPPP STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar Sodding 10/01/2018 NStd. &Spec. 3.33) Mulching 10/01/2018 NAStd. &Spec. 3.35) Soil Stabilization Blankets&Matting 05/01/2018 NAStd. &Spec. 3.36) Dust Control 04/01/2018 NAStd. &Spec. 3.37) 07/2014, Rev. 1 Single Family Residence, CPoD, SWPPP zaQE5a a. aa) a a)a za o Q 5 cn Om 0 >c a)cf.) 0 ov) .CO 0 Q.Z c p14, o ` o w 0toUWNmO rea o a0) C d "U) UOa 70 p f: a) o fy JCEO28 as a 3 > . ( 0 v CD C CO o v ami CZ a Q a c) n 0 O sjeaiweq Ppm"iaulo x x x x x > H smog'soda°Vali x x x x x x x x x x sasnmv epalpee x x eseei0 V HiQ x x x X sePPI4JaH'8 seppgsad x x 0 (seseq pue sppe)Hd x x x x x X C tlf °0 c Malan Atne9H x x x x x z a co a siuN x x x x x X c 0 luauupag x x x X x x a) d O. z z z z z z z z z z z i Cl) 0 a. lls CO CO CO (/) CO Cl) CO (I) En COo1..• w a) a) w a) w a) a) a) a) a) a as'2 >- >- >- >- >- >- >- >- >- >- >- a a ® ® ® ® ® ® ® ® ® ® c 0 3 O c O di v a) a) Qto 3 m C_ o X Cp .0 C - p L Ca d N co C O C co y m L 0 N N f0 N .n. C p ? 'a) " O ... 0) U 5CCl) a as a. rnN a 3 m (g m CM c a a)rY O m 3 a) o T (pQ@ - o c p) a) C 7 0) a) _o N N 3 U COc6C 'a m V ' N ` a) 0 W r- NN > c E 5 3 m m v_ E 10 Cl)o C co 0 a) '( a) Co ca o O 06 2 L N Um a 0 o (na o 2 2a (I) Cl) J 0 ib0 STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar Pollution Prevention Practices: 1) Clearing, grading, excavating and un-stabilized areas — Utilize erosion and sediment controls to prevent sediment laden or turbid runoff from leaving the construction site. Dispose of clearing debris at acceptable disposal sites. Apply permanent or temporary stabilization, sodding and/or mulching to denuded areas in accordance with the erosion and sediment control specifications and the general VPDES permit for discharges of stormwater from construction activities. 2) Paving operations — Cover storm drain inlets during paving operations and utilize pollution prevention materials such as drip pans and absorbent/oil dry for all paving machines to limit leaks and spills of paving materials and fluids. 3) Concrete washout and cement waste—Direct concrete wash water into a leak-proof container or leak-proof settling basin that is designed so that no overflows can occur due to inadequate sizing or precipitation. Hardened concrete wastes shall be removed and disposed of in a manner consistent with the handling of other construction wastes. 4) Structure construction,stucco, painting and cleaning — Enclose, cover or berm building material storage areas if susceptible to contaminated stormwater runoff. Conduct painting operations consistent with local air quality and OSHA regulations. Mix paint indoors, in a containment area or in a flat unpaved area. Prevent the discharge of soaps, solvents, detergents and wash water from construction materials, including the clean-up of stucco paint,form release oils and curing compounds. 5) Dewatering operations — Construction site dewatering from building footings or other sources may not be discharged without treatment. Sediment laden or turbid water shall be filtered, settled or similarly treated prior to discharge. 6) Material delivery and storage — Designate areas of the construction site for material delivery and storage. Place near construction entrances, away from waterways, and avoid transport near drainage paths or waterways. 7) Material use during building process — Use materials only where and when needed to complete the construction activity. Follow manufacturer's instructions regarding uses, protective equipment, ventilation, flammability and mixing of chemicals. 8) Solid waste disposal — Designate a waste collection area on the construction site that does not receive a substantial amount of runoff from upland areas and does not drain directly to a waterway. Ensure that containers have lids so they can be covered before periods of rain, and keep containers in a covered area whenever possible. Schedule waste collection to prevent the containers from overfilling. 9) Sanitary waste — Prevent the discharge of sanitary waste by providing convenient and well-maintained portable sanitary facilities. Locate sanitary facilities in a convenient location away from waterways. 10) Landscaping operations — Maintain as much existing vegetation as practicable. Apply permanent or temporary stabilization, sodding and/or mulching to denuded areas in accordance with the erosion and sediment control specifications and the general VPDES permit for discharges of stormwater from construction activities. Apply nutrients in accordance with manufacturer's recommendations and not during rainfall events. 11) Others—If applicable,describe your Pollution Prevention Practice. 6.0 Stormwater Management Controls Select all Estima#:d Responsible that apply Stormwater Management Control installation PartyDate Post-development Stormwater Management Controls Common Plan provided by a NA Construction Larger Common Plan of Development or Sale Activity Operator Rooftop Disconnection NA Sheetflow to Vegetated Filter(1 or 2) 10/01/2017 Via Level Spreaders Construction Grass Channel NA Activity Operator See Cover Page of this SWPPP) Rainwater Harvesting NA Permeable Pavement(1 or 2) NA 07/2014, Rev. 1 Single Family Residence, CPoD, SWPPP STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar Estimated that aSelect l l Stormwater Management Control Installation Responsible PP Y Date Party Infiltration (1 or 2) NA Construction Bioretention(1 or 2) NA Activity Operator See Cover Page of this SWPPP) Others[describe] Insert Date 7.0 Spill Prevention&Response Most spills can be cleaned up following manufacturer specifications. Absorbent/oil dry, sealable containers, plastic bags, and shovels/brooms are suggested minimum spill response items that should be available at this location. 1st Priority:Protect all people 2nd Priority: Protect equipment and property 3rd Priority:Protect the environment 1. Check for hazards(flammable material, noxious fumes, cause of spill)—if flammable liquid, turn off engines and nearby electrical equipment. If serious hazards are present leave the area and call 911. LARGE SPILLS ARE LIKELY TO PRESENT A HAZARD. 2. Make Sure the spill area is safe to enter and that it does not pose an immediate threat to health or safety of any person. 3. Stop the spill source. 4. Call co-workers and supervisor for assistance and to make them aware of the spill and potential dangers. 5. If possible, stop spill from entering drains(use absorbent or other material as necessary). 6. Stop spill from spreading(use absorbent or other material) 7. If spilled material has entered a storm sewer; contact locality's storm water department. 8. Clean up spilled material according to manufacturer specifications, for liquid spills use absorbent materials and do not flush area with water. 9. Properly dispose of cleaning materials and used absorbent material according to manufacturer specifications. Emergency Contacts: Normal Working Hours DEQ Blue Ridge Regional Office(Roanoke) 540-562-6700 DEQ Blue Ridge Regional Office(Lynchburg) 434-582-5120 DEQ Northern Regional Office 703-583-3800 DEQ Piedmont Regional Office 804-527-5020 DEQ Southwest Regional Office 276-676-4800 DEQ Tidewater Regional Office 757-518-2000 DEQ Valley Regional Office 540-574-7800 Nights,Holidays&Weekends VA Dept. of Emergency Management 804-674-2400 24 Hour Reporting Service Local Contacts Local Fire Department 434)296-5807 Local Police Department 434)971-1583 07/2014, Rev. 1 Single Family Residence, CPoD, SWPPP STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar 8.0 Inspections&Corrective Action Log(make additional copies as necessary) Qualified Inspector Company/Organization: TBD Name: TBD Telephone Number:TBD Qualifications: TBD Inspection Schedule Discharges to surface waters: Once every 5 business days;or Once every 10 business days and no later than 48 hours following a measurable storm event. Discharges to impaired waters,surface waters within a TMDL watershed,or exceptional waters: O Once every 4 business days;or Once every 5 business days and no later than 48 hours following a measurable storm event. Inspection Date: Measurable Storm Event Best Management In Compliance Corrective Action Needed;Date Corrective Practices(BMPs) with SWPPP? Responsible Party Action Taken Erosion&Sediment Controls 0 Yes 0 No Section 4.0) Pollution Prevention Practices Yes 0 No Section 5.0) Stormwater 0 Yes 0 No Management Controls Section 6.0) El NA Certification I certify under penalty of law that I have read and understand this document and that this document and all attachments were prepared in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the Information submitted. Based on my Inquiry of the person or persons who manage the system,or those persons directly responsible for gathering the Information,the Information submitted is,to the best of my knowledge and belief,true,accurate,and complete. I am aware that there are significant penalties for submitting false Information,including theempossibi' of fine and imprisonment for knowing violations." Operator Name:I"pof si r•- Inspector Name: Signature: Signature: Date: A •.s"`—/7 Date: 07/2014, Rev. 1 Single Family Residence,CPoD,SWPPP STORMWATER POLLUTION PREVENTION PLAN Wilson Residence in Blandemar 9.0 Grading&Stabilization Activities Log Date Description of the Date Date Description of theGradingGradingActivityGradingStabilization Stabilization MeasureActivityincludinglocation) Activity Measures including location)Initiated Ceased Initiated 10.0 SWPPP Modification&Update Log Modification Modification Prepared By Date Description of the Modification/Update name&title) 07/2014, Rev. 1 Single Family Residence, CPoD, SWPPP INSTRUCTIONS for COMPLETING the SINGE FAMILY RESIDENCE,COMMON PLAN of DEVELOPMENT or SALE STORMWATER POLLUTION PREVENTION PLAN (SWPPP) General A Stormwater Pollution Prevention Plan (SWPPP) must be developed prior to obtaining locality (e.g., City, County, Town) authorization to commence land disturbance. Cover Page For a construction activity, enter the project/site name and physical address (if available), including city (or town), state and zip code. Enter the latitude and longitude in decimal degrees of the construction activity. Enter the Construction Activity Operator's company/organization name,the Operator's name and mailing address, including city(or town),state,and zip code,telephone number,email address(if available),and a 24-hour emergency contact. Enter the SWPPP preparation date. The Construction Activity Operator identified on the cover page of the SWPPP is responsible for certifying the information contained therein. Please sign the certification in INK. Please note that state statues require the SWPPP to be signed as follows: 1)For a corporation:by a responsible corporate officer; 2)For a partnership or sole proprietorship:by a general partner or the proprietor,respectively; 3)For a municipality,state,federal,or other public agency:by either a principal executive officer or ranking elected official. Section 1.0 SWPPP Documents Located Onsite&Available for Review Utilize the provided checklist to ensure that the required SWPPP documents are located onsite and are available for review, if applicable. Section 2.0 Authorized Non-Stormwater Discharges Identify the authorized non-stormwater discharges likely to be present at the project site. If an unlisted authorized non-stormwater discharge is likely to be present at the project site,provide it here. Section 3.0 Pollution Prevention Awareness Provide employees with a"walk through"of the project site and identify areas of possible pollution,erosion and sediment controls, and pollution prevention practices which are applicable to their assigned job duties. Conduct refresher meetings and perform additional"walk throughs"on an as needed basis. Section 4.0 Erosion&Sediment Controls Identify the erosion and sediment controls to be implemented at the project site. For each erosion and sediment control,enter the estimated installation date and estimated removal date. If an unlisted erosion and sediment control will be implemented at the project site,provide the applicable information here. Section 5.0 Potential Sources of Pollution&Pollution Prevention Practices Identify the pollutant-generating activities likely to be present at the project site; implement and maintain the corresponding pollution prevention practices. If an unlisted pollutant-generating activity is likely to be present at the project site, describe it, identify the associated pollutant(s),and provide the corresponding pollution prevention practice(s)to be implemented and maintained. Section 6.0 Stormwater Management Controls Identify the stormwater management controls to be implemented at the project site,if applicable. For each stormwater management control,enter the estimated installation date. If an unlisted stormwater management control will be implemented at the project site, provide the applicable information here. Section 7.0 Spill Prevention&Response Most spills can be cleaned up following manufacturer specifications. The priority should be to protect all people, equipment, property,and the environment. Enter the telephone number of your local fire and police departments. Section 8.0 Inspections&Corrective Action Log Enter the qualified inspector's company/organization name,the inspector's name,telephone number,and qualifications. Select the applicable inspection schedule, enter the construction activity inspection date, and enter the date and rainfall amount of the last measurable storm event(if applicable). Identify if the implemented best management practices are in compliance with the SWPPP. Enter corrective actions needed;the party responsible for implementing the corrective actions,and the date corrective actions were taken,if applicable. Make additional copies of the inspection and corrective action log as necessary. Section 9.0 Grading&Stabilization Activities Log Enter the date grading activities were initiated, a description of the grading activities including location, the date grading activities ceased,the date stabilization measures were initiated,and a description of the stabilization measures including location. Section 10.0 SWPPP Modification&Update Log Enter the SWPPP modification date, description of the SWPPP modification/update, and the name and title of the SWPPP modification preparer,if applicable. 07/2014;.Rev; I Single Family Residence, CPoD, SWPPP