Loading...
HomeMy WebLinkAboutARB201800072 Staff Report 2018-06-261 ARCHITECTURAL REVIEW BOARD STAFF REPORT Project #/Name ARB-2018-72: Pantops Corner Initial Site Plan Review Type Initial Site Development Plan, First review of an architectural design for the hotel Parcel Identification 078000000005A0, 078000000005B0, 078000000005G1 Location On the north side of Richmond Road (Rt. 250 east) across from People Place Zoned Highway Commercial (HC)/Entrance Corridor (EC) Owner/Applicant Pantops Corner LC/Shimp Engineering (Justin Shimp) Magisterial District Rivanna Proposal To construct a 5-story hotel and a retail building with associated site improvements. Context The site of the proposed development is surrounded by a mix of retail, office and residential development. Visibility The hotel will be visible from both the Rt. 250 and Rt. 20 Entrance Corridors. ARB Meeting Date July 2, 2018 Staff Contact Margaret Maliszewski PROJECT HISTORY  Multiple pre-application conferences were held for a hotel development at this site in late 2017 and early 2018. Staff recommended that the applicant submit preliminary architectural designs early in the process to get feedback from the ARB on the hotel design.  In 2016 and 2017 the ARB completed multiple reviews of a LIDL grocery store at this site. That application has been withdrawn. 2 ANALYSIS Gray highlight = means the guideline can’t be reviewed at initial site plan stage, but recommendations can be provided for final Yellow highlight = means the guideline can only be reviewed for location/configuration at the initial plan stage Regular text = means the guideline can be reviewed at initial plan stage, can be made a condition of initial plan approval, and can be the basis for denial REF GUIDELINE ISSUE RECOMMENDATION Structure design 1 The goal of the regulation of the design of development within the designated Entrance Corridors is to insure that new development within the corridors reflects the traditional architecture of the area. Therefore, it is the purpose of ARB review and of these Guidelines, that proposed development within the designated Entrance Corridors reflect elements of design characteristic of the significant historical landmarks, buildings, and structures of the Charlottesville and Albemarle area, and to promote orderly and attractive development within these corridors. Applicants should note that replication of historic structures is neither required nor desired. Two options are illustrated for the building design. In both designs, the building is 5 stories tall with a single bay, three-story wing on the west elevation, that is provided to meet the stepback requirement. (For each story that begins above 40’ in height, or for each story above the third story, whichever is less, the minimum stepback shall be 15’.) Both options have: 1) an off-center, 4-bay, brick-framed, EIFS-faced entrance element that projects forward from the main building wall; 2) north and south elevations with brick-faced walls at the three lower stories and EIFS walls above; 3) side elevations with brick-faced walls at the lower 2 stories and EIFS walls above; and 4) a fenced patio on the north side and a porte cochere with an angled roof supported by stone-faced columns on the south side. The primary difference in the designs is that Option 1 has a hipped roof with rectangular tower- like elements at the building corners, extending up from the third story, and Option 2 transforms the towers into oversized stepped gables at the ends of the building. In both cases the roof has a deep overhang on the north and south elevations. The various elements of the design and the materials and colors contribute to a “busy” and uncoordinated appearance. The stepped gable doesn’t have a strong local precedent, appears overscaled, and further contributes to the lack of The stepped gables of Option 2 are not appropriate for the EC. Revise the corner towers of Option 1 so that they appear more fully as towers or eliminate them. Revise the EIFS material and detailing of the entrance bay to better reflect the importance of the entrance function. Note on the elevation drawings that the vents at the windows will be colored to match the adjacent wall surface. Refine and simplify the hotel design to establish greater coordination of architectural elements throughout. Clarify the proposed shingle color and note it consistently throughout the drawings. 2 Visitors to the significant historical sites in the Charlottesville and Albemarle area experience these sites as ensembles of buildings, land, and vegetation. In order to accomplish the integration of buildings, land, and vegetation characteristic of these sites, the Guidelines require attention to four primary factors: compatibility with significant historic sites in the area; the character of the Entrance Corridor; site development and layout; and landscaping. 3 New structures and substantial additions to existing structures should respect the traditions of the architecture of historically significant buildings in the Charlottesville and Albemarle area. Photographs of historic buildings in the area, as well as drawings of architectural features, which provide important examples of this tradition are contained in Appendix A. 4 The examples contained in Appendix A should be used as a guide for building design: the standard of compatibility with the area’s historic structures is not intended to 3 impose a rigid design solution for new development. Replication of the design of the important historic sites in the area is neither intended nor desired. The Guideline’s standard of compatibility can be met through building scale, materials, and forms which may be embodied in architecture which is contemporary as well as traditional. The Guidelines allow individuality in design to accommodate varying tastes as well as special functional requirements. coordination. The brick proposed for the base of the building is a tie to a traditional building material in the county, but overall the design does not have a strong connection to the historic architecture of the area. The architectural elevations note gray dimensional shingles for the roof; the renderings show brown shingles. The addition of a three-story wing on the east end of the building would balance the design and make it more consistent with some historic precedents. The entrance bay of the hotel is emphasized by a brick surround, increased height, and a projection out from the main wall of the building. The material (EIFS) and apparent lack of texture and detail in the wall surface are not consistent with the importance of the entrance function. Note that architectural elevations for Building A were not submitted with the Initial Plan; however, staff recently met with the applicant to view preliminary designs. Based on the materials and details presented, staff recommended that the applicant provide the elevations for a work session level review with the ARB. These drawings will be forwarded to the ARB as soon as they are made available. 9 Building forms and features, including roofs, windows, doors, materials, colors and textures should be compatible with the forms and features of the significant historic buildings in the area, exemplified by (but not limited to) the buildings described in Appendix A [of the design guidelines]. The standard of compatibility can be met through scale, materials, and forms which may be embodied in architecture which is contemporary as well as traditional. The replication of important historic sites in Albemarle County is not the objective of these guidelines. 5 It is also an important objective of the Guidelines to establish a pattern of compatible architectural characteristics throughout the Entrance Corridor in order to achieve unity and coherence. Building designs should demonstrate sensitivity to other nearby structures within the Entrance Corridor. Where a designated corridor is substantially developed, these Guidelines require striking The proposed hotel will appear considerably larger (at approx. 210’ x 65’) and taller (at approx. 74’ tall) than the buildings on the adjacent properties (Goodwill, Malloy Ford, Flow Auto) and will appear considerably different in form, style and detail. The building height is more consistent with the Virginia National Bank building across Rt. 250 None at this time. 4 a careful balance between harmonizing new development with the existing character of the corridor and achieving compatibility with the significant historic sites in the area. to the south. Future buildings in the Pantops Corner development could be designed to be compatible with the hotel. Future buildings will also serve to limit visibility of the hotel. 10 Buildings should relate to their site and the surrounding context of buildings. 11 The overall design of buildings should have human scale. Scale should be integral to the building and site design. Details and treatments employed to help establish human scale include: material and color changes, brick banding, and projections. None. 12 Architecture proposed within the Entrance Corridor should use forms, shapes, scale, and materials to create a cohesive whole. The proposed design incorporates a number of different forms, details, materials and colors. A greater level of coordination among these elements would establish more of a cohesive whole. Refine and simplify the hotel design to establish greater coordination of architectural elements throughout. 13 Any appearance of “blankness” resulting from building design should be relieved using design detail or vegetation, or both. In both hotel designs, blankness in the end elevations is relieved by a single, central bay of windows and changes in materials and colors. It is anticipated that most of the eastern elevation will not be visible from the EC. None. 14 Arcades, colonnades, or other architectural connecting devices should be used to unify groups of buildings within a development. The nearest building to the hotel that is proposed at this time is 500’ away. No connecting devices are provided. None. 15 Trademark buildings and related features should be modified to meet the requirements of the Guidelines. The proposed design is a Holiday Inn Express & Suites standard with some revisions made in an attempt to address local context and requirements. See recommendations above. 16 Window glass in the Entrance Corridors should not be highly tinted or highly reflective. Window glass in the Entrance Corridors should meet the following criteria: Visible light transmittance (VLT) shall not drop below 40%. Visible light reflectance (VLR) shall not exceed 30%. Specifications on the proposed window glass should be submitted with the application for final review. Window glass is not addressed in this submittal. Include the standard window glass note on the drawings and provide specs for review. Accessory structures and equipment 17 Accessory structures and equipment should be integrated into the overall plan of development and shall, to the extent possible, be compatible with the building designs used on the site. Dumpsters are proposed at the northeast corner of the site. Evergreen shrubs are proposed around the dumpster screen. Given the location, if the dumpster screen material is coordinated with the building material, the appearance is expected to be appropriate. Add a dumpster detail to the site plan. Coordinate dumpster screening materials with the building materials. 18 The following should be located to eliminate visibility from the Entrance Corridor street. If, after appropriate siting, 5 these features will still have a negative visual impact on the Entrance Corridor street, screening should be provided to eliminate visibility. a. Loading areas, b. Service areas, c. Refuse areas, d. Storage areas, e. Mechanical equipment, f. Above-ground utilities, and g. Chain link fence, barbed wire, razor wire, and similar security fencing devices. Mechanical equipment for the hotel is expected to be located below the roof. Vents at individual rooms appear to be colored to coordinate with the adjacent wall material. No information has been provided regarding equipment for Building A. Confirm that mechanical equipment for the hotel will be screened by the roof. Note on the elevation drawings that vents at the individual rooms will be colored to coordinate with the adjacent wall material. Show where Building A mechanical equipment is located. 19 Screening devices should be compatible with the design of the buildings and surrounding natural vegetation and may consist of: a. Walls, b. Plantings, and c. Fencing. 21 The following note should be added to the site plan and the architectural plan: “Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated.” The note does not appear on the drawings. Add the standard mechanical equipment note to the site and architectural drawings. Lighting No lighting is proposed at this time. The roof of the port cochere is angled up and away from the building. This may allow the under-canopy light fixtures to produce glare and/or emit light above the horizontal plane. Include details in the lighting plan to confirm that the under-canopy light fixtures are full cutoff fixtures that do not produce glare. Update the lighting plan to include information on all proposed building lights. Landscaping 7 The requirements of the Guidelines regarding landscaping are intended to reflect the landscaping characteristic of many of the area’s significant historic sites which is characterized by large shade trees and lawns. Landscaping should promote visual order within the Entrance Corridor and help to integrate buildings into the existing environment of the corridor. Rt. 250 Large shade trees, 3½” caliper at planting, are shown along the Rt. 250 frontage, spaced 35’ on center with a gap in the planting where the entrance/exit is proposed. Ornamental trees are interspersed. Clearly show all utilities and easements on the utility and landscape plans. Provide required planting free of utilities and easements. 6 8 Continuity within the Entrance Corridor should be obtained by planting different types of plant materials that share similar characteristics. Such common elements allow for more flexibility in the design of structures because common landscape features will help to harmonize the appearance of development as seen from the street upon which the Corridor is centered. An existing water line is shown approximately 15’ from the trunks of the large trees. Site plans previously reviewed for this site showed two underground fiber optic lines, a Centel easement, an overhead power line, a power easement and a Service Authority easement in addition to the water line. Rt. 20 Substantial right-of-way (up to approximately 60’ in depth) exists between the property line and the edge of pavement along Rt. 20. Some of the right- of-way is occupied by existing trees that are shown to remain. This wooded area ranges from 10’ to 30’ deep. Grading is shown into the edges of the wooded area. The ground rises approximately 20’ from Rt. 20 to the base of a proposed retaining wall that runs along a parking lot on the north side of the hotel. The wall varies in height from 6’ to 12’. A row of evergreen shrubs is shown along the parking lot side of the portion of the wall closest to Rt. 20. Only one perimeter parking lot tree is provided along 585 linear feet of retaining in this area. There is no landscape easement on the wooded area in the right-of-way. Consequently, the standard EC frontage planting should be provided. South of the entrance on Rt. 20, there is a much shorter length of frontage; it is without trees. One tree is shown off-site in the right-of-way at the intersection of Pantops Corner Way with Rt. 20. A separate diagram of the frontage planting that details the utility lines and easements in varying colors would help clarify the feasibility of the proposed planting. Eliminate the conflicts between proposed grading and wooded area to remain along Rt. 20. Provide large shade trees, 3½” caliper at planting, 35’ on center, along the Rt. 20 side of the site. Intersperse ornamentals among the shade trees. 32 Landscaping along the frontage of Entrance Corridor streets should include the following: a. Large shade trees should be planted parallel to the Entrance Corridor Street. Such trees should be at least 3½ inches caliper (measured 6 inches above the ground) and should be of a plant species common to the area. Such trees should be located at least every 35 feet on center. b. Flowering ornamental trees of a species common to the area should be interspersed among the trees required by the preceding paragraph. The ornamental trees need not alternate one for one with the large shade trees. They may be planted among the large shade trees in a less regular spacing pattern. c. In situations where appropriate, a three or four board fence or low stone wall, typical of the area, should align the frontage of the Entrance Corridor street. d. An area of sufficient width to accommodate the foregoing plantings and fencing should be reserved parallel to the Entrance Corridor street, and exclusive of road right-of-way and utility easements. 33 Landscaping along interior roads: a. Large trees should be planted parallel to all interior roads. Such trees should be at least 2½ inches caliper (measured six inches above the ground) and should be of a plant species common to the area. Such trees should be Large shade trees, 2½” caliper at planting, are spaced 40’ apart along the interior road. None at this time. 7 located at least every 40 feet on center. 34 Landscaping along interior pedestrian ways: a. Medium trees should be planted parallel to all interior pedestrian ways. Such trees should be at least 2½ inches caliper (measured six inches above the ground) and should be of a species common to the area. Such trees should be located at least every 25 feet on center. Trees are shown at 40’ on center along the sidewalks that are located adjacent to interior roads (which also require trees at 40’ spacing). A sidewalk surrounds the hotel, but the 25’ tree spacing is only met at its southwest corner. Sidewalks are provided north of Building A, but the 25’ spacing requirement is not met. Provide medium street trees parallel to the sidewalks at the hotel and Building A at 25’ on center. 35 Landscaping of parking areas: a. Large trees should align the perimeter of parking areas, located 40 feet on center. Trees should be planted in the interior of parking areas at the rate of one tree for every 10 parking spaces provided and should be evenly distributed throughout the interior of the parking area. b. Trees required by the preceding paragraph should measure 2½ inches caliper (measured six inches above the ground); should be evenly spaced; and should be of a species common to the area. Such trees should be planted in planters or medians sufficiently large to maintain the health of the tree and shall be protected by curbing. c. Shrubs should be provided as necessary to minimize the parking area’s impact on Entrance Corridor streets. Shrubs should measure 24 inches in height. The cover sheet notes a total of 177 parking spaces proposed. The landscape plan notes 176 parking spaces. Sufficient interior parking lot trees are provided. Coordinate the number of proposed parking spaces noted on the cover sheet with the number noted on the landscape plan and the actual number provided. 36 Landscaping of buildings and other structures: a. Trees or other vegetation should be planted along the front of long buildings as necessary to soften the appearance of exterior walls. The spacing, size, and type of such trees or vegetation should be determined by the length, height, and blankness of such walls. b. Shrubs should be used to integrate the site, buildings, and other structures; dumpsters, accessory buildings and structures; “drive thru” windows; service areas; and signs. Shrubs should measure at least 24 inches in height. Medium shade trees are proposed along the Rt. 250 side of the hotel, spaced 40’, 50’ and 60’ apart. Two trees are provided on the north side of the hotel – one in each of two planting islands at the corners of the building. The side elevations have limited windows. Additional trees located just west of the hotel building would be appropriate. Add trees west of the hotel building to soften the appearance of the west elevation. 37 Plant species: a. Plant species required should be as approved by the Staff based upon but not limited to the Generic Landscape Plan Recommended Species List and Native Plants for Virginia Landscapes (Appendix D). Plant species have not yet been provided. None at this time. 38 Plant health: The following note should be added to the The note appears on the plan. Note 4 on the Eliminate Note 4 on the 8 landscape plan: “All site plantings of trees and shrubs shall be allowed to reach, and be maintained at, mature height; the topping of trees is prohibited. Shrubs and trees shall be pruned minimally and only to support the overall health of the plant.” landscape plan indicates that landscaping shall be replaced when necessary. This note is too open- ended and should be deleted. Note 5 indicates that planting will occur after building and road construction. Additional information should be provided to clarify the timing of the EC frontage planting. landscape plan. Provide additional clarification regarding the timing of EC frontage planting. Site Development and layout 6 Site development should be sensitive to the existing natural landscape and should contribute to the creation of an organized development plan. This may be accomplished, to the extent practical, by preserving the trees and rolling terrain typical of the area; planting new trees along streets and pedestrian ways and choosing species that reflect native forest elements; insuring that any grading will blend into the surrounding topography thereby creating a continuous landscape; preserving, to the extent practical, existing significant river and stream valleys which may be located on the site and integrating these features into the design of surrounding development; and limiting the building mass and height to a scale that does not overpower the natural settings of the site, or the Entrance Corridor. Proffers associated with ZMA-2013-02 require a private road from Rt. 20 to Rt. 250 through the property; the road is shown on the plan. The hotel is located approximately 575’ from Rt. 250 and 125’ from Rt. 20. Retail building A is located 27’ from Rt. 250. The phasing of the project leaves a 2-acre pad for future development adjacent to the Rt. 250 EC, in front of the hotel. Retaining walls line the eastern edge of the pad. Trees are shown along the EC frontage of the future pad site. In addition to the three-tiered wall east of the future pad site, there are other significant retaining walls proposed throughout the site to accommodate the development. The walls reach 6’, 8’ and 12’ tall, but only those east of the pad site are stepped. The hotel is proposed at 5 stories high. This is taller than all buildings in the immediate vicinity except for the VNB building located on the south side of Rt. 250. Eventually, buildings in the “future development” area will limit visibility of the hotel from Rt. 250. Terrace retaining walls 6’ in height and taller and plant the terraces. 39 The relationship of buildings and other structures to the Entrance Corridor street and to other development within the corridor should be as follows: a. An organized pattern of roads, service lanes, bike paths, Building A and the hotel building are situated parallel to the Rt. 250 EC. The hotel is not parallel to the Rt. 20 EC. None. 9 and pedestrian walks should guide the layout of the site. b. In general, buildings fronting the Entrance Corridor street should be parallel to the street. Building groupings should be arranged to parallel the Entrance Corridor street. c. Provisions should be made for connections to adjacent pedestrian and vehicular circulation systems. d. Open spaces should be tied into surrounding areas to provide continuity within the Entrance Corridor. e. If significant natural features exist on the site (including creek valleys, steep slopes, significant trees or rock outcroppings), to the extent practical, then such natural features should be reflected in the site layout. If the provisions of Section 32.5.2.n of the Albemarle County Zoning Ordinance apply, then improvements required by that section should be located so as to maximize the use of existing features in screening such improvements from Entrance Corridor streets. f. The placement of structures on the site should respect existing views and vistas on and around the site. The layout of the site appears generally organized, though a large portion of the development is not yet shown. Sidewalk connections are made to both Rt. 250 and Rt. 20. A small pocket of existing wooded area is shown to remain at the northeast corner of the site. It is connected to a larger wooded area located behind the Ford car dealership. Site Grading 40 Site grading should maintain the basic relationship of the site to surrounding conditions by limiting the use of retaining walls and by shaping the terrain through the use of smooth, rounded land forms that blend with the existing terrain. Steep cut or fill sections are generally unacceptable. Proposed contours on the grading plan shall be rounded with a ten foot minimum radius where they meet the adjacent condition. Final grading should achieve a natural, rather than engineered, appearance. Retaining walls 6 feet in height and taller, when necessary, shall be terraced and planted to blend with the landscape. The use of retaining walls is not limited in this proposal. A large portion of the development adjacent to Rt. 250, east of the interior road would be graded for future development. This results in a large, rectangular pad with three retaining walls adjacent to the eastern property line. The walls are approximately 270’, 350’ and 390’ long with 3’ spacing between each wall. A note indicates that they are approximately 6’ tall. Rows of shrubs are shown at the base of each wall. A 6’-12’-tall retaining wall approximately 450’ long, runs along the northeastern, northern, and northwestern boundaries of the hotel parking lot. A 225’-long 8’-tall wall marks the southeast corner of the hotel parking lot. A 165’-long wall parallels the interior road just Terrace retaining walls 6’ in height and taller and plant the terraces. Provide top-of-wall and bottom-of-wall elevations for the retaining walls. 10 north of the proposed retail building. 41 No grading, trenching, or tunneling should occur within the drip line of any trees or other existing features designated for preservation in the final Certificate of Appropriateness. Adequate tree protection fencing should be shown on, and coordinated throughout, the grading, landscaping and erosion and sediment control plans. Some proposed grading falls within the line of trees to remain along the Rt. 20 frontage. Adjust the proposed grading to eliminate conflicts with wooded area to remain. Show adequate tree protection fencing on the grading, landscaping and erosion and sediment control plans. 42 Areas designated for preservation in the final Certificate of Appropriateness should be clearly delineated and protected on the site prior to any grading activity on the site. This protection should remain in place until completion of the development of the site. 43 Preservation areas should be protected from storage or movement of heavy equipment within this area. 20 Surface runoff structures and detention ponds should be designed to fit into the natural topography to avoid the need for screening. When visible from the Entrance Corridor street, these features must be fully integrated into the landscape. They should not have the appearance of engineered features. No above-ground stormwater facilities are proposed. None at this time. 44 Natural drainage patterns (or to the extent required, new drainage patterns) should be incorporated into the finished site to the extent possible. SUMMARY OF RECOMMENDATIONS Staff recommends the following as the primary points of discussion: 1. The architectural design of the hotel: roof forms, materials, colors, overall coordination 2. Proposed landscaping along the ECs/utility conflicts 3. The extensive use of retaining walls 11 Staff recommends that the ARB forward the following recommendations to the Agent for the Site Review Committee:  Regarding requirements to satisfy the design guidelines as per § 18-30.6.4c(2), (3) and (5) and recommended conditions of initial plan approval: o Prior to Initial Plan approval the following items shall be resolved to the satisfaction of the ARB: 1. Clearly show all utilities and easements on the utility and landscape plans. Provide required planting free of utilities and easements. A separate diagram of the frontage planting that details the utility lines and their easements in varying colors would help clarify the feasibility of the proposed planting.  Regarding recommendations on the plan as it relates to the guidelines: None.  Regarding conditions to be satisfied prior to issuance of a grading permit: 1. Adjust the proposed grading to eliminate conflicts with wooded area to remain. Show adequate tree protection fencing on the grading, landscaping and erosion and sediment control plans.  Regarding the final site plan submittal: 1. The stepped gables of Option 2 are not appropriate for the EC. 2. Revise the corner towers of Option 1 so that they appear more fully as towers or eliminate them. 3. Revise the EIFS material and detailing of the entrance bay to better reflect the importance of the entrance function. 4. Note on the elevation drawings that the vents at the windows will be colored to match the adjacent wall surface. 5. Refine and simplify the hotel design to establish greater coordination of architectural elements throughout. 6. Clarify the proposed shingle color and note it consistently throughout the drawings. 7. Include the standard window glass note on the drawings and provide specs for review: Visible light transmittance (VLT) shall not drop below 40%. Visible light reflectance (VLR) shall not exceed 30%. 8. Add a dumpster detail to the site plan. Coordinate dumpster screening materials with the building materials. 9. Confirm that mechanical equipment for the hotel will be screened by the roof. Note this on the architectural drawings. 10. Show on the plan where Building A mechanical equipment is located. 11. Add the standard mechanical equipment note to the site and architectural drawings: Visibility of all mechanical equipment from the Entrance Corridor shall be eliminated. 12. Include details in the lighting plan to confirm that the under-canopy light fixtures are full cutoff fixtures that do not produce glare. 13. Update the lighting plan to include information on all proposed building lights. 14. Clearly show all utilities and easements on the utility and landscape plans. Provide required planting free of utilities and easements. A separate diagram of the frontage planting that details the utility lines and easements in varying colors would help clarify the feasibility of the proposed planting. 15. Provide large shade trees, 3½” caliper at planting, 35’ on center, along the Rt. 20 side of the site. Intersperse ornamentals among the shade trees. 16. Provide medium street trees, spaced 25’ on center, parallel to the sidewalks at the hotel and Building A. 17. Coordinate the number of proposed parking spaces noted on the cover sheet with the number noted on the landscape plan and the actual number provided. 18. Add trees west of the hotel building to soften the appearance of the west elevation. 12 19. Eliminate Note 4 on the landscape plan. Provide additional clarification regarding the timing of EC frontage planting. 20. Terrace retaining walls 6’ in height and taller and plant the terraces. 21. Provide top-of-wall and bottom-of-wall elevations for the retaining walls. 22. Adjust the proposed grading to eliminate conflicts with wooded area to remain. Show adequate tree protection fencing on the grading, landscaping and erosion and sediment control plans. TABLE A This report is based on the following submittal items: Sheet # Drawing Name Drawing Date Sheet # Drawing Name Drawing Date C1 Cover Sheet 5/21/2018 C6 Road Details & Site Details 5/21/2018 C2 Existing Conditions & Demo Plan 5/21/2018 A100 Cover Sheet June 7 2018 C3 Site Plan 5/21/2018 5 of 6 Landscape Plan 5/21/2018 C4 Utility & Grading Plan 5/21/2018 A201 Site Sections June 7 2018 C5 Landscape Plan 5/21/2018 A202 Drive By Visibility from 250 June 7 2018 Option 1 Drawing Name Drawing Date Option 2 Drawing Name Drawing Date A101 View from Southwest June 7 2018 A101A View from Southwest June 7 2018 A102 View from Southeast June 7 2018 A102A View from Southeast June 7 2018 A103 View from Northwest June 7 2018 A103A View from Northwest June 7 2018 A104 View from Northeast June 7 2018 A104A View from Northeast June 7 2018 A105 Aerial View June 7 2018 A105A Aerial View June 7 2018 A501 Front (north) Elevation June 7 2018 A501A Front (north) Elevation June 7 2018 A502 Rear (south) Elevation June 7 2018 A502A Rear (south) Elevation June 7 2018 A503 Side Elevations June 7 2018 A503A Side Elevations June 7 2018 A406 Roof Plan (Option 1) June 7 2018 A406A Roof Plan (Option 2) June 7 2018 A401 First Floor Plan June 7 2018 A402 Second Floor Plan June 7 2018 A403 Typical (3-5) Floor Plan June 7 2018 A505 Building Sections June 7 2018 A507 Section Details June 7 2018