I can pencil you in for these dates; however, I think these are the main outstanding items that need resolution. (There
could be more.)
1. You will need to include residential units in the revised traffic study. I don’t see that you ever completed a
revised traffic study. Am I correct?
2. You need to provide a corrected table and other changes to the Code of Development to revise the changes in
use, square footage, etc.
3. The issue of cash proffers has never been resolved. I did not follow up with John Blair in April. I’ve just sent him
info and am waiting to hear back from him as to what we would advise, if anything.
All of these things will need to be in order before you submit on July 16.
Thanks.
Elaine
From: Kelsey Schlein <kelsey@shimp-engineering.com>
Sent: Friday, June 22, 2018 10:29 AM
To: Elaine Echols <EECHOLS@albemarle.org>
Cc: Justin Shimp <justin@shimp-engineering.com>
Subject: Re: ZMA201700005 Hollymead Town Center Area C, Blocks II, III, and VII
Hi Elaine,
We would like to request to resubmit prior to the July 16 which would put us at a public hearing date no sooner
than September 25. Please let me know if you need a letter or more formal correspondence to confirm this date.
Thank you!
Best,
Kelsey
On Thu, Jun 21, 2018 at 5:50 PM, Elaine Echols <EECHOLS@albemarle.org> wrote:
I will have to look into your questions before responding. For now, could you just send an email asking for indefinite
deferral? I will get you answers to your questions early next week after I’m able to pull the file and review my notes on
our last discussion. I will probably have to ask you some questions before I can answer your question below.
2
For now, I need to update CountyView with a status, so if you know a date you plan to resubmit, you can ask for a
deferral to a specific date. If not, an indefinite deferral is preferable so we can work together towards a conclusion.
Thanks.
Elaine
From: Kelsey Schlein <kelsey@shimp-engineering.com>
Sent: Thursday, June 21, 2018 5:44 PM
To: Elaine Echols <EECHOLS@albemarle.org>
Cc: Justin Shimp <justin@shimp-engineering.com>
Subject: ZMA201700005 Hollymead Town Center Area C, Blocks II, III, and VII
Hi Elaine,
Thank you for the follow up on HTC. I have a question concerning the possible increase in residential units
allowable that was discussed during the meeting that occurred in late March (I was not in attendance so please
correct me if I am referencing the wrong meeting). We would like to propose an increase in residential units
allowable because residential use would contribute to the community center design and use principles
designated for this area by serving as a compliment to the existing commercial and service areas.
If we were to propose an increase in the allowable residential units, are there applicable cash proffers for
residential units in Blocks II, III, and VII?
Thanks Elaine.
Best,
Kelsey