HomeMy WebLinkAboutWPO201800040 Review Comments WPO VSMP 2018-06-28
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Project: Flow Auto – VSMP Amendment
Project File Number: WPO2018000040
Plan preparer: Graham Murray, Collins Engineering, 200 Garrett Street, Suite, K,
Charlottesville, VA 22902 [graham@collins-engineering.com]
Owner or rep.: Don Speight /Flow Companies, 1425 Plaza Drive, Winston Salem, NC 27103
Plan received date: 22 May 2018
Date of comments: 28 June 2018
Reviewer: John Anderson
County Code section 17-410 and Virginia Code §62.1-44.15:34 requires the VSMP authority to act on any
VSMP permit by issuing a project approval or denial. This project is denied. The rationale is given in the
comments below. The application may be resubmitted for approval if all of the items below are
satisfactorily addressed. The VSMP application content requirements can be found in County Code section
17-401.
A. Stormwater Pollution Prevention Plan (SWPPP)
The SWPPP content requirements can be found in County Code section 17-405. A SWPPP must contain
(1) a PPP, (2) an ESCP, (3) a SWMP, and (4) any TMDL measures necessary.
1. Sect. 1, Registration statement: Revise to include e-mail address if DEQ may contact Operator via e-mail.
2. Sec. 1, Sign /date registration statement.
3. Sec. 4, 5: Update ESC, SWM, and SWPPP exhibit, with final revised versions, whe n available.
4. Sec. 9 –Sign Certification Statement
Note: Items 1, 2, and 4, should be closely reviewed with future SWPPP submittals.
SWM Plan
1. Please transfer VRRM .xls v. 3.0 redevelopment spreadsheet summary tab to plans, to more easily track
/review nutrient credit purchase requirements.
2. Ref. to VSMP Amendment indicates prior VSMP. Please provide reference to prior approved WPO#
(WPO200600089?). Area of disturbance does not qualify for VDEQ VAR10, since less than 1.0 Ac.
3. Contact Ana Kilmer, Albemarle Management Analyst to initiate nutrient credit purchase (0.78 lb). Please
do not purchase nutrient credits without consulting with Ms. Kilmer /Albemarle County.
4. Sheet 7, SWM Plan details: Please label drainage structures and pipes.
5. Sheet 7: Please label 2nd Access riser with steps into proposed UG detention (near inlet).
6. Sheet 7, text edits:
a. 66” weir plate detail: Please clarify 4.90’ is (top of) weir width. Also: please check base of weir
plate Elev. =402.30; ensure correct.
b. Please check /revise proposed overflow bypass pipe length and slope, for consistency; compare
SWM Plan detail with Str. 28 –Ex. 1 detail.
c. Str. 28 –Ex. 1: Please check Ex. 1 TP elevation.
7. Sheet 8-9, Foundation bedding preparation /Construction Loads: Provide bedding and depth of cover design
appropriate for typical construction loads. Albemarle understands contractor responsibility, but general
design guidance should inform design. While plan information may remain, revise design to provide
Engineering Review Comments
Page 2 of 3
specific bedding material and depth of bedding material, and to provid e sufficient cover for typical
construction loads above underground detention system. Note: Looking ahead, Albemarle welcomes CE
estimate of UG detention Mfr. material and installation expense to help improve bond estimate accuracy.
8. Sheet 8: Please provide profile of proposed 66” UG detention pipes, with inlet /outfall INV elevations.
9. Sheet 9: Similar to item #7, select round or square concrete perimeter for UG detention access openings
(MH cap detail). Arrange Notes 1.-9. to eliminate appearance notes 1.-6. may apply only to round option
plan view, and Notes 7.-9. may apply only to square option plan view (manhole cap detail).
10. Sheet 10
a. Geomembrane barrier: Show geomembrane in project-specific design profile.
b. Construction loading: Provide project-specific design. (Also, item #7 above)
c. Inspection: Engineering strongly recommends transfer SWM Facility As-built drawing
requirements from county website document to plans (link:
http://www.albemarle.org/upload/images/forms_center/departments/Community_Development/forms/Engine
ering_and_WPO_Forms/WPO_VSMP_Construction_Record_Drawings_Policy_23May2014.pdf )
d. Inspection /Maintenance: Revise to require SWM Facility (UG detention) inspection frequency not
less than once per year.
B. Pollution Prevention Plan (PPP)
The PPP content requirements can be found in County Code section 17 -404.
1. Included with SWPPP.
C. Erosion and Sediment Control Plan (ESCP)
Virginia Code §62.1-44.15:55 requires the VESCP authority to approve or disapprove an ESCP. This plan
is disapproved, and the reasons are provided in the comments below. The erosion control plan content
requirements can be found in County Code section 17-402.
Sheet 3:
1. Modify Temporary 18” Diversion Detail, for use on paved surface. Eliminate earth material. Specify stone
for berm. Specify impermeable fabric overlay (of berm) to deflect clean-side runoff to existing storm inlet.
Sheets 4, 5, 6
2. Revise notes to reflect Modified right-of-way diversion berm. May not be constructed using earth; use
stone.
3. Specify containment for fueling tank, sufficient to contain stored volume + 2- or 10-yr. rainfall event.
4. Revise note that reads Min. CE Entrance is 12 × 170’ (to read 70’). Provide wash rack note, since wash
rack required with paved CE. Note: No material may be tracked from this site onto U.S. Rt. 250.
5. Ensure all drainage structures and storm drain pipes are labeled, all sheets.
6. Provide drainage computations (inlets /pipes) with VSMP plan.
7. Temp stockpile Area measuring approximately 25’ × 35’ may be inadequate. Recommend re-evaluate size.
8. Sediment trap #1: Label SAF. Label floor dimensions. Label weir on sheet 5, as well as sheet 3.
9. Revise ref. to diversions and berms to specify non-earth, non-erodible (stone) material requirement.
10. Given timing /sequence of sediment trap #1 removal and paving, and the possibility that sediment-laden
runoff may reach the UG system, include note that Albemarle may require video of UG detention separate
and apart from VSMP As-built drawing requirements.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to discuss
this review.
Process
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate request
form and fee to the Department of Community Development. One of the plan reviewers will prepare estimates and
check parcel and easement information based on the approved plans. The County’s Management Analyst will
Engineering Review Comments
Page 3 of 3
prepare bond agreement forms, which will need to be completed by the owner and submitted along with cash,
certificates or sureties for the amounts specified. The agreements will need to be approved and signed by the
County Attorney and County Engineer. This may take 2-4 weeks to obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded. The
County’s Management Analyst or other staff will prepare the forms and check for ownership and signature
information. The completed forms will need to be submitted along with court recording fees.
Deed of Dedication of Stormwater Facility and Drainage Easements is required. Deed will reference book-page
of recorded Maintenance Agreement. Engineering prepares this document (Deed), using template and recorded
Maintenance Agreement information.
After bonding, agreements, and recorded deed are complete, the County can hold a pre-construction conference.
Applicants will need to complete the request for a pre-construction conference form, and pay the remainder of the
application fee. The form identifies the contractor and responsible land disturbed, and the fee remaining to be
paid. This will be checked by county staff, and upon approval, a pre-construction conference will be scheduled
with the County inspector. At the pre-construction conference, should everything proceed satisfactorily, a grading
permit will be issued by the County so that work may begin.
County forms can be found on the county website forms center under engineering;
http://www. albemarle. ore/deptforms. asp?department=cdenywpo
If you have any questions, please contact me either by email (janderson2@albemarle.org) or by phone at
434.296-5832 ext. 3069. Thank you.
J. Anderson, Engineering Division
WPO201800040_Flow Auto VSMP Amendment_062818.doc