HomeMy WebLinkAboutWPO201700045 Inspection 2018-06-15COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road
Charlottesville, Virginia 22902-4596
Phone (434) 296-6832 Fax (434) 972-4126
VSMPNESCP PERMIT SITE INSPECTION REPORT
COVERAGE & POSTING REQUIREMENTS IYesl No IN/AI Reviewed during re -Inspection? ❑Yes []No
Construction site has permit coverage? (Va. Code §62.1- 44.15:34.A)
(9VAC25-S70-310)(Alb. Co. Code §17-300, 17-302)
13applicablIre",
A copy of the notice of coverage letter is posted conspicuously near the
main entance of the construction activity? (CGP Part II.C)
Notice of the location of the SWPPP is posted near the site's entrance, if
and information for public access is provided? (9VAC25-870-
54.G)(CGP Part Il D.2 & 3)
SWPPP AVAILABILITY AND CONTENTS jYes1 No �N/A� Reviewed during re -inspection? ❑Yes ❑No
4 The SWPPP is on -site or made available during the inspection? (CGP
Part !I D.1 & 2)(9VAC25-870-54.G)
5 The SWPPP contains a signed copy of the registration statement?
(CGP Part 11 A.1.a)
B The SWPPP includes, upon receipt, a copy of the notice of coverage
letter and the CGP? (CGP Part II A.1.b & c)
Page 1 of 7
• The SWPPP includes a narrative description of the nature of the
7 construction activity, including the function of the project? (CGP Part II
A.1.d)
The SWPPP includes a legible site plan identifying all appropriate
8 measures and that includes the locations of support activities and the
onsite rain gauge, when applicable? (CGP Part II A.1.e(1-7))
The SWPPP contains the name, phone number and qualifications of
9 "Qualified Personnel" conducting inspections? (CGP Part 11 A.6)
;concem,
SWPPP contains an approved erosion and sediment control plan?
C25-870-54.B)(CGP Part iI.A.2)
WPPP contains an approved stormwater management plan or an
ing construction site has a stormwater management plan that
res compliance with the water quality and quantity requirements?
C25-870-54.C)(CGP Part FI.A.3) Technical Criteria ILB ❑ ILCWPPP contains an adequate pollution prevention plan? (9VAC25-
4.D)(CGP Part II.A.4)
WPPP identifies impaired water(s), approved TMDL, poilutant(s) of
m, exceptional waters and the additional controls measures
able? (9VAC 25-870-54.E)(CGP Part IIA.S (a-b))
14 Delegation of Authority is provided and signed in accordance with Part III
K? (CGP Part II A.7)
15 The SWPPP is signed and dated in accordance with Part III K? (CGP Pap
II A.8)
SWPPP AMENDMENTS, MODIFICATIONS AND UPDATES
Is the SWPPP being amended whenever there is a change in the design,
16 onstruction, operation, or maintenance that has a significant effect on the
ischarge of pollutants to surface waters? (CGP Part 11 B(1))(9VAC25-870-
4.G)
Has the SWPPP been amended if inspections or investigations by the
17 perator's qualified personnel, or by local, state or federal officials find that
xisting control measures are ineffective in minimizing pollutants in
ischarges? (CGP Part 11 B(2))(9VAC25-870-54.G)
18 ontractor(s) that will implement and maintain each control measure are
identified? (CGP Part 11 B(3))(9VAC25-870-54.G)
Have there been updates to the SWPPP when any modifications to its
Implementation have occurred, including a record of dates when major
19 rading activities occur, construction activities temporarily or permanently
ase on a portion of the site or stabilization measures are initiated? (CGP
Part 11 B.4(a))(9VAC25-870-54.G)
20 Is there documentation in the SWPPP of replaced or modified controls?
(CGP Part II B.4(b))(9VAC25-870-54.G)
21 Is the SWPPP updated to indicate areas that have reached final
tabilization? (CGP Part II BA(c))(9VAC25-870-54.13)
Is the SWPPP updated to indicate properties that are no longer under the
22 egal control of the operator and the dates on which the operator no longer
Pad legal control over each property? (CGP Part 11 B.4(d))(9VAC25-870-
123lu
.G)
es the SWPPP identify the date of any prohibited discharges, the
me released, actions taken to minimize the impact of the release and
nsures taken to prevent the recurrence of any prohibited discharge?
GP Part 11 B.4(e-0) (9VAC25-870-54.G)
24 mendments, modifications, or updates to the SWPPP are signed in
accordance with Part Ili K? (CGP Part II B(S))(9VAC25-870-54.G)
INSPECTIONS AND CORRECTIVE ACTIONS
No IN/AI Reviewed during inspection? E]Yes [:]No
No JN/A+ Reviewed during inspection? ❑Yes E]No
Page 2 of 7
25 1 Inspections required by the SWPPP are conducted at the required
frequency, including a modified frequency for impaired water(s), approved
TMDL(s), and exceptional waters when applicable? (CGP Part II F (2))
(CGP Part Il A.5.b.3)
26 Inspection reports are completed and signed in accordance with CGP
Part II F (3-4)? (CGP Part If F (3-4))
27 Corrective actions are taken consistent with the requirements of the
CGP? (CGP Part 11 G(1-2))
ESC AND SWM PLAN IMPLEMENTATION IYesJ No
28 Have stream buffers and steep slopes been protected as shown on the
plan?
Sequencing of the project is implemented in accordance with the
29 approved erosion and sediment control plan and stormwater managemen
plans? (9VAC25,870-54.B and C)
Have all denuded areas requiring temporary or permanent stabilization
peen stabilized, and have stabilization requirements for impaired waters,
30 approved TMDL(s), pollutants of concern and exceptional waters, when
applicable, been met? (9VAC 25-840-40.1) (9VAC25-870-54.B) (9VAC25-
880-60) (CGP Part I F.1(a)) (CGP Part II A.5.b(1)) (CGP Part 11 A.2.c (8))
(CGP 11 E(1-2))
Are soil stockpiles adequately stabilized with seeding and/or protected
31 with sediment trapping measures? (9VAC 25-840-40.2) (CGP Part 11
A.2(c)) (9VAC25-870-54.B)
A permanent vegetative cover has been established that is uniform,
32 mature enough to survive and will inhibit erosion? (9VAC 25-840-40.3)
(CGP Part II A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.B)
Have sediment trapping facilities been constructed as the first step in land
33 disturbance activities? (9VAC 25-840-40.4) (CGP Part 11 A.2(c)) (CGP II
Have earthen structures been stabilized immediately after installation?
34 (9VAC 25-840-40.5) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54.B)
Are sediment traps and basins installed in accordance with MS-6 and the
35 approved plan? (9VAC 25-840-40.6) (CGP Part 11 A.2.c (9)) (CGP Part II
A.2(c)) (CGP Il E(1-2)) (9VAC25-870-54.13)
Are finished cut and fill slopes adequately stabilized to prevent or correct
36 excessive erosion? (9VAC 25-840-40.7) (CGP Part 11 A.2(c)) (CGP 11 E(1-
Is concentrated runoff down cut or fill slopes contained in an adequate
37
permanent or temporary structure? (9VAC 25-840-40.8) (CGP Part II
A.2(c)) (CGP 11 E(1-2)) (9VAC25-870-54.B)
Is adequate drainage or other protection provided for water seeps?
38
(9VAC 25-840-40.9) (CGP Part II A.2(c)) (CGP II E(1-2)) (9VAC25-870-
54. B)
Do all operational storm sewer inlets have adequate inlet protection?
39
(9VAC 25-840-40.10) (CGP Part II A.2(c)) (CGP If E(1-2)) (9VAC25-87Q-
54.8)
Are stormwater conveyance channels adequately stabilized with channel
40
lining and/or outlet protection? (9VAC 25-840-40.11) (CGP Part II A.2(c))
(CGP II E(1-2)) (9VAC25-870-54.13)
Is in -stream construction conducted using measures to minimize channel
41
damage? (9VAC 25-840-40.12) (CGP Part 11 A.2(c)) (CGP 11 E(1-2))
(9VAC25-870-54.8)
Are temporary stream crossings of non -erodible material installed where
42
applicable? (9VAC 25-840-40.13) (CGP Part 11 A.2(c)) (CGP II E(1-2))
(9VAC25-870-54.B)
43
Is necessary restabilization of in -stream construction complete? (9VAC
25-840-40.15) (CGP 11 E(1-2)) (9VAC25-870-54.B)
Reviewed during inspection? ❑Yes []No
Page 3 of 7
Are utility trench operations conducted and stabilized in accordance with
44 1 MS-16? (9VAC 25-840-40.16) (CGP Part II A.2(c)) (CGP 11 E(1-2))
(9VAC25-870-54. B)
soil and mud kept off paved or public roads to minimize the transport
45TAre
f sediment? (9VAC 25-840-40.17) (CGP Part II A.2(c)) (CGP II E(1-2))
9VAC25-870-54. B)
Have all temporary control structures that are no longer needed been
46 removed and disturbed soil resulting from their removal permanently
stabilized? (9VAC 25-840-40.18) (CGP Part II A.2(c)) (CGP 11 E(1-2))
(9VAC25-870-54. B)
Are properties and waterways downstream from development adequately
47 protected from erosion, sediment and damage in accordance with the
standards and criteria specified by 9VAC25-840.19(a-n)? (9VAC 25-840-
40.19(a-n))
48 Permanent control measures included in the SWPPP are in place?
(9VAC25-870-54.C) (9VAC25-880-60) (CGP Part II F.1(a))
POLLUTION PREVENTION PLAN IMPLEMENTATION
Practices are in place to prevent and respond to leaks, spills, and other
releases including (i) procedures for expeditiously stopping, containing,
49 and cleaning up spills, leaks, and other releases; and (ii) procedures for
reporting leaks, spills, and other releases in accordance with Part III G?
(CGP Part II A.4.e(1))(9VAC25-870-56)
Practices are in place to prevent the discharge of spilled and Leaked fuels
50 and chemicals from vehicle fueling and maintenance activities? (CGP Part I I
A A _-I ,w. .. ,..... ..__ __.
Practices are in place to prevent the discharge of soaps, solvents,
51 detergents, and wash water from construction materials, including the
clean-up of stucco, paint, form release oils, and curing compounds? (CG
Part 11 A.4.e(3))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from vehicle
52 and equipment washing, wheel wash water, and other types of washing?
(CGP Part 11 A.4.e(4))(9VAC25-870-sr;)
53 Concrete wash water is directed into a leak -proof container or leak -proof
settling basin? (CGP Part 11 A.4.e(5))(9VAC25-870-56)
Practices are in place to minimize the discharge of pollutants from
54 storage, handling, and disposal of construction products, materials, and
was
(CGP Part 11 A.4.e(6))(9VAC25-870-56)
Practices are in place to prevent the discharge of fuels, oils, and other
55 petroleum products, hazardous or toxic wastes, and sanitary wastes?
(CGP Part II A.4.e(7)(9VAC25-870-56)
Practices are in place to minimize any other discharge from the potential
56 pollutant -generating activities not addressed above, when applicable?
(CGP Part 11 A.4.e(8))(9VAC25-870-56)
Inspector Signature:
No'N/AJ Reviewed during inspection? ❑Yes ❑No
Page 4 of 7