HomeMy WebLinkAboutSDP201800052 Review Comments Initial Site Plan 2018-08-17County of Albemarle Department of Community Development Memorandum To: Megan Nedostup From: Emily Cox Date: 17 Aug 2018 Subject: Brookhill —Sections 9, 10 & 11 - ISP (SDP201800052) The initial site plan for Brookhill —Sections 9-11 has been reviewed by Engineering. The following comments will need to be addressed before approval: 1. WPO Plan must be approved before final site plan can be approved. 2. Road Plan must be approved before final site plan can be approved. Road plan must include all roads encompassed by this site plan. There appears to be a road between sections 4A & 8A as well as through 8A. 3. VDOT approval is necessary before final site plan can be approved. 4. Ensure all critical slopes, buffers, etc. are shown as approved on ZMA 2015-007 on all applicable sheets. 5. Ensure the accurate FEMA 100 year floodplain is shown. The ZMA appeared to show the 500 year. 6. Note 1 on Sheet 4 says no floodplain exists on site, however, a floodplain is shown. Please clarify and correct. 7. Show how the proposed impacts to the steep slopes and Greenway compare to the approved ZMA. 8. The proposed greenway should not be located on any lots. Per the Code of Development (COD), page 18, the Greenway area will be a public space, dedicated to Albemarle County. Also, the Greensapce includes the Greenway, and the Greenway shall be located outside of private lots and right -of --way. 9. The 100' buffer is not existing, it is proposed as greenway/open space with the ZMA. Please label appropriately. 10. Show all proposed parking space dimensions. 11. Show top and bottom elevations of proposed retaining walls. Note that per COD, Page 23, the maximum height is six feet. 12. The County is not aware of anything that has be submitted regarding the preserved steep slopes. The note, "limits of existing...." is not accurate. Show the preserved slopes and their impacts as shown on the approved on the ZMA. New topographic information can be provided for evaluation, as outlined in county code, 30.7.4 b-1-h. However, this must be signed and sealed by a surveyor. 13. Water quality and quantity requirements will be fully evaluated with the VSMP Plan submission. Please note that all concentrated outfalls must be analyzed to comply with state requirements. Also, water quality summary table for overall Brookhill Development must be provided. Please reference proposed pond as pond 12 from the approved master stormwater management plan.