Subject: Brookhill —Block 8B - ISP (SDP201800054)
The initial site plan for Brookhill —Block 8B has been reviewed by Engineering. The following comments
will need to be addressed before approval:
1. WPO Plan must be approved before final site plan can be approved.
2. Road Plan must be approved before final site plan can be approved. Road plan must
include all roads encompassed by this site plan. There appears to be a road between
sections 4A & 8A as well as through 8A.
3. VDOT approval is necessary before final site plan can be approved.
4. The minimum ROW (or easement width) is 30' per the Design Standards Manual.
VDOT subdivision street design guide —Appendix b, section B-4-B-3-d states that
the pavement width can be reduced to 22ft, but the right -of --way must still be 30
feet.
5. Ensure all critical slopes, buffers, etc. are shown as approved on ZMA 2015-007 on all
applicable sheets.
6. Ensure the accurate FEMA 100 year floodplain is shown. The ZMA appeared to show the
500 year. Also, Note 4 states there is not floodplain, however there is floodplain shown on
the plans.
7. Show how the proposed impacts to the steep slopes and Greenway compare to the
approved ZMA.
8. On sheet 4, an approved VSMP plan is referenced. Provide the approved plan #and
facilitiy ID's that are proposed to be modified or removed.
9. Show all proposed parking space dimensions (at each parking area).
10. Show top and bottom elevations of proposed retaining walls. Note that per COD, Page 23,
the maximum height is six feet.
11. Please label contour elevations.
12. 2:1 Slopes should be avoided wherever possible. The 2:1 slopes behind lots 1-15 are not
desirable.
13. Water quality and quantity requirements will be fully evaluated with the VSMP Plan
submission. Please note that all concentrated outfalls must be analyzed to comply with
state requirements. Also, water quality summary table for overall Brookhill Development
must be provided.