HomeMy WebLinkAboutSUB201600131 Review Comments Road Plan and Comps. 2016-12-05Short Review Comments Report for:
SUB201600131
SubApplication Type:
Avinity Phase IV - Road Plans
New Private Use Road Plan
Date Completed:08/17/2016
Reviewer:Matthew Wentland CDD Engineering
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:07/12/2016
Reviewer:Adam Moore VDOT
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:
Reviewer:Jeremy Lynn ACSA
Review Status:Pending
Reviews Comments:
Division:
Date Completed:07/23/2016
Reviewer:Robbie Gilmer Fire Rescue
Review Status:No Objection
Reviews Comments:Based on plans dated 6/22/16.
No comments or objections.
Division:
Date Completed:08/17/2016
Reviewer:Megan Nedostup CDD Planning
Review Status:Requested Changes
Reviews Comments:
Division:
Date Completed:12/05/2016
Reviewer:Matthew Wentland CDD Engineering
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:11/08/2016
Reviewer:Adam Moore VDOT
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:11/15/2016
Reviewer:Jeremy Lynn ACSA
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:11/20/2016
Reviewer:Robbie Gilmer Fire Rescue
Review Status:No Objection
Reviews Comments:Based on plans dated 9/29/16.
No comments or objections.
Division:
Page:1 of 2 County of Albemarle Printed On:August 29, 2018
No comments or objections.
Date Completed:10/24/2016
Reviewer:Megan Nedostup CDD Planning
Review Status:No Objection
Reviews Comments:
Division:
Date Completed:12/05/2016
Reviewer:Matthew Wentland CDD Engineering
Review Status:See Recommendations
Reviews Comments:
Division:
Page:2 of 2 County of Albemarle Printed On:August 29, 2018
Charles A. Kilpatrick, P.E.
Commissioner
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper Virginia 22701
November 8, 2016
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
Attn: Matthew Wentland
Re: Avinity Phase IV — Road Plan
SUB -2016-00131
Review #2
Dear Mr. Wentland:
The Department of Transportation, Charlottesville Residency Transportation and Land Use
Section, has reviewed the above referenced plan as submitted by Collins Engineering, most
recently revised 29 September 2016. This plan proposes private roads that will connect to an
existing private road network; therefore, VDOT has no objection.
If further information is desired please contact Justin Deel at (434) 422-9894.
Sincerely,
Adam J. Moore, P.E.
Area Land Use Engineer
Charlottesville Residency
VirginiaDOT.org
WE KEEP VIRGINIA MOVING
COUNTY OF ALBEMARLE
Department of Community Development
401 McIntire Road, Room 227
Charlottesville, Virginia 22902-4596
Phone (434) 296-5832 Fax (434) 972-4126
Project title:
Project file number:
Plan preparer:
Owner or rep.:
Date Received:
Date of comments:
Reviewer:
Road and Drainage plan review
Avinity Phase IV - Road Plans
SUB201600131
Collins Engineering
Avon Properties LLC
22 June 2016
17 August 2016
Matt Wentland
Scott,
We have reviewed the plans and have the following comments:
Engineering
1. The pond shown on the plan does not appear to be the same as the most recently approved WPO
submittal. Please show the approved pond, grey out the pond, or submit an amendment to the
WPO for the new pond design.
2. Provide drainage calculations for the proposed stormwater pipes and inlets. Also show and
dimension the drainage easements.
3. Show the location of the street sign(s).
ACSA and Fire Rescue have no objection to the plans. VDOT comments were sent on 7/12/16 and
Planning comments are attached.
Engineering plan review staff are available from 2-4 PM on Thursdays, should you require a meeting to
discuss this review.
Process;
After approval, plans will need to be bonded. The bonding process is begun by submitting a bond estimate
request form and fee to the Department of Community Development. One of the plan reviewers will
prepare estimates and check parcel and easement information based on the approved plans. The County's
Management Analyst will prepare bond agreement forms, which will need to be completed by the owner
and submitted along with cash, certificates or sureties for the amounts specified. The agreements will need
to be approved and signed by the County Attorney and County Engineer. This may take 2-4 weeks to
obtain all the correct signatures and forms.
Stormwater Management Facilities Maintenance agreements will also need to be completed and recorded.
The County's Management Analyst or other staff will prepare the forms and check for ownership and
Engineering Review Comments
Page 2 of 2
signature information. The completed forms will need to be submitted along with court recording fees.
After bonding and agreements are complete, county staff will need to enter project information in a DEQ
database for state application processing. DEQ will review the application information based on local
VSMP authority approval. At this time, the DEQ portion of the application fees will need to be paid
directly to the state. For fastest processing, this is done electronically with the emails provided on the
application. DEQ should notify applicants with instructions on how to pay fees. When DEQ approves the
application, they will issue a permit coverage letter. This should be copied to the county.
After DEQ coverage is issued, via the coverage letter, the County can hold a pre -construction conference.
Applicants will need to complete the request for a pre -construction conference form, and pay the remainder
of the application fee. The form identifies the contractor and responsible land disturber, and the fee
remaining to be paid. This will be checked by county staff, and upon approval, a pre -construction
conference will be scheduled with the County inspector. At the pre -construction conference, should
everything proceed satisfactorily, a joint VSMP and grading permit will be issued by the County so that
work may begin.
County forms can be found on the county website forms center under engineering;
ht!p://www.albemarle.or,-/deptforms.asp?department=cden,izwpo
If you have any questions or concerns, please contact me either by email (mwentland@albemarle.org) or
by phone at 434-296-5832 ext. 3458.
Sincerely,
Matt Wentland, P.E.
Civil Engineer H
File: SUB201600131 Avinity Phase IV Road Plans review comments 08-17-16.doc
County of Albemarle
Department of Community Development
Memorandum
To: Matt Wentland- Engineering
From: Megan Yaniglos, AICP- Principal Planner
Division: Planning Services
Date: August 17, 2016
Subject: SUB -2016-131 Avinity Phase IV- Road Plans
1. A path needs to be provided and bonded off of the parking/street as shown on
the approved rezoning application plan (ZMA2013-016).
/ 1
"STINGACCE$SPOINTr/ !+ ! �! I J lJ 1 ! J r ♦\ � � `
-�� TCdjPROP
93LDREZONING % r / I &OtWP�40 AY ♦\
J NNECTID T`D WiN TY IN F�1571NG-
r ff
'WATERLINE '~
wr
PROPOSED ARE)
YOT
�PA55111E RECREJ
~'I •�" •� T + : f IVEaMASSIVE~
,.. I T f""[ • "� , - j� i 1 ReCREATI.ONAL
..AREA'
car
I• Ill ,
ll I�III III
'AVINITY ISLOG
'
111111 IIIj ItA ,1 PROPOSER
I + ♦ TOWNHOUSES+ r r
L ! 1J �♦ IN LIEU OF r 1 + + EX SWM FACILITY
p �'
f (I♦+ !' +!I �!1l�I : -C1.
r `I r'
1 ! FOR AVINITY I TO BEEN LARGED TO
A /l �ARTMET
THIS SIZE TO ACCOMMODATE THE
AVINITY Il STORMWATER
MANAGEMENT
Yr.l �STRIREDSt'IL
2. Street trees should be shown and bonded with the road plans. A minor
amendment (SDP2015-026) was approved for this area, however it does not
appear that the street trees were bonded with that amendment.
1
uRms
{l'lP.F
LD APARTM@Mf
MMA SUIUGN6
RAPA
ZrREAM C7
Please contact Megan Yaniglos at the Department of Community Development 296-
5832 ext. 3004 for further information.
2
COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATION
1601 Orange Road
Culpeper Virgina 22701
Charles A. Kilpatrick, P.E.
Commissioner
July 12, 2016
County of Albemarle
Department of Community Development
401 McIntire Road
Charlottesville, VA 22902
Attn: Matthew Wentland
Re: Avinity Phase N — Road Plan
SUB -2016-00131
Review #1
Dear Mr. Wentland:
The Department of Transportation, Charlottesville Residency Transportation and Land Use
Section, has reviewed the above referenced plan as submitted by Collins Engineering, dated 22
June 2016. This plan proposes private roads that will connect to an existing private road network;
therefore, VDOT has no objection.
If further information is desired please contact Justin Deel at (434) 422-9894.
Sincerely,
Adam J. Moore, P.E.
Area Land Use Engineer
Charlottesville Residency
VirginiaDOT.org